| | | | |
- Unless specified otherwise, all terms shall have the meanings set forth in the Environmental Protection Act.
|
For purposes of this Part and 35 Ill. Adm. Code 660, the following definitions apply: |
| | | | |
"Act" means the Environmental Protection Act (Ill. Rev. Stat. 1985, ch. 111 ½, pars. 1001 et seq., as amended).
|
| | | | |
"Addenda" means written or graphic instruments issued prior to the execution of the agreement which modify or interpret the contract documents, drawings, and specifications, by additions, deletions, clarifications, or corrections.
|
| | | | |
"Agency" means the Illinois Environmental Protection Agency.
|
| | | | |
"Applicant" means grant applicant.
|
| | | | |
"Bid" means the offer or proposal of the bidder submitted on the prescribed form setting forth the prices for the work to be performed.
|
| | | | |
"Bidder" means any person, firm or corporation submitting a bid for the work.
|
| | | | |
"Change order" means a written order to the contractor authorizing an addition, deletion or revision in the work within the general scope of the contract documents, or authorizing an adjustment in the contract price or contract time.
|
| | | | |
"Construction" means any one or more of the following: surveys, designs, plans, working drawings, specifications, erection, building, acquisition (of equipment, supplies, or components), alteration, remodeling, improvement, or extension of treatment works, or the inspection or supervision of any of the foregoing items.
|
| | | | |
"Contract documents" means the contract, including advertisement for bid, information for bidders, bid, bid bond, agreements, payment bond, performance bond, notice of award, notice to proceed, change order, drawings, specifications, and addenda.
|
| | | | |
"Contract price" means the total monies payable to the contractor under the terms and conditions of the contract documents.
|
| | | | |
"Contract time" means the number of calendar days stated in the contract documents for the completion of all the work including punch list items.
|
| | | | |
"Contractor" means the person, firm or corporation with whom the owner has executed a subagreement.
|
| | | | |
"Director" means the Director of the Illinois Environmental Protection Agency.
|
| | | | |
"Drawings" means the part of the contract documents which show the characteristics and scope of the work to be performed and which have been prepared by or approved by the engineer based upon the engineer's professional judgement as defined in this subsection.
|
| | | | |
"Engineer" means the person, firm or corporation named as such in the contract documents.
|
| | | | |
"Field order" means a written order effecting a change in the work not involving an adjustment in the contract price or an extension of the contract time, issued by the engineer to the contractor during construction.
|
| | | | |
"Force account work" means work performed or a purchase made by a grantee in lieu of such work being performed or purchase being made by a person other than the grantee.
|
| | | | |
"Generally accepted accounting principles" means procedures adopted by the Financial Accounting Standards Board (High Ridge Park, Stamford, Connecticut; June 1, 1987). (This incorporation contains no further amendments or editions.)
|
| | | | |
"Generally accepted auditing standards" means procedures adopted by the Auditing Standards Board (Codification of Statements on Auditing Standards; 1211 Avenue of the Americas, New York City, New York; January 1986) (This incorporation contains no further amendments or editions).
|
| | | | |
"Grant" means a grant under Section 4(v) of the Act.
|
| | | | |
"Grant agreement" means the written agreement between the Agency and a grant recipient (applicant) in which the terms and conditions governing the grant are stated and agreed to by both parties.
|
| | | | |
"Grant applicant" means the unit of local government which has applied for a grant under Section 4(v) of the Act.
|
| | | | |
"Grantee" or "Owner" means the unit of local government which has received a grant under Section 4(v) of the Act.
|
| | | | |
"Grant procedures" means the procedures for issuing grants under Section 4(v) of the Act.
|
| | | | |
"Initiation of operation" means the date specified by the grant recipient on which use of the project begins for the purposes that it was planned, designed, and built.
|
| | | | |
"Notice of award" means the written notice of the acceptance of the bid from the owner to the successful bidder.
|
| | | | |
"Notice to proceed" means written communications issued by the owner to the contractor authorizing him to proceed with the work and establishing the date of commencement of the work.
|
| | | | |
"Professional judgement" means the use of those engineering principles and practices used by engineers when fulfilling their requirements and duties consistent with the specific requirements of this Part and as certified by a Professional Engineer licensed under the Illinois Professional Engineering Act (Ill. Rev. Stat. 1985, ch. 111, par. 5101 et seq.).
|
| | | | |
"Project" means the undertaking to be performed as provided in the grant agreement.
|
| | | | |
"Resident project representative" means the authorized representative of the owner who is assigned to the project site or any part thereof.
|
| | | | |
"Responsible bidder" means a bidder who meets all of the criteria for responsibility established by the grantee or contractor in the invitation for bid or proposal and, in addition, meets all of the criteria set forth in Section 661.301(j)(1).
|
| | | | |
"Responsive bidder" means a bidder who complies with the invitation for bid or proposal in all material respects as to the method, substance, and timeliness of submission.
|
| | | | |
"Shop drawings" means all drawings, diagrams, illustrations, brochures, schedules and other data which are prepared by the contractor, subcontractor, manufacturer, supplier or distributor, which illustrate how specific portions of the work shall be fabricated or installed.
|
| | | | |
"Specifications" means a part of the contract documents consisting of written descriptions of a technical nature of materials, equipment, construction systems, standards and workmanship.
|
| | | | |
"Subagreement" means a written agreement between the grant recipient and another party and any tier of agreement thereunder for the furnishing of services, supplies, or equipment necessary to complete the project for which a grant was awarded, including contracts for personal and professional services and purchase orders.
|
| | | | |
"Subcontractor" means an individual, firm, or corporation having a direct contract with the contractor or with any other subcontractor for the performance of a part of the work.
|
| | | | |
"Substantial completion" means the date as certified by the engineer when the construction of the project or a specified part thereof is sufficiently completed, in accordance with the contract documents, so that the project or specified part can be utilized for the purpose for which it is intended.
|
| | | | |
"Supplier" means any person or organization who supplies materials or equipment for the work, including that fabricated to a special design, but who does not perform labor at the site.
|
| | | | |
"Unit of local government" means a county, municipality, township, municipal or county water or utility authority, municipal public water district, improvement authority, municipal subdivision whose primary purpose is to construct, operate and maintain public water supply facilities.
|
| | | | |
"Work" means all labor necessary to produce the construction required by the contract documents, and all materials and equipment incorporated or to be incorporated in the project.
|
| | | | |
"Written notice" means any notice to any party of the agreement relative to any part of this agreement in writing. Written notice shall be considered delivered and the service thereof completed, when posted by certified or registered mail to the said party at his last given address, or delivered in person to said party or his authorized representative on the work.
|
| | | | |
f)
| General requirements | |
| | | | |
Subagreements must:
| |
| | | | |
1)
| Be necessary for and directly related to the accomplishment of the project work based upon the Agency's professional judgement as defined in Section 661.102(b); |
2)
| Be in the form of a bilaterally executed written agreement (except for small purchases of $10,000 or less); |
3)
| Be for monetary or in-kind consideration; and |
4)
| Not be in the nature of a grant or gift. |
| | | | |
g)
| Documentation | |
| | | | |
1)
| Procurement records and files for purchases in excess of $10,000 shall include the following: |
| | | | |
A)
| Basis for contractor selection; |
| | | | |
B)
| Justification for lack of competition if competition appropriate to the type of project work to be performed is required but not obtained; and |
| | | | |
C)
| Basis for award cost or price. |
| | | | |
2)
| Procurement documentation as described in subsection (g)(1) shall be retained by the grantee or contractors of the grantee for the period of time required under Section 661.502. |
| | | | |
h)
| Specifications | |
| | | | |
1)
| Nonrestrictive specifications |
| | | | |
| No specification for bids or statement of work in connection with work performed under this grant shall be written in such a manner as to contain proprietary, exclusionary, or discriminatory requirements other than those based upon performance (as determined by the Agency based upon the Agency's professional judgement as defined in Section 661.102(b)), unless such requirements are necessary to test or demonstrate a specific thing or to provide for necessary interchangeability of parts and equipment, or at least one brand name or trade name of comparable quality or utility are listed and followed by the words "or equal". The single base bid method of solicitation for equipment and parts for determination of a low, responsive bidder may not be utilized. With regard to materials, if a single material is specified, the applicant must be prepared to substantiate the basis for the selection of the material.
|
| | | | |
2)
| Standard or proven production techniques |
| | | | |
| Project specifications shall provide for maximum use of structures, machines, products, materials, construction methods, and equipment which are readily available through competitive procurement, or through standard or proven production techniques (consistent with 35 Ill. Adm. Code: Subtitle F), methods, and processes, except to the extent that advanced technology may be utilized if approved by the Agency (based upon the Agency's professional judgement as defined in Section 661.102(b)) by the issuance of a construction permit or authorization to construct.
|
| | | | |
3)
| Sole source restriction | |
| | | | |
| A specification shall not require the use of structures, materials, equipment, or processes which are known to be available only from a sole source, unless such use has been justified in writing by the grantee's engineer as meeting the needs of the particular project.
