    CITY OF GALENA
    V.
    )
    PCB 72—122
    ENVIRONMENTAL PROTECTION AGENCY
    OPINION
    AND
    INTERIM ORDER:
    On March
    29, 1972,
    the City of Galena filed a petition with
    the Board seeking a variance from the Board with regard to the
    Open turning Regulations.
    The City seeks to open burn piles of
    brush obtained from clearing a 22 acre area near the Galena River.
    The petition recites that to otherwise dispose of the piles of
    brush would constitute
    a financial hardship to the City; however,
    the petition does not recite what alternatives to open burning
    of the piles of brush the City investigated and the costs of those
    alternatives.
    Under normal circumstances
    if
    a petition does not
    contain such relevant information, it would be dismissed and the
    petitioner would be required to file a new petition with the new
    information if it wanted a variance.
    In this case, however, we will
    allow
    the petitioner 15 days to amend its petition to include the
    necessary information on alternative means
    of disposal of the piles
    of brush
    and
    the
    cost
    of those means.
    If the petitioner fails
    to
    give the Board adequate additional information within that time,
    the
    petition will be dismissed.
    If the petitioner does give the Board
    the necessary information, then we will await the Agency recommen-
    dation before deciding whether a variance should be granted.
    It is so ordered.
    I, Christan L. Moffett, Clerk of the Pollution Control Board,
    ce~ifythat the above Opinion and Interim Order was adopted this
    ‘f
    I
    day of April,
    1972, by
    a vote of ~~-o
    4--
    167

    Back to top