ILLINOIS POLLUTION CONTROL BOARD
    July 19, 1973
    ENVIRONMENTAL PROTECTION AGENCY
    #72-468
    v.
    ELIZABETH STREET FOUNDRY,
    INC.
    ORDER
    OF
    THE
    BOARD
    (BY SAMUEL T.
    LAWTON, JR.):
    On
    April
    17,
    1973, we entered an Order in the above-captioned
    proceeding directing that prior to June 17,
    1973, Respondent cease
    and desist its pollutional discharge and submit a program of com-
    pliance prior to said date.
    The order directed that the parties
    conduct such testing as
    is necessary prior to June 17, to ascertain
    that Respondent had complied with all relevant regulations with
    respect to the control of air pollution.
    Subsequent thereto, Respondent filed a motion stating that the
    presence of a spark arrester created difficulty in testing the
    emissions:
    that testing before the spark arrester failed
    to take
    into consideration the discharges diminished by said
    devices and t~tsampling above the stack would be the testing
    of the ambient air to which results the testing companies would
    not certify.
    Respondent stated that it proposes to install an
    afterburner and requested that our order be modified to permit
    such installation, that the stack test be taken subsequent
    to the
    completion of the installation and that Respondent continue to
    operate while proceeding with the afterburner installation and
    tests.
    We indicated in an order of June
    14, 1973 that we were not
    unfavorably disposed to the request but that Respondent had failed
    to set forth a time schedule for compliance,
    as previously directed,
    and accordingly,
    denied the motion and directed that Respondent
    file its proposed schedule of installation and testing within 10
    days, pursuant to which we would enter such further order as might
    be appropriate.
    8—527

    Respondent has filed a petition in response
    to
    our
    June
    14,
    1973 Order, stating that Respondent had contacted various manufac-
    turers of gas—fired afterburners to obtain estimates of delivery
    dates and that inquiry made of Peoples Gas, Light and Coke Company
    indicated that gas pressure of the amount needed for operation of the
    type of afterburner required, would not be available.
    Inquiry was
    next made with
    a view of obtaining a gas booster pump which Respon-
    dent now indicates has been made available.
    An afterburner has
    been ordered with delivery schedule of six weeks after approval
    of shop drawings, which will be ready on July 20, 1973.
    Installa-
    tion and testing of the equipment is anticipated to take two weeks
    for completion.
    Stack testing would commence immediately after
    installation.
    Respondent
    asks
    that we permit the installation of
    the
    afterburner
    and
    gas
    booster
    pump
    and
    testing
    in
    accordance
    with
    the schedule provided.
    If the contemplated program is implemented as Respondent repre-
    sents, the equipment would be delivered by approximately August
    31,
    1973 and installed by September 14,
    1973.
    Stack testing would
    commence immediately thereafter.
    In view of the representations of the Respondent and the
    apparent good faith efforts to achieve compliance, we amend our
    April
    17,
    1973 order to grant Respondent until October
    1, 1973 to
    complete its program of installation, testing and compliance pur-
    suant to its proposed schedule and direct that all provisions
    of
    our earlier order be achieved by said date and that Respondent
    cease and desist all violation of the relevant Regulations and the
    Environmental Protection Act by October
    1, 1973.
    IT
    IS SO
    ORDERED.
    I,
    Christan Moffett, Clerk of the Pollution Control Board, certify
    that
    the
    above
    Order
    was
    adopted
    on
    the
    f1~
    day of July,
    1973,
    byavoteof
    ~
    to
    ______
    —2—
    528

    Back to top