|
| | | | |
4)
| Experience clause restriction |
| | | | |
| The general use of experience clauses requiring equipment manufacturers to have a record of satisfactory operation for a specified period of time or of bonds or deposits to guarantee replacement in the event of failure is restricted to special cases in which the grantee justifies any such requirement in writing. The Agency's acceptance of the justification shall be based upon the Agency's acceptance of the justification shall be based upon the Agency's professional judgement as defined in Section 661.102(b). Where such justification has been made, submission of a bond or deposit shall be permitted in lieu of a specified experience period, and the period of time for which such bond or deposit is required may not exceed the experience period specified.
|
| | | | |
i)
| Force account work | |
| | | | |
1)
| The grantee must request and secure prior written approval of the Agency for utilization of the force account method in lieu of subagreement. |
| | | | |
2)
| The Agency's approval shall be based on its determination that: |
| | | | |
A)
| All of the following conditions are met: |
| | | | |
| | | | |
B)
| Emergency circumstances (i.e., conditions that threaten the safety or adequacy of the water supply) so dictate. |
| | | | |
j)
| No subagreement shall be awarded to any person or organization which does not: |
| | | | |
1)
| Have adequate financial resources for performance, the necessary experience, organization, technical qualifications, and facilities, or a firm commitment, arrangement, or ability to obtain such (including proposed subagreements); |
| | | | |
2)
| Have resources sufficient to comply with the proposed or required completion schedule for the project; |
| | | | |
3)
| Have a satisfactory record of integrity, judgment, and performance, including in particular any prior performance under grants and contracts with the federal or state government; |
| | | | |
4)
| Have a financial management system and audit procedure which complies with generally accepted accounting principles and with American Institute of Certified Public Accountant's Professional Standards. (666 Fifth Avenue, N.Y., N.Y. 10019, June 1, 1987). (This incorporation contains no later amendments or editions.) |
| | | | |
5)
| Maintain a standard of procurement in accordance with this Part; |
| | | | |
6)
| Maintain a property management system which provides adequate procedures for the acquisition, maintenance, safeguarding and deposition of all property; and |
| | | | |
7)
| Conform to the civil rights, equal employment opportunity, and labor laws of the State of Illinois. |
| | | | |
k)
| Fraud and other unlawful or corrupt practices |
| | | | |
1)
| The award and administration of grants by the State of Illinois, and of subagreements awarded by grantees under those grants, must be accomplished free from bribery, graft, kickbacks, and other corrupt practices. The grantee bears the primary responsibility for prevention and detection of such conduct and for cooperation with appropriate authorities in the prosecution of any such conduct. |
| | | | |
2)
| The grantee must effectively pursue available state or local legal and administrative remedies, and take appropriate remedial action with respect to any allegations or evidence of such illegality or corrupt practices which are brought to its attention. The grantee shall advise the Agency immediately when any such allegation or evidence comes to its attention, and shall periodically advise the Agency of the status and ultimate disposition of any such matter. |
| | | | |
l)
| Negotiation of subagreements |
| | | | |
| Negotiation of subagreements (i.e., award of subagreements by any method other than formal advertising) is authorized if one or more of the following conditions exist:
|
| | | | |
1)
| Public exigency, as evidenced by governmental declaration will not permit the delay incident to advertising (e.g., an emergency procurement); |
| | | | |
2)
| The material or service to be procured is available from only one person or firm, and the Agency has given prior written approval of the justification submitted under subsection (h)(3); |
| | | | |
3)
| The aggregate amount involved does not exceed $2,500; |
| | | | |
4)
| The procurement is for personal or professional services, or for any service to be rendered by a university or other educational institution; |
| | | | |
5)
| No responsive, responsible bids at acceptable price levels have been received after formal advertising, and the Agency has given advance written approval. The Agency shall give such approval upon a showing by the grantee that no responsive, responsible bids were received; |
| | | | |
a)
| This Section shall apply to construction contracts (subagreements) awarded by the grantee. |
| | | | |
b)
| The project work shall be performed under one or more contracts awarded by the grantee to private firms, except for force account work authorized by the Agency under Section 661.301(i). |
| | | | |
c)
| Each contract shall be either a fixed-price (lump-sum) contract or fixed-rate (unit price) contract, or a combination of the two, unless the Agency gives advance written approval (based upon the Agency's professional judgment as defined in Section 661.102(b)) for the grantee to use some other acceptable type of contract (such as, but not limited to, per diem contracts as discussed under Section 661.303(b)(5)). The cost-plus-a-percentage-of-cost type of contract shall not be used. |
| | | | |
d)
| For each construction contract to be awarded by the grantee, the grantee shall require a: |
| | | | |
1) Bid bond for 5% of the bid price;
|
| | | | |
2) Performance bond for 100% of the contract price; and
|
| | | | |
3) Payment bond for 100% of the contract price.
|
| | | | |
e)
| The grantee must obtain written Agency approval prior to formal advertising. The Agency shall provide such approval if the grantee has complied with this Part and the conditions of the grant. Each contract shall be awarded after formal advertising, unless negotiation is permitted in accordance with Section 661.301(1). Formal advertising shall be in accordance with the following: |
| | | | |
1)
| Adequate public notice | |
| | | | |
| The applicant will cause adequate notice to be given of the solicitation by publication in newspapers or journals of general circulation statewide, inviting bids on the project work, and stating the method by which bidding documents may be obtained and examined. Where the estimated prospective cost of construction is ten million dollars or more, such notice must be published in trade journals of nationwide distribution. The applicant must in addition solicit bids directly from bidders, if it maintains a bidders list.
|
| | | | |
2)
| Adequate time for preparing bids |
| | | | |
| Not less than 30 days must be allowed between the date when public notice pursuant to subsection (e)(1) is first published and the date by which bids must be submitted. Bidding documents (including specifications and drawings) shall be available to prospective bidders from the date when such notice is first published.
|
| | | | |
3)
| Adequate bidding documents |
| | | | |
| Bidding documents (invitations for bid) shall be prepared by the grantee and shall be furnished upon request on a first-come, first-served basis. A complete set of bidding documents shall be maintained by the grantee and shall be available for inspection and copying by any party. Such bidding documents shall include:
|
| | | | |
A)
| A complete statement of the work to be performed, including necessary drawings and specifications, and a completion schedule. Drawings and specifications may be made available for inspection instead of being furnished; |
| | | | |
B)
| The terms and conditions of the contract to be awarded; |
| | | | |
C)
| A clear explanation of the method of bidding and the method of evaluation of bid prices, and the basis and method for award of the contract; |
| | | | |
D)
| A copy of all the general conditions, special conditions, assurances, agreements, and terms of the grant; |
| | | | |
E)
| Responsibility requirements or criteria which will be employed in evaluating bidders; provided, that an experience requirement may not be utilized unless justified under Section 661.301(h)(4); |
| | | | |
F)
| The following statement: | |
| | | | |
| "Any contract awarded under this Invitation for Bids is expected to be funded in part by a grant from the State of Illinois. Neither the State of Illinois nor any of its departments, agencies or employees is or will be a party to this Invitation for Bids or any resulting contract.";
|
| | | | |
G)
| A copy of subsection (e)(3)(H) shall be in the proposal form to be used by bidders and shall constitute a representation and certification to be considered part of the bid. The grantee shall not award any contract to a bidder who has deleted or modified the language contained in subsection (e)(3)(H) as set forth in the proposal form; |
| | | | |
H)
| By submission of the bid, each bidder certifies, and in the case of a joint bid each party thereto certifies as to his own organization, that in connection with the bid: |
| | | | |
f)
| Negotiations of contract amendments (change orders) |
| | | | |
1)
| Grantee responsibility | |
| | | | |
| The grantee is responsible for negotiation of construction contract change orders. This function may be performed by the grantee directly or by the consulting engineer, if authorized by the grantee.
|
| | | | |
A)
| During negotiations the grantee shall: |
| | | | |
i)
| Provide the contractor with a detailed description of the scope and extent of work to be performed; |
| | | | |
ii)
| Require the contractor to demonstrate that he will make available or will obtain the necessary personnel, equipment and materials to accomplish the work within the required time; and |
| | | | |
iii)
| Require a fair and reasonable price for the work. |
| | | | |
B)
| For each change order the grantee shall maintain a written summary of all negotiations and an independent cost estimate prepared by the grantee's consulting engineer. |
| | | | |
2)
| Changes in contract price or time |
| | | | |
| The contract price or time may be changed only by a change order. Negotiations shall be conducted in accordance with this subsection (f). The value of any work covered by a change order, or the value of claim for increases or decreases in the contract price, shall be determined by whichever method set forth below is the most advantages to the grantee:
|
| | | | |
A)
| Unit prices | | |
| | | | |
i)
| Original bid items: Unit prices set forth in the original bid are acceptable for pricing change orders. However, when changes in quantities exceed 15 percent of the original bid quantity, the unit price shall be reviewed by the grantee to determine if a new unit price should be negotiated. |
| | | | |
ii)
| New items: Unit prices of new items shall be negotiated. |
| | | | |
B)
| A lump sum to be negotiated. |
| | | | |
C)
| Cost reimbursement | |
| | | | |
| The actual cost for labor, direct overhead, materials, supplies, equipment, and other services necessary to complete the work plus an amount to be agreed upon to cover the cost of general overhead and profit to be negotiated.
