ILLINOIS POLLUTION CONTROL BOARD
May 1, 2003
J & C CENTRAL, INC.,
Petitioner,
v.
ILLINOIS ENVIRONMENTAL
PROTECTION AGENCY,
Respondent.
)
)
)
)
)
)
)
)
)
)
PCB 03-206
(UST Appeal)
(90-Day Extension)
ORDER OF THE BOARD (by T.E. Johnson):
On April 28, 2003, the parties timely filed a joint notice to extend the 35-day period
within which J & C Central, Inc. (J & C Central) may appeal an April 4, 2003 determination of
the Illinois Environmental Protection Agency (Agency).
See
415 ILCS 5/40(a)(1) (2002); 35 Ill.
Adm. Code 105.402, 105.406. At issue is the Agency’s approval of the payment of corrective
action costs, with deductions, for J & C Central’s leaking underground petroleum storage tank
facility located at 586 Crescent Boulevard, Glen Ellyn, DuPage County. The Board extends the
appeal period until August 7, 2003, as the parties request.
See
415 ILCS 5/40(a)(1) (2002); 35
Ill. Adm. Code 105.406. If J & C Central fails to file an appeal on or before that date, the Board
will dismiss this case and close the docket.
IT IS SO ORDERED.
I, Dorothy M. Gunn, Clerk of the Illinois Pollution Control Board, certify that the Board
adopted the above order on May 1, 2003, by a vote of 7-0.
Dorothy M. Gunn, Clerk