ILLINOIS POLLUTION CONTROL BOARD
July 19, 1973
ENVIRONMENTAL PROTECTION AGENCY
#72-468
v.
ELIZABETH STREET FOUNDRY,
INC.
ORDER
OF
THE
BOARD
(BY SAMUEL T.
LAWTON, JR.):
On
April
17,
1973, we entered an Order in the above-captioned
proceeding directing that prior to June 17,
1973, Respondent cease
and desist its pollutional discharge and submit a program of com-
pliance prior to said date.
The order directed that the parties
conduct such testing as
is necessary prior to June 17, to ascertain
that Respondent had complied with all relevant regulations with
respect to the control of air pollution.
Subsequent thereto, Respondent filed a motion stating that the
presence of a spark arrester created difficulty in testing the
emissions:
that testing before the spark arrester failed
to take
into consideration the discharges diminished by said
devices and t~tsampling above the stack would be the testing
of the ambient air to which results the testing companies would
not certify.
Respondent stated that it proposes to install an
afterburner and requested that our order be modified to permit
such installation, that the stack test be taken subsequent
to the
completion of the installation and that Respondent continue to
operate while proceeding with the afterburner installation and
tests.
We indicated in an order of June
14, 1973 that we were not
unfavorably disposed to the request but that Respondent had failed
to set forth a time schedule for compliance,
as previously directed,
and accordingly,
denied the motion and directed that Respondent
file its proposed schedule of installation and testing within 10
days, pursuant to which we would enter such further order as might
be appropriate.
8—527
Respondent has filed a petition in response
to
our
June
14,
1973 Order, stating that Respondent had contacted various manufac-
turers of gas—fired afterburners to obtain estimates of delivery
dates and that inquiry made of Peoples Gas, Light and Coke Company
indicated that gas pressure of the amount needed for operation of the
type of afterburner required, would not be available.
Inquiry was
next made with
a view of obtaining a gas booster pump which Respon-
dent now indicates has been made available.
An afterburner has
been ordered with delivery schedule of six weeks after approval
of shop drawings, which will be ready on July 20, 1973.
Installa-
tion and testing of the equipment is anticipated to take two weeks
for completion.
Stack testing would commence immediately after
installation.
Respondent
asks
that we permit the installation of
the
afterburner
and
gas
booster
pump
and
testing
in
accordance
with
the schedule provided.
If the contemplated program is implemented as Respondent repre-
sents, the equipment would be delivered by approximately August
31,
1973 and installed by September 14,
1973.
Stack testing would
commence immediately thereafter.
In view of the representations of the Respondent and the
apparent good faith efforts to achieve compliance, we amend our
April
17,
1973 order to grant Respondent until October
1, 1973 to
complete its program of installation, testing and compliance pur-
suant to its proposed schedule and direct that all provisions
of
our earlier order be achieved by said date and that Respondent
cease and desist all violation of the relevant Regulations and the
Environmental Protection Act by October
1, 1973.
IT
IS SO
ORDERED.
I,
Christan Moffett, Clerk of the Pollution Control Board, certify
that
the
above
Order
was
adopted
on
the
f1~
day of July,
1973,
byavoteof
~
to
______
—2—
—
528