|
| | | | |
3)
| For each change order, the contractor shall submit to the grantee cost and pricing data to enable the grantee to determine if the costs are fair and reasonable. Such data shall include: |
| | | | |
A)
| As a minimum, proposed change order costs shall be presented in summary format as prescribed by the Agency and shall be supported by a certification executed by the contractor that proposed costs reflect complete, current and accurate cost and pricing data applicable to the data of the change order. |
| | | | |
B)
| In addition to the specific elements of cost, the estimated amount of profit shall be set forth separately in the cost summary for fixed price change orders and a specific total dollar amount of profit will be set forth separately in the cost summary for cost reimbursement change orders. |
| | | | |
C)
| More detailed cost data than that set forth by the summary format may be required to enable the grantee to determine if the costs are fair and reasonable. |
| | | | |
D)
| For costs under cost reimbursement change orders, the contractor shall have an accounting system which accounts for such costs in accordance with generally accepted accounting principles. This system shall provide for the identification, accumulation, and segregation of allowable and unallowable change orders. The contractor shall propose and account for allowable change order costs in a manner consistent with such accounting procedures. |
| | | | |
E)
| Change orders awarded on the basis of review of a cost element summary and a certification of complete, current, and accurate cost and pricing data shall be subject to downward renegotiation or recoupment of funds where subsequent audit pursuant to this Part substantiates that such certification was not based on complete, current and accurate cost and pricing data and on costs allowable under these regulations at the time of the change order execution. |
| | | | |
4)
| Agency review | |
| | | | |
| For any change order, the grantee shall submit the following to the Agency for review to determine compliance with this Part:
|
| | | | |
A)
| The cost and pricing data submitted by the contractor; |
| | | | |
B)
| A certification of review and acceptance of the contractor's cost or price; and |
| | | | |
C)
| A copy of the change order with a justification describing the need and reasonableness of the change order. |
| | | | |
5)
| Profit | | |
| | | | |
| For the purpose of negotiated change orders to construction contracts under Agency grants, profit is defined as the net proceeds obtained by deducting all allowable costs (direct and indirect) from the price. The estimate of profit is to be reviewed by the grantee as are all other elements of price.
|
| | | | |
6)
| Allowability | | |
| | | | |
| Allowability of costs for change orders shall be determined in accordance with Section 661.701.
|
| | | | |
g)
| Progress payments to contractors |
| | | | |
1)
| Policy | | |
| | | | |
| Except as may be otherwise required by law, prompt progress payments shall be made by grantees to prime contractors and by prime contractors to subcontractors and suppliers for eligible construction, material, and equipment costs, including those of undelivered specifically manufactured equipment, incurred under a contract under an Agency construction grant.
|
| | | | |
2)
| Protection of progress payments made for specifically manufactured equipment |
| | | | |
| The grantee shall assure protection of the State's interest in progress payments made for specifically manufactured equipment. This protection must be in a manner or form acceptable to the grantee and shall take the form of recordation under the Uniform Commercial Code (Ill. Rev. Stat. 1985, ch. 26, pars. 1-101 et seq., as amended), adequate to protect the interest of the grantee and the State.
|
| | | | |
3)
| Limitations on progress payments |
| | | | |
| In no case may progress payments for undelivered equipment or items be made in any amount greater than seventy-five percent of the cumulative incurred costs allocable to contract performance with respect to the undelivered equipment or items. Submission of a request for any such progress payments shall be accompanied by a certification furnished by the fabricator of the equipment or item that the amount of progress payment claimed constitutes not more than seventy-five percent of cumulative incurred costs allocable to contract performance, and in addition, in the case of the first progress payment request, a certification that the amount claimed does not exceed 15 percent of the contract or item price quoted by the fabricator.
|
| | | | |
4)
| A subcontractor or supplier which is determined by the Agency to have frustrated the intent of the provisions regarding progress payments for major equipment or specifically manufactured equipment through failure to deliver the equipment shall be determined nonresponsible. |
| | | | |
5)
| Contract provisions | |
| | | | |
| Appropriate provisions regarding progress payments must be included in each contract and subcontract.
|
| | | | |
6)
| The foregoing progress payments policy shall be implemented in invitations for bids under construction grants. |
| Each construction contract shall include the "General Conditions of Construction Contract Document" as set forth in Appendix A. In addition, each construction contract shall include the following provisions:
|
| | | | |
1)
| Audit; access to records: |
| | | | |
A)
| The contractor shall maintain books, records, documents and other evidence directly pertinent to performance on grant work under this agreement in accordance with generally accepted accounting principles and with American Institute of Certified Public Accountants' Professional Standards (666 Fifth Avenue, New York City, New York 10019; June 1, 1987). (This incorporation contains no later amendments or editions.). The Contractor shall also maintain the financial information and data used by the Contractor in the preparation or support of any cost submissions required under subsection (f) of this Section and a copy of the cost summary submitted to the owner. The Auditor General, the owner, the Agency, or any of their duly authorized representatives shall have access to such books, records, documents, and other evidence for the purpose of inspection, audit, and copying. The contractor will provide proper facilities for such access and inspection. |
| | | | |
B)
| If this contract is a formally advertised, competitively awarded, fixed price contract, the contractor agrees to include the language set forth in subsection (i)(1) in all contract amendments or negotiated change orders in excess of $10,000, which affect the contract price. In the case of all other prime contracts, the contractor agrees to include language set forth in Section 661.303(i)(1) in all his contracts and all tier subcontracts or change orders thereto directly related to project performance which are in excess of $10,000. |
| | | | |
C)
| Audits conducted pursuant to this provision shall be in accordance with generally accepted auditing standards. |
| | | | |
D)
| The contractor agrees to the disclosure of all information and reports resulting from access to records pursuant to subsection (i)(1)(A). Where the audit concerns the contractor, the auditing agency will afford the contractor an opportunity for an audit exit conference and an opportunity to comment on the pertinent portions of the draft audit report. The final audit report will include the written comments, if any, of the audited parties. |
| | | | |
E)
| Records under subsection (i)(1)(A) shall be maintained and made available pursuant to Section 661.501 during performance on Agency grant work under this agreement and until three years from the date of final grant payment for the project. In addition, those records which relate to any dispute or litigation or the settlement of claims arising out of such performance, or costs or items to which an audit exception has been taken, shall be maintained and made available until three years after the date of resolution of such dispute, appeal, litigation, claim, or exception. |
| | | | |
2)
| Price reduction for defective cost or pricing data. |
| | | | |
A)
| This clause is applicable only to: |
| | | | |
i)
| any negotiated prime contract in excess of $10,000; |
| | | | |
ii)
| negotiated contract amendments or change orders affecting the price of a formally advertised, competitively awarded fixed price contract; or |
| | | | |
iii)
| any subcontract or purchase order under a prime contract other than a formally advertised, competitively awarded, fixed price contract. |
| | | | |
B)
| This clause is not applicable for contracts or subcontracts to the extent that they are awarded on the basis of effective price competition. |
| | | | |
C)
| If the Agency determines that any price (including profit) negotiated in connection with this contract, or any cost reimbursable under this contract, was increased by any significant sums because the contractor or any subcontractor furnished incomplete or inaccurate cost or pricing data or data not current as certified in his certification of current cost or pricing data, then such price or cost or profit shall be reduced accordingly and the contract shall be modified in writing to reflect such reduction. |
| | | | |
D)
| Failure to agree on a reduction shall be subject to 35 Ill. Adm. Code 661. Appendix A, Article 30. |
| | | | |
3)
| Covenant against contingent fees |
| | | | |
| The contractor warrants that no person or selling agency has been employed or retained to solicit or secure this contract upon an agreement or understanding for a commission, percentage, brokerage, or contingent fee. For breach or violation of this warranty the owner shall have the right to annul this contract without liability or in its discretion to deduct from the contract price or consideration, or otherwise recover, the full amount of such commission, percentage, brokerage, or contingent fee.
|
| | | | |
4)
| Gratuities | | |
| | | | |
A)
| The owner shall, by written notice to the contractor, terminate the right of the contractor to proceed under this contract if it is found, after notice and hearing, by the owner that gratuities (in the form of entertainment, gifts, or otherwise) were offered or given by the contractor or any agent or representative of the contractor, to any official or employee of the owner or of the State of Illinois with a view toward securing a contract or securing favorable treatment with respect to the awarding or amending, or the making of any determinations with respect to the performance of this contract: Provided, that if the existence of the facts upon which the owner makes such findings are in issue, they shall be reviewed in proceedings pursuant to 35 Ill. Adm. Code 661. Appendix A, Article 30. |
| | | | |
B)
| In the event this contract is terminated as provided in subsection (i)(4)(A) the owner shall be entitled to pursue the same remedies against the contractor as it could pursue in the event of a breach of the contract by the contractor. |
| | | | |
C)
| The rights and remedies of the owner provided in this clause shall not be exclusive and are in addition to any rights and remedies provided by law or under this contract. |
a)
| All grants are awarded subject to State law, including but not limited to the requirements of the following Illinois statutes: |
| | | | |
1)
| The Illinois Architecture Act (Ill. Rev. Stat. 1985, ch. 111, par. 1201 et seq.) relating to the practice of architecture. |
| | | | |
2)
| "AN ACT to prescribe the duty of an owner or occupant of lands upon which excavations are made in reference to the furnishing of lateral and subjacent support to adjoining lands and structures thereon" (Ill. Rev. Stat. 1985, ch. 111 ½, Par. 3301 et seq.) relating to the duty of an owner or occupant of land upon which excavations are made in reference to the furnishing of lateral and subjacent support to adjoining lands and structures thereon. |
| | | | |
3)
| Section 18f of "AN ACT in relation to the regulation of the rivers, lakes and streams of the State of Illinois" (Ill. Rev. Stat. 1985, ch. 19, par. 65f) relating to flood plains. |
| | | | |
4) "AN ACT in relation to bonds of contractors entering into contracts for public construction" (Ill. Rev. Stat. 1985, ch. 29, par. 15 et seq.) relating to bonds of contractors entering into contracts for public construction.
|
| | | | |
5)
| "AN ACT to prohibit discrimination and intimidation on account of race, creed, color, sex, religion, physical or mental handicap unrelated to ability, or national origin in employment under contracts for public buildings or public works" (Ill. Rev. Stat. 1985, ch. 29, par. 17 et seq.) relating to the prohibition of discrimination and intimidation on account of race, creed, color, sex or national origin in employment under Contracts for Public Works. |
| | | | |
6)
| "AN ACT regulating wages of laborers, mechanics and other workers employed in any public works by the State, county, city or any public body or any political subdivision or by any one under contract for public works" (Ill. Rev. Stat. 1985, ch. 48, par. 39s-1 et seq.) relating to the regulation of laborers, mechanics and other workmen employed in any public works by the State, county, city or any public body or any political subdivision or by anyone under contract for public works. |
| | | | |
7)
| The Health and Safety Act (Ill. Rev. Stat. 1985, ch. 48, par. 137.1 et seq.) relating to the health and safety of persons employed and vesting in the industrial commission power to make reasonable rules relating thereto. |
| | | | |
8)
| The Workers' Compensation Act (Ill. Rev. Stat. 1985, ch. 48, par. 138.1 et seq.) relating to providing compensation for accidental injuries or death suffered in the course of employment within this State, and without the State where the contract of employment is made within this State. |
| | | | |
9)
| "AN ACT forbidding employers to require employees or applicants for employment to pay the cost of medical examinations required as a condition of employment" (Ill. Rev. Stat. 1985, ch. 48, par. 172d et seq.) relating to forbidding employers to require employees or applicants for employment to pay the cost of medical examinations required as a condition of employment. |
| | | | |
10)
| The Workers' Occupational Diseases Act (Ill. Rev. Stat. 1985, ch. 48, par. 172.36 et seq.) relating to providing remedies for injuries suffered or death resulting from occupational diseases incurred in the course of employment. |
| | | | |
11)
| "AN ACT concerning the distribution of certain federal grants and the employment of Illinois workers" (Ill. Rev. Stat. 1985, ch. 48, par. 2201 et seq.) relating to employment of Illinois laborers only during periods of excessive unemployment in Illinois. |
| | | | |
12)
| Illinois Professional Engineering Act (Ill. Rev. Stat. 1985, ch. 111, par. 5101 et seq.) relating to the practices of professional engineering. |
| | | | |
13)
| "AN ACT to revise the law in relation to notices" (Ill. Rev. Stat. 1985, ch. 100, par. 1 et seq.) relating to publication of notices. |
| | | | |
14)
| Sections 3 and 4 of "AN ACT to prevent fraudulent and corrupt practices in the making or accepting of official appointments and contracts by public officers" (Ill. Rev. Stat. 1985, ch. 102, pars. 3 and 4) relating to the prevention of fraudulent and corrupt practices in the making or accepting of contracts by public officers. |
| | | | |
15)
| The Open Meetings Act (Ill. Rev. Stat. 1985, ch. 102, par. 41 et seq.) relating to meetings. |
| | | | |
16)
| The Environmental Protection Act (Ill. Rev. Stat. 1985, ch. 111 ½, par. 1001 et seq.) and regulations thereunder. |
| | | | |
17)
| The Illinois Structural Engineering Act (Ill. Rev. Stat. 1985, ch. 111, par. 6501 et seq.) relating to the practice of structural engineering. |
a)
| The grantee will be paid, upon request, in accordance with Section 661.704 for the State share of all necessary costs within the scope of the approved project not to exceed the total grant offer and determined to be allowable in accordance with the criteria set forth in this Section. |
| | | | |
| | | | |
- Allowable project costs.
| |
| | | | |
| Allocable project costs of the grantee which are reasonable and necessary are allowable. Necessary costs may include, but are not limited to:
|
| | | | |
1)
| Costs of salaries, benefits, and expendable material incurred by the grantee for the project, except as provided in subsection (c)(7); |
| | | | |
2)
| Costs under construction contracts; |
| | | | |
3)
| Professional and consultant services; |
| | | | |
4)
| Landscaping; | | |
| | | | |
5)
| Supervision of construction work; |
| | | | |
6)
| Removal and relocation or replacement of utilities for which the grantee is legally obligated to pay; |
| | | | |
7)
| Materials acquired, consumed, or expended specifically for the project; |
| | | | |
8)
| An inventory of laboratory chemicals and supplies necessary to initiate plant operations; |
| | | | |
9)
| Flood plain insurance; and |
| | | | |
10)
| Project identification signs. |
| | | | |
c)
| Unallowable costs | |
| | | | |
| Costs which exceed the total amount of the grant offer or which are not necessary for the completion of the work authorized by the grant agreement are unallowable. Such costs include, but are not limited to:
|
| | | | |
1)
| Costs relating to service connections; |
| | | | |
2)
| Bonus payments not legally required for completion of construction in advance of a contractual completion date; |
| | | | |
3)
| Personal injury compensation or damages arising out of the project, whether determined by adjudication, arbitration, negotiation, or otherwise; |
| | | | |
4)
| Fines and penalties resulting from violations of, or failure to comply with, federal, state, or local laws; |
| | | | |
5)
| Costs outside the scope of the approved project; |
| | | | |
6)
| Interest on bonds or any other form of indebtedness required to finance the project costs; |
| | | | |
7)
| Ordinary operating expenses of local government, such as salaries and expenses of a mayor, city council members, or city attorney, except as provided in subsection (d); |
| | | | |
8)
| Site acquisition; | |
| | | | |
9)
| Costs for which payment has been or will be received under another state of federal assistance program; |
| | | | |
10)
| Costs of equipment or material procured in violation of any provisions of this Part; |
| | | | |
11)
| Costs of special funds (i.e., industry advancement funds; funds to reimburse bidding costs to unsuccessful offerors, etc.) financed by contractors, contributions in the construction industry for methods and materials research, public and industry relations, market development, labor-management matters, wage negotiations, jurisdictional disputes, defraying of all or part of unsuccessful offerors bidding costs, or similar purposes; |
| | | | |
12)
| Costs for resident inspection where such costs are incurred after the expiration of the applicable contractual completion date, even if the contractual completion date is subsequently extended by the grantee, unless such extension has been approved by the Agency in accordance with Section 661.402; |
| | | | |
13)
| Personal and professional services costs (including but not limited to professional engineering costs) arising under a cost-plus-percentage of cost type of agreement (including the multiplier contract where profit is included in the multiplier) or a percentage-of-construction-cost type of contract; |
| | | | |
14)
| Personal and professional services costs (including but not limited to professional engineering costs) when the Agency has been refused access to the books and records of the contractor or the contractor has refused to renegotiate a personal or professional services contract in accordance with the provisions of Section 661.303; |
| | | | |
15)
| Increase in personal and professional services contract fees which are based solely on a percentage of an increased construction cost not withstanding the contractual liabilities of the grantee under such contract; and |
| | | | |
16)
| Personal and professional service costs, either direct or indirect, relating to entertainment, interest on borrowed capital, or bad debts. |
| | | | |
d)
| Design allowance | |
| | | | |
| The grant shall provide for a design allowance determined in accordance with Appendix C. The grantee shall not otherwise be reimbursed for costs incurred for project design.
|
| | | | |
e)
| Disputes concerning costs |
| | | | |
| The grantee shall seek to resolve questions relating to costs in accordance with Section 661.306.
|
| | | | |
f)
| Limitation upon project costs incurred prior to grant award |
| | | | |
| Payment will not be authorized for costs incurred prior to the date of the grant award except as in accordance with the following:
|
| | | | |
1)
| Advance acquisition of equipment items requiring long lead times, or advance construction of portions of the project, in emergencies or instances where delay could result in significant cost increases, shall not be approved by the Agency unless the grantee: |
| | | | |
A)
| Submits a written request for approval that demonstrates: |
| | | | |
1. Definitions
| | |
| | | | | |
1.1
| Wherever used in the Contract Documents, the following terms shall have the meanings indicated which shall be applicable to both the singular and plural thereof: |
| | | | | |
1.2
| Addenda -- Written or graphic instrument issued prior to the execution of the Agreement which modify or interpret the Contract Documents, Drawings and Specifications, by additions, deletions, clarifications or corrections. |
| | | | | |
1.3
| Bid -- The offer or proposal of the Bidder submitted on the prescribed form setting forth the prices for the Work to be performed. |
| | | | | |
1.4
| Bidder -- Any person, firm or corporation submitting a Bid for the Work. |
| | | | | |
1.5
| Bonds -- Bid, Performance, and Payment Bonds and other instruments of security, furnished by the Contractor and his surety in accordance with the Contract Documents. |
| | | | | |
1.6
| Change Order -- A written order to the Contractor authorizing an addition, deletion or revision in the Work within the general scope of the Contract Documents, or authorizing an adjustment in the Contract Price or Contract Time. |
| | | | | |
1.7
| Contract Documents -- The contract, including Advertisement For Bids, Information For Bidders, Bid, Bid Bond, Agreement, Payment Bond, Performance Bond. Notice of Award, Notice to Proceed, Change Order, Drawings, Specifications, and Addenda. |
| | | | | |
1.8
| Contract Price -- The total monies payable to the Contractor under the terms and conditions of the Contract Documents. |
| | | | | |
1.9
| Contract Time -- The number of calendar days stated in the Contract Documents for the completion of the Work. |
| | | | | |
1.10
| Contractor -- The person, firm or corporation with whom the Owner has executed the Agreement. |
| | | | | |
1.11
| Drawings -- The part of the Contract Documents which show the characteristics and scope of the Work to be performed and which have been prepared by or approved by the Engineer. |
| | | | | |
1.12
| Engineer -- The person, firm or corporation named as such in the Contract Documents. |
| | | | | |
1.13
| Field Order -- A written order effecting a change in the Work not involving an adjustment in the Contract Price or an extension of the Contract Time, issued by the Engineer to the Contractor during construction. |
| | | | | |
1.14
| Notice of Award -- The written notice of the acceptance of the Bid from the owner to the successful Bidder. |
| | | | | |
1.15
| Notice To Proceed -- Written communication issued by the Owner to the Contractor authorizing him to proceed with the Work and establishing the date of commencement of the Work. |
| | | | | |
1.16
| Owner -- A public or quasi-public body in authority, corporation, association, partnership, or individual for whom the Work is to be performed. |
| | | | | |
1.17
| Project -- The undertaking to be performed as provided in the Contract Documents. |
| | | | | |
1.18
| Resident Project Representative -- The authorized representative of the Owner who is assigned to the Project site or any part thereof. |
| | | | | |
1.19
| Shop Drawings -- All drawings, diagrams, illustrations, brochures, schedules and other data which are prepared by the Contractor, a Subcontractor, manufacturer, Supplier or distributor, which illustrate how specific portions of the Work shall be fabricated or installed. |
| | | | | |
1.20
| Specifications -- A part of the Contract Documents consisting of written descriptions of a technical nature of materials, equipment, construction systems, standards and workmanship. |
| | | | | |
1.21
| Subcontractor -- An individual, firm or corporation having a direct contract with the Contractor or with any other Subcontractor by the performance of a part of the Work at the site. |
| | | | | |
1.22
| Substantial Completion -- The date as certified by the Engineer when the construction of the Project or a specified part thereof is sufficiently completed, in accordance with the Contract Documents, so that the Project or specified part can be utilized for the purpose for which it is intended. |
| | | | | |
1.23
| Supplemental General Conditions -- Modifications to General Conditions required by a Federal agency for participation in the Project and approved by the agency in writing prior to inclusion in the Contract Documents, or such requirements that may be imposed by applicable state laws. |
| | | | | |
1.24
| Supplier -- Any person or organization who supplies materials or equipment for the Work, including that fabricated to a special design, but who does not perform labor at the site. |
| | | | | |
1.25
| Work -- All labor necessary to produce the construction required by the Contract Documents, and all materials and equipment incorporated or to be incorporated in the Project. |
| | | | | |
1.26
| Written Notice -- Any notice to any party of the Agreement relative to any part of this Agreement in writing and considered delivered and the service thereof completed, when posted by certified or registered mail to the said party at his last given address, or delivered in person to said party or his authorized representative on the Work. |
| | | | | |
2.
| Additional Instructions and Detail Drawings |
2.1
| The Contractor may be furnished additional instructions and detail drawings, by the Engineer, as necessary to carry out the Work required by the Contract Documents. |
| | | | | |
2.2
| The additional drawings and instruction thus supplied will become a part of the Contract Documents. The Contractor shall carry out the Work in accordance with the additional detail drawings and instructions. |
| | | | | |
3.
| Schedules, Reports and Records |
| | | | | |
3.1
| The Contractor shall submit to the Owner such schedule of quantities and costs, progress schedules, payrolls, reports, estimates, records and other data where applicable as are required by the Contract Documents for the Work to be performed. |
| | | | | |
3.2
| Prior to the first partial payment estimate the Contractor shall submit construction progress schedules showing the order in which he proposes to carry on the Work, including dates at which he will start the various parts of the Work, estimated date of completion of each part and, as applicable: |
| | | | | |
3.2.1
| The dates at which special detail drawings will be required; and |
| | | | | |
| | | | | |
3.3
| The Contractor shall also submit a schedule of payments that he anticipates he will earn during the course of the Work. |
| | | | | |
4.
| Drawings and Specifications |
| | | | | |
4.1
| The intent of the Drawings and Specifications is that the Contractor shall furnish all labor, materials, tools, equipment, and transportation necessary for the proper execution of the Work in accordance with the Contract Documents and all incidental work necessary to complete the Project in an acceptable manner, ready for use, occupancy or operation by the Owner. |
| | | | | |
4.2
| In case of conflict between the Drawings and Specifications, the Specifications shall govern. Figure dimensions on Drawings shall govern over scale dimensions, and detailed Drawings shall govern over general Drawings. |
| | | | | |
4.3
| Any discrepancies found between the Drawings and Specifications and site conditions or any inconsistencies or ambiguities in the Drawings or Specifications shall be immediately reported to the Engineer, in writing, who shall promptly correct such inconsistencies or ambiguities in writing. Work done by the Contractor after his discovery of such discrepancies, inconsistencies or ambiguities shall be done at the Contractor's risk. |
| | | | | |
5.
| Shop Drawings | |
| | | | | |
5.1
| The Contractor shall provide Shop Drawings as may be necessary for the prosecution of the Work as required by the Contract Documents. The Engineer shall promptly review all Shop Drawings. The Engineer's approval of any Shop Drawings shall not release the Contractor from responsibility for deviations from the Contract Documents. The approval of any Shop Drawing which substantially deviates from the requirement of the Contract Documents shall be evidenced by a Change Order. |
| | | | | |
5.2
| When submitting for the Engineer's review Shop Drawings shall bear the Contractor's certification that he has reviewed, checked and approved the Shop Drawings and that they are in conformance with the requirements of the Contract Documents. |
| | | | | |
5.3
| Portions of the Work requiring a Shop Drawing or sample submission shall not begin until the Shop Drawing or submission has been approved by the Engineer. A copy of each approved Shop Drawing and each approved sample shall be kept in good order by the Contractor at the site and shall be available to the Engineer. |
| | | | | |
6.
| Materials, Services and Facilities |
| | | | | |
6.1
| It is understood that except as otherwise specifically stated in the Contract Documents, the Contractor shall provide and pay for all materials, labor, tools, equipment, water, light, power, transportation, supervision, temporary construction of any nature, and all other services and facilities of any nature whatsoever necessary to execute, complete, and deliver the Work within the specified time. |
| | | | | |
6.2
| Materials and equipment shall be so stored as to insure the preservation of their quality and fitness for the Work. Stored materials and equipment to be incorporated in the Work shall be located so as to facilitate prompt inspection. |
| | | | | |
6.3
| Manufactured articles, materials and equipment shall be applied, installed, connected, erected, used, cleaned and conditioned as directed by the manufacturer. |
| | | | | |
6.4
| Materials, supplies and equipment shall be in accordance with samples submitted by the Contractor and approved by the Engineer. |
| | | | | |
6.5
| Materials, supplies or equipment to be incorporated into the Work shall not be purchased by the Contractor or the Subcontractor subject to a chattel mortgage or under a conditional sale contract or other agreement by which an interest is retained by the seller. |
| | | | | |
7.
| Inspection and Testing | |
| | | | | |
7.1
| All materials and equipment used in the construction of the Project shall be subject to adequate inspection and testing in accordance with generally accepted standards, as required and defined in the Contract Documents. |
| | | | | |
7.2
| The Owner shall provide all inspection and testing services not required by the Contract Documents. |
| | | | | |
7.3
| The Contractor shall provide at his expense the testing and inspection services required by the Contract Documents. |
| | | | | |
7.4
| If the Contract Documents, laws, ordinances, rules, regulations or orders of any public authority having jurisdiction require any Work to specifically be inspected, tested, or approved by someone other than the Contractor, the Contractor will give the Engineer timely notice of readiness. The Contractor will then furnish the Engineer the required certificates of inspection, testing or approval. |
| | | | | |
7.5
| Inspections, test or approvals by the engineer or others shall not relieve the Contractor from his obligations to perform the Work in accordance with the requirements of the Contract Documents. |
| | | | | |
7.6
| The Engineer and his representatives will at all times have access to the Work. In addition, authorized representatives and agents of any participating Federal or state agency shall be permitted to inspect all work, materials, payrolls, records of personnel, invoices of materials, and other relevant data and records. The Contractor will provide proper facilities for such access and observation of the Work and also for any inspection, or testing thereof. |
| | | | | |
7.7
| If any Work is covered contrary to the written instructions of the Engineer it must, if requested by the Engineer, be uncovered for his observation and replaced at the Contractor's expense. |
| | | | | |
7.8
| If the Engineer considers it necessary or advisable that covered Work be inspected or tested by others, the Contractor, at the Engineer's request, will uncover, expose or otherwise make available for observation, inspection or testing as the Engineer may require, that portion of the Work in question, furnishing all necessary labor, materials, tools, and equipment. If it is found that such Work is defective, the Contractor will bear all the expenses of such uncovering, exposure, observation, inspection and testing and of satisfactory reconstruction. If, however, such Work is not found to be defective the Contractor will be allowed an increase in the Contract Price or an extension of the Contract Time, or both, directly attributable to such uncovering, exposure, observation, inspection, testing and reconstruction and an appropriate Change Order shall be issued. |
| | | | | |
8.
| Substitutions | | |
| | | | | |
8.1
| Whenever a material, article or piece of equipment is identified on the Drawings or Specifications by reference to brand name or catalogue number, it shall be understood that this is referenced for the purpose of defining the performance or other salient requirements and that other products of equal capacities, quality and function shall be considered. The Contractor may recommend the substitution of a material, article, or piece of equipment of equal substance and function for those referred to in the Contract Documents by reference to brand name or catalogue number, and if, in the opinion of the Engineer, such material, article, or piece of equipment is of equal substance and function to that specified, the Engineer may approve its substitution and use by the Contractor. Any cost differential shall be deductible from the Contract Price and the Contract Documents shall be appropriately modified by Change Order. The Contractor warrants that if substitutes are approved, no major changes in the function or general design of the Project will result. Incidental changes or extra component parts required to accommodate the substitute will be made by the Contractor without a change in the Contract Price or Contract Time. |
| | | | | |
9.
| Patents | | |
| | | | | |
9.1
| The Contractor shall pay all applicable royalties and license fees. He shall defend all suits of claims for infringement of any patent rights and save the Owner harmless from loss on account thereof, except that the Owner shall be responsible for any such loss when a particular process design on the product of a particular manufacturer or manufacturer is specified, however, if the Contractor has reason to believe that the design process or product specified is an infringement of a patent, he shall be responsible for such loss unless he promptly gives such information to the Engineer. |
| | | | | |
10.
| Surveys, Permits, Regulations |
| | | | | |
10.1
| The Owner shall furnish all boundary surveys and establish all base lines for locating the principal component parts of the Work together with a suitable number of bench marks adjacent to the Work as shown in the Contract Documents. From the information provided by the Owner, unless otherwise specified in the Contract Documents, the Contractor shall develop and make all detail survey, needed for construction such as slope stakes, batterboards, stakes for pile locations and other working points, lines, elevations and cut sheets. |
| | | | | |
10.2
| The Contractor shall carefully preserve bench marks, reference points and stakes and in case of willful or careless destruction, he shall be charged with the resulting expense and shall be responsible for any mistakes that may be caused by their unnecessary loss or disturbance. |
| | | | | |
10.3
| Permits and licenses of a temporary nature necessary for the prosecution of the Work shall be secured and paid for by the Contractor unless otherwise stated in the Supplemental General Conditions. Permits, licenses and easements for permanent structures or permanent changes in existing facilities shall be secured and paid for by the Owner, unless otherwise specified. The Contractor shall give all notices and comply with all laws, ordinances, rules and regulations bearing on the conduct of the Work as drawn and specified. If the Contractor observes that the Contract Documents are at variance therewith, he shall promptly notify the Engineer in writing, and any necessary changes shall be adjusted as provided in Section 13, Changes in the Work. |
| | | | | |
11.
| Protection of Work, Property and Persons |
| | | | | |
11.1
| The Contractor will be responsible for initiating, maintaining and supervising all safety precautions and programs in connection with the Work. He will take all necessary precautions for the safety of and will provide the necessary protection to prevent damage, injury or loss to all employees on the Work and other persons who may be affected thereby, all the Work and all materials or equipment to be incorporated therein, whether in storage on or off the site, and other property at the site or adjacent thereto, including trees, shrubs, lawns, walks, pavements, roadways, structures and utilities not designated for removal, relocation or replacement in the course of construction. |
| | | | | |
11.2
| The Contractor will comply with all applicable laws, ordinances, rules, regulations and orders of any public body having jurisdiction. He will erect and maintain, as required by the conditions and progress of the Work, all necessary safeguards for safety and protection. He will notify owners of adjacent utilities when prosecution of the Work may affect them. The Contractor will remedy all damage, injury or loss to any properly caused directly or indirectly, in whole or in part, by the Contractor, any Subcontractor or anyone directly or indirectly employed by any of them or anyone for whose acts any of them be liable, except damage or loss attributable to the fault of the Contract Documents or to the acts or omissions of the Owner or the Engineer or anyone employed by either of them or anyone for whose acts either of them may be liable and not attributable, directly or indirectly, in whole or in part, to the fault or negligence of the Contractor. |
| | | | | |
11.3
| In emergencies affecting the safety of persons or the Work or property at the site or adjacent thereto, the Contractor, without special instruction or authorization from the Engineer of Owner, shall act to prevent threatened damage, injury or loss. He will give the Engineer prompt Written Notice of any significant changes in the Work or deviations from the Contract Documents caused thereby, and a Change Order shall thereupon be issued covering the changes and deviations involved. |
| | | | | |
12.
| Supervision by Contractor |
| | | | | |
12.1
| The Contractor will supervise and direct the Work. He will be solely responsible for the means, methods, techniques, sequences and procedures of construction. The Contractor will employ and maintain on the Work a qualified supervisor or superintendent who shall have been designated in writing by the Contractor as the Contractor's representative at the site. The supervisor shall have full authority to act on behalf of the Contractor and all communications given to the supervisor shall be as binding as if given to the Contractor. The supervisor shall be present on the site at all times as required to perform adequate supervision and coordination of the Work. |
| | | | | |
13.
| Changes in the Work |
| | | | | |
13.1
| The Owner may at any time, as the need arises, order changes within the scope of the Work without invalidating the Agreement. If such changes increase or decrease the amount due under the Contract Documents or in the time required for performance of the Work an equitable adjustment shall be authorized by Change Order. |
| | | | | |
13.2
| The Engineer, also, may at any time, by issuing a Field Order, make changes in the details of the Work. The Contractor shall proceed with the performance of any changes in the Work so ordered by the Engineer unless the contractor believes that such Field Order entitles him to a change in Contract Price or Time, or both, in which event he shall give the Engineer Written Notice thereof within seven (7) days after the receipt of the ordered change. Thereafter the Contractor shall document the basis for the change in Contract Price or Time within thirty (30) days. The Contractor shall not execute such changes pending the receipt of an executed Change Order or further instruction from the Owner. |
| | | | | |
14.
| Changes in Contract Price |
| | | | | |
14.1
| The Contract Price may be changed only by a Change Order. The value of any Work covered by a Change Order or of any claim for increase or decrease in the Contract Price shall be determined by one or more of the following methods in the order or precedence listed below: |
| | | | | |
a.
| Unit prices previously approved |
b.
| An agreed lump sum | |
c.
| The actual cost for labor, direct overhead, materials, supplies, equipment, and other services necessary to complete the work. In addition, there shall be added an amount to be agreed upon but not to exceed fifteen (15) percent of the actual cost of the Work to cover the cost of general overhead profit. |
| | | | | |
15.
| Time for Completion and Liquidated Damages |
| | | | | |
15.1
| The date of beginning and the time for completion of the Work are essential conditions of the Contract Documents and the Work embraced shall be commenced on a date specified in the Notice to Proceed. |
| | | | | |
15.2
| The Contractor will proceed with the Work at such rate of progress to insure full completion within the Contract Time. It is expressly understood and agreed, by and between the Contractor and the Owner, that the Contract Time, for the completion of the Work described herein is a reasonable time, taking into consideration the average climatic and economic conditions and other factors prevailing in the locality of the Work. |
| | | | | |
15.3
| If the Contractor shall fail to complete the Work within the Contract Time, or an extension of time granted by the Owner, then the Contractor will pay to the Owner the amount for liquidated damages as specified in the BID for each calendar day that the Contractor shall be in default after the time stipulated in the Contract Documents. |
| | | | | |
15.4
| The Contractor shall not be charged with liquidated damages of any excess cost when the delay in completion of the Work is due to the following and the Contractor has promptly given Written Notice of such delay to the owner or Engineer. |
| | | | | |
17.2
| The Owner shall promptly investigate the conditions, and if he finds that such conditions do so materially differ and cause an increase or decrease in the cost of, or in the time required for, performance of the Work, an equitable adjustment shall be made and the Contract Documents shall be modified by a Change Order. Any claim of the Contractor for adjustment hereunder shall not be allowed unless he has given the required Written Notice, provided that the Owner may, if he determines the facts so justify, consider and adjust any such claims asserted before the date of final payment. |
| | | | | |
18.
| Suspension of Work, Termination and Delay |
| | | | | |
18.1
| The Owner may suspend the Work on any portion thereof for a period of not more than ninety days or such further time as agreed upon by the Contractor, by Written Notice to the Contractor and the Engineer which notice shall fix the date on which Work shall be resumed. The Contractor will resume the Work on the date so fixed. The Contractor will be allowed an increase in the Contract Price or an extension of the Contract Time, or both, directly attributable to any suspension. |
| | | | | |
18.2
| If the Contractor is adjudged bankrupt or insolvent, or if he makes a general assignment for the benefit of his creditors, or if a trustee or receiver is appointed for the Contractor or for any of his property, or if he files a petition to take advantage of any debtor's act, or to reorganize under the bankruptcy or applicable laws, or if he repeatedly fails to supply sufficient skilled workmen or suitable materials or equipment, or if he repeatedly fails to make prompt payments to Subcontractors or for labor, materials or equipment or if he disregards laws, ordinances, rules, regulations or orders of any public body having jurisdiction of the Work or if he disregards the authority of the Engineer, or if he otherwise violates any provision of the Contract Documents, then the Owner may, without prejudice to any other right or remedy and after giving the Contractor and his surety a minimum of ten (10) days from delivery of a Written Notice, terminate the services of the Contractor and take possession of the Project and of all materials, equipment, tools, construction equipment and machinery thereon owned by the Contractor, and finish the Work by whatever method he may deem expedient. In such case the Contractor shall not be entitled to receive any further payment until the Work is finished. If the unpaid balance of the Contract Price exceeds the direct and indirect costs of completing the Project, including compensation for additional professional services, such excess Shall be Paid to the Contractor. If such costs exceed such unpaid balance, the Contractor will pay the difference to the Owner. Such costs incurred by the Owner will be determined by the Engineer and incorporated in a Change Order. |
| | | | | |
18.3
| Where the Contractor's services have been so terminated by the Owner, said termination shall not affect any rights of the Owner against the Contractor then existing or which may thereafter accrue. Any retention or payment of monies by the Owner due the Contractor will not release the Contractor from compliance with the Contract Documents. |
| | | | | |
18.4
| After ten (10) days from delivery of a Written Notice to the Contractor and the Engineer the Owner may, without cause and without prejudice to any other right or remedy elect to abandon the Project and terminate the Contract in such case, the Contractor shall be paid for all Work executed and any expense sustained plus reasonable profit. |
| | | | | |
18.5
| If, through no act or fault of the Contractor, the Work is suspended for a period of more than ninety (90) days by the Owner or under an order of court or other public authority or the Engineer fails to act on any request for payment within thirty (30) days after it is submitted or the Owner fails to pay the Contractor substantially the sum approved by the Engineer or awarded by arbitrators within thirty (30) days of its approval and presentation, then the Contractor may after ten (10) days from delivery of a Written Notice to the Owner and the Engineer, terminate the Contract and recover from the Owner payment for all Work executed and all expenses sustained. In addition and in lieu of terminating the Contract, if the Engineer has failed to act on a request for payment or if the Owner has failed to make any payment as aforesaid, the Contractor may upon ten (10) days written notice to the Owner and the Engineer stop the Work until he has been paid all amounts then due in which event and upon resumption of the Work, Change Orders shall be issued for adjusting the Contract Price or extending the Contract Time or both to compensate for the costs and delays attributable to the stoppage of the Work. |
| | | | | |
18.6
| If the performance of all or any portion of the Work is suspended, delayed, or interrupted as a result of a failure of the Owner or Engineer to act within the time specified in the Contract Documents, or if no time is specified, within a reasonable time, an adjustment in the Contract Price or an extension of the Contract Time, or both, shall be made by Change Order to compensate the Contractor for the costs and delays necessarily caused by the failure of the Owner or Engineer. |
| | | | | |
19.
| Payments to Contractor |
| | | | | |
19.1
| At least ten (10) days before each progress payment falls due (but not more often than once a month), the Contractor will submit to the Engineer a partial payment estimate filled out and signed by the Contractor covering the Work performed during the period covered by the partial payment estimate and supported by such data as the Engineer may reasonably require. If payment is requested on the basis of materials and equipment not incorporated in the Work but delivered and suitably stored at or near the site, the partial payment estimate shall also be accompanied by such supporting data, satisfactory to the Owner, as will establish the Owner's title to the material and equipment and project his interests therein, including applicable insurance. The Engineer will, within ten (10) days after receipt of each partial payment estimate, either indicate in writing his approval of payment and present the partial payment estimate to the Owner, or return the partial payment estimate to the Contractor indicating in writing his reasons for refusing to approve payment. In the latter case, the Contractor may make the necessary corrections and resubmit the partial payment estimate. The Owner will, within ten (10) days of presentation to him of an approved partial payment estimate, pay the Contractor a progress payment on the basis of the approved partial payment estimate. The Owner shall retain ten (10) percent of the amount of each payment until final completion and acceptance of all work covered by the Contract Documents. The Owner at any time, however, after fifty (50) percent of the Work has been completed, if he finds that satisfactory progress is being made, shall reduce retainage to five (5%) percent on the current and remaining estimates. When the Work is substantially complete (operational or beneficial occupancy), the retained amount may be further reduced below five (5) percent to only that amount necessary to assure completion. On completion and acceptance of a part of the Work on which the price is stated separately in the Contract Documents, payment may be made in full, including retained percentages, less authorized deductions. |
| | | | | |
19.2
| The request for payment also include an allowance for the cost of such major materials and equipment which are suitably stored either at or near the site. |
| | | | | |
19.3
| Prior to Substantial Completion, the Owner, with the approval of the Engineer and with the concurrence of the Contractor, may use any completed or substantially completed portions of the Work. Such use shall not constitute an acceptance of such portions of the Work. |
| | | | | |
19.4
| The Owner shall have the right to enter the premises for the purpose of doing work not covered by the Contract Documents. This provision shall not be construed as relieving the Contractor of the sole responsibility for the care and protection of the Work, or the restoration of any damaged Work except such as may be cause by agents or employees of the Owner. |
| | | | | |
19.5
| Upon completion and acceptance of the Work, the Engineer shall issue a certificate attached to the final payment request that the Work has been accepted by him under the conditions of the Contract Documents. The entire balance found to be due the Contractor, including the retained percentages, but except such sums as may be lawfully retained by the Owner, shall be paid to the Contractor within thirty (30) days of completion and acceptance of the Work. |
| | | | | |
19.6
| The Contractor will indemnify and save the Owner or the Owner's agents harmless from all claims growing out of the lawful demands of Subcontractors, laborers, workmen, mechanics, materialmen, and furnishers of machinery and parts thereof, equipment, tools, and all supplies incurred in the furtherance of the performance of the Work. The Contractor shall, at the Owner's request, furnish satisfactory evidence that all obligations of the nature designated above have been paid, discharged, or waived. If the Contractor fails to do so the Owner may, after having notified the Contractor, either pay unpaid bills or withhold from the Contractor's unpaid compensation a sum of money deemed reasonably sufficient to pay any and all such lawful claims until satisfactory evident is furnished that all liabilities have been fully discharged whereupon payment to the Contractor shall be resumed, in accordance with the terms of the Contract Documents, but in no event shall the provisions of this sentence be construed to impose any obligations upon the Owner to either the Contractor, his Surety, or any third party. In paying any unpaid bills of the Contractor, any payment so made by the Owner shall be considered as a payment made under the Contract Documents by the Owner to the Contractor and the Owner shall not be liable to the Contractor for any such payments made in good faith. |
| | | | | |
19.7
| If the Owner fails to make payment thirty (30) days after approval by the Engineer, in addition to other remedies available to the Contractor, there shall be added to each such payment interest at the maximum legal rate commencing on the first day after said payment is due and continuing until the payment is received by the Contractor. |
| | | | | |
20.
| Acceptance of Final Payment as Release |
| | | | | |
20.1
| The acceptance by the Contractor of final payment shall be and shall operate as a release to the Owner of all claims and all liability to the Contractor other than claims in stated amounts as may be specifically excepted by the Contractor for all things done or furnished in connection with this Work and for every act and neglect of the Owner and others relating to or arising out of this Work. Any payment, however, final or otherwise, shall not release the Contractor or his sureties from any obligations under the Contract Documents or the Performance Bond and Payment Bonds. |
| | | | | |
21.
| Insurance | |
| | | | | |
21.1
| The Contractor shall purchase and maintain such insurance as will protect him from claims set forth below which may arise out of or result from the Contractor's execution of the Work, whether such execution be by himself or by any Subcontractor or by anyone directly or indirectly employed by any of them, or by anyone for whose acts any of them may be liable: |
| | | | | |
| | | | | |
21.4
| The Contractor shall procure and maintain, at his own expense during the Contract Time, in accordance with the provisions of the laws of the state in which the work is performed, Workmen's Compensation Insurance including occupational disease provisions, for all of his employees at the site of the Project and in case and work is sublet, the Contractor shall require such Subcontractor similarly to provide Workmen's Compensation Insurance, including occupational disease provisions for all of the latter's employees unless such employees are covered by the protection afforded by the Contractor. In case any class of employees engaged in hazardous work under this contract at the site of the Project is not protected under Workmen's Compensation statute, the Contractor shall provide, and shall cause each Subcontractor to provide, adequate and suitable insurance for the protection of his employees not otherwise protected. |
| | | | | |
21.5
| The Contractor shall secure, if applicable, "All Risk" type Builder's Risk Insurance for Work to be performed. Unless specifically authorized by the Owner, the amount of such insurance shall not be less than the Contract Price totaled in the Bid. The policy shall cover not less than the losses due to fire, explosion, hail, lightning, vandalism, malicious mischief, wind, collapse, riot, aircraft, and smoke during the Contract Time, and until the Work is accepted by the Owner. The policy shall name the insured the Contractor, the Engineer, and the Owner. |
| | | | | |
22.
| Contract Security | |
| | | | | |
22.1
| The Contractor shall within ten (10) days after the receipt of the Notice of Award furnish the Owner with a Performance Bond and a Payment Bond in penal sums equal to the amount of the Contract Price conditioned upon the performance by the Contractor of all undertakings, convenants, terms, conditions and agreements of the Contract Documents, and upon the prompt payment by the Contractor to all persons supplying labor and materials in the prosecution of the Work provided by the Contract Documents. Such Bonds shall be executed by the Contractor and a corporate bonding company licensed to transact such business in the state in which the Work is to be performed and named on the current list of "Surety Companies Acceptable on Federal Bonds" as published in the Treasury Department Circular Number 570. The expense of these Bonds shall be borne by the Contractor. If at any time a surety on any such Bond is declared a bankrupt or loses its right to do business in the state in which the Work is to be performed or is removed from the list of Surety Companies accepted on Federal Bonds, Contractor shall within ten (10) days after notice from the Owner to do so, substitute an acceptable Bond (or Bonds) in such form and sum and signed by such other surety and sureties as may be satisfactory to the Owner. The premiums on such Bond shall be paid by the Contractor. No further payments shall be deemed due nor shall be made until the new surety or sureties shall have furnished an acceptable Bond to the Owner. |
| | | | | |
23
| Assignments | |
| | | | | |
23.1
| Neither the Contractor nor the Owner shall sell, transfer, assign or otherwise dispose of the Contract or any portion thereof, or of his right, title or interest therein, or his obligations thereunder without written consent of the other party. |
| | | | | |
24.
| Indemnification | |
| | | | | |
24.1
| The Contractor will indemnify and hold harmless the Owner and the Engineer and their agents and employees from and against all claims, damages, losses and expenses including attorney's fees arising out of or resulting from the performance of the Work, provided that any such claims, damage, loss or expense is attributable to bodily injury, sickness, disease or death, or to injury to or destruction of tangible property, including the loss of use resulting therefrom; and is caused in whole or in part by any negligent or willful act or omission of the Contractor, and Subcontractor, anyone directly or indirectly employed by any of them or anyone for whose acts any of them may be liable. |
| | | | | |
24.2
| In any and all claims against the Owner or the Engineer, or any of their agents or employees, by any employee of the Contractor, any Subcontractor, anyone directly or indirectly employed by any of them, or anyone for whose acts any of them may be liable, the indemnification obligation shall not be limited in any way by any limitation of the amount or type of damages, compensation or benefits payable by or for the Contractor or any Subcontractor under workmen's compensation acts, disability benefit acts or other employee benefits acts. |
| | | | | |
24.3
| The obligation of the Contractor under this paragraph shall not extend to the liability of the Engineer, his agents or employees arising out of the preparation or approval of maps, Drawings, opinions, reports, surveys, Change Orders, designs or Specifications. |
| | | | | |
25.
| Separate Contracts | |
| | | | | |
25.1
| The Owner reserves the right to let other contracts in connection with this Project. The Contractor shall afford other Contractors reasonable opportunity for the introduction and storage of their materials and the execution of their Work, and shall properly connect and coordinate his Work with theirs. If the proper execution or results of any part of the Contractor's Work depends upon the Work of any other Contractor, the Contractor shall inspect and promptly report to the Engineer any defects in such Work that render it unsuitable for such proper execution and results. |
| | | | | |
25.2
| The Owner may perform additional Work related to the Project by himself, or he may let other contracts containing provisions similar to these. The Contractor will afford the other Contractors who are parties to such contracts (or the Owner, if he is performing the additional Work himself), reasonable opportunity for the introduction and storage of materials and equipment and the execution of Work, and shall properly connect and coordinate his Work with theirs. |
| | | | | |
25.3
| If the performance of additional Work by other Contractors or the Owner is not noted in the Contract Documents prior to the execution of the Contract, written notice thereof shall be given to the Contractor prior to starting any such additional Work. If the Contractor believes that the performance of such additional work by the Owner or others involves him in additional expense or entitles him to an extension of the Contract Time, he may make a claim therefore as provided in Sections 14 and 15. |
| | | | | |
26.
| Subcontracting | |
| | | | | |
26.1
| The Contractor may utilize the services of specialty Subcontractors on those parts of the Work which, under normal contracting practices, are performed by specialty Subcontractors. |
| | | | | |
26.2
| The Contractor shall not award Work to Subcontractor(s), in excess of fifty (50%) percent of the Contract Price, without prior written approval of the Owner. |
| | | | | |
26.3
| The Contractor shall be fully responsible to the Owner for the acts and omissions of his Subcontractors, and of persons either directly or indirectly employed by them, as he is for the acts and omissions of persons directly employed by him. |
| | | | | |
26.4
| The Contractor shall cause appropriate provisions to be inserted in all subcontracts relative to the Work to bind Subcontractors to the Contractor by the terms of the Contract Documents insofar as applicable to the Work of Subcontractors and to give the Contractor the same power or regards terminating any subcontract that the Owner may exercise over the Contractor under any provision of the Contract Documents. |
| | | | | |
26.5
| Nothing contained in this Contract shall create any contractual relation between any Subcontractor and the Owner. |
| | | | | |
27.
| Engineer's Authority |
| | | | | |
27.1
| The Engineer shall act as the Owner's representative during the construction period. He shall decide questions which may arise as to quality and acceptability of materials furnished and Work performed. He shall interpret the intent of the Contract Documents in a fair and unbiased manner. The Engineer will make visits to the site and determine if the Work is proceeding in accordance with the Contract Documents. |
| | | | | |
27.2
| The Contractor will be held strictly to the intent of the Contract Documents in regard to the quality of materials, workmenship and execution of the Work. Inspections may be made at the factory or fabrication plant of the source of material supply. |
| | | | | |
27.3
| The Engineer will not be responsible for the construction means, control, techniques, sequences, procedures, or construction safety. |
| | | | | |
27.4
| The Engineer shall promptly make the decisions relative to interpretation of the Contract Documents. |
| | | | | |
28.
| Land and Rights-of-Way |
| | | | | |
28.1
| Prior to issuance of Notice to Proceed, the Owner shall obtain all land and rights-of-way necessary for carrying out and for the completion of the Work to be performed pursuant to the Contract Documents, unless otherwise mutually agreed. |
| | | | | |
28.2
| The Owner shall provide to the Contractor information which delineates and describes the lands owned and rights-of-way acquired. |
| | | | | |
28.3
| The Contractor shall provide at his own expense and without liability to the Owner any additional land and access thereto that the Contractor may desire for temporary construction facilities, or for storage of materials. |
| | | | | |
29.
| Guaranty | |
| | | | | |
29.1
| The Contractor shall guarantee all materials and equipment furnished and Work performed for a period of one (1) year from the date of Substantial Completion. The Contractor warrants and guarantees for a period of one (1) year from the date of Substantial Completion of the system that the completed system is free from all defects due to faulty materials or workmanship and the Contractor shall promptly make such corrections as may be necessary by reason of such defects including the repairs of any damage to other parts of the system resulting from such defects. The Owner will give notice of observed defects with reasonable promptness. In the event that the Contractor should fail to make such repairs, adjustments, or other Work that may be made necessary by such defects, the Owner may do so and charge the Contractor the cost thereby incurred. The Performance Bond shall remain in full force and effect through the guarantee period. |
| | | | | |
30.
| Arbitration | |
| | | | | |
30.1
| All claims, disputes and other matters in question arising out of, or relating to, the Contract Documents or the breach thereof, except for claims which have been waived by the making and acceptance of final payment as provided by Section 20 shall be decided by arbitration in accordance with the Construction Industry Arbitration Rules of the American Arbitration Association (140 W. 51st Street, N.Y., N.Y. 10020; 1986). This agreement to arbitrate shall be specifically enforceable under the prevailing arbitration law. The award rendered by the arbitrators shall be final, and judgement may be entered upon it in any court having jurisdiction thereof. |
| | | | | |
30.2
| Notice of the demand for arbitration shall be filed in writing with the other party to the Contract Documents and with the American Arbitration Association, and a copy shall be filed with the Engineer. Demand for arbitration shall in no event be made on any claim, dispute or other matter in question which would be barred by the applicable statue of limitations. |
| | | | | |
30.3
| The Contractor will carry on the Work and maintain the progress schedule during any arbitration proceedings, unless otherwise mutually agreed in writing. |
| | | | | |
31.
| Taxes | | |
| | | | | |
31.1
| The Contractor will pay all sales consumer use and other similar taxes required by the law of the place where the Work is performed. |