ILLINOIS POLLUTION CONTROL BOARD
August 22,
1972
ENVIRONMENTAL PROTECTION AGENCY
v.
)
4171—157
CITY OF SILVIS
Mr. John C.
Parkhurst,
for the Environmental Protection Agency;
Mr.
N.
L.
McGehee,
for City of Silvis
Opinion of the Board
(by Mr. Currie):
After a long and tortuous history, this case has resulted
in a settlement proposal that is
a credit to all parties and a
significant triumph for the important principle of regional
sewage treatment.
We approve the settlement for reasons given
below.
The complaint of the Environmental Protection Agency,
filed
June 22,
1971,
charged Silvis with polluting the Rock River by
discharging inadequately treated sewage and with failure to
meet the deadlines of Rules and Regulations SWB-11, which re-
quired submission of plans for secondary treatment by June
1,
1967 and prompt construction thereafter.
Only primary treat-
ment is at present provided.
At
a hearing September 13,
1971,
the Agency and the City
proposed the entry of
a consent order under which Silvis would
construct its own secondary treatment facilities in accordance
with
a specified time schedule.
We found in the record no
sufficient explanation for the abandonment of an earlier plan
to construct an interceptor to transport Silvis’s wastes
to
East Moline for treatment in a single large regional plant.
Noting that
“the Board has consistently taken the position that
it favors the use of larger plants where possible” because
“this regional,
large plant approach makes the cost of waste
treatment
less and in many cases
improves the efficiency of the
treatment process,” we ordered the parties to submit “a full
and complete explanation as
to the obstacles which prevent the
City of Silvis from connecting the treatment plant of the City
of East Moline.”
EPA v. City of Silvis,
#71—157
(Oct.
18, l97i)~
On November
11, 1971 we entered
a supplementary order re-
citing that the City’s response, which reaffirmed opposition to a
regional solution, raised important issues requiring input from
parties not then represented,
including the City of East Moline,
which would be required to treat the sewage under
a regional
solution, and the Bi--State Planning Commission, which had long
favored the regional approach.
We added the necessary parties and
authorized
a further hearing.
5—
2t~
5
—2—
After considerable negotiation and further proceedings,
a
final hearing was held July 24,
1972,
and all interested parties
concurred in the submission of the proposed settlement now before
us.
All parties now agree that the optimum solution is the
construction of an interceptor to allow for regional treatment
at East Moline, which will eliminate the need for any discharge
into the Rock River at Silvis,
East Moline itself must expand its
facilities in order to accommodate the increased load, and it
must provide secondary treatment under our revised regulations
by December,
1973,
for its effluent discharge to the Mississippi
River.
East Moline undertakes in the present settlement to
make the necessary improvements;
Silvis’s discharge is to be
terminated by the end of 1973 or such later date as East Moline
may be allowed for completing the expansion of its primary
(not secondary)
facilities.
The record is clear that a certain
delay has been occasioned
in East Moline’s plans by the need
to resolve the disposition of Silvis’s problem.
The proposed program fully conforms to our expressed policy
of encouraging regional treatment facilities, as more fully
explained in our opinion in In the Matter of DuPage County
Sewage Regionalization, #R7O~-l7 (Jan,
6,
1972).
We are con-
vinced that,
~iven past delays, it offers the best
practicable solution today to Silvis’s problem.
A complete solution to the problem will require not only
East Moline’s acceptance of the Silvis waste but also the
secondary treatment required by our regulations even for the
Mississippi.
East Moline~sprogram for providing such treat-
ment is under way, and East Moline has asked us to grant a
variance extending the December 1973 deadline in that regard.
We agree with the Agency that this question cannot adequately
be decided on the record now before us; East Moline should
file a petition meeting the requirements
of our procedural
rules and be prepared to demonstrate its hardship and the
justifications for its delay in
a public hearing in which the
Agency can take an active part.
The remaining question is whether Silvis should be
penalized for the substantial delay in meeting its obligation
to
terminate the discharge of inadequately treated wastes to the
Rock River.
It is conceded that there has been a violation of the
deadlines regarding secondary treatment;
the Agency in its
stipulation and proposed order “acknowledges mitigating circum-
stances in the delay” and notes that the City “has cooperated
fully in all hearings and pre-hearing conferences in an attempt
to arrive at the best possible solution,” and therefore the
settlement proposal provides for no money penalty.
We are not
5
—
206
—3—
informed as to what the Agency regards as “mitigating circumstances,”
and we should be under our rules so that we can better evaluate
the proposal.
And working diligently now, while indicating
a presently favorable attitude, cannot completely excuse
an earlier default.
See Packaging Corp.
of l½merica v.
EPA,
#71-352
(August 15, 1972).
On the other hand,
we have
consistently afforded considerable latitude to the adver-
sary parties in achieving a consent order that resolves the
controversy and provides for adequate future control of
pollution without further expense of litigation, provided
that the settlement is not such
as to encourage disregard
for the
law by grossly underpenalizing past defaults.
See,
e.g., EPA v. Granite City Steel Co.,
#70-34
(April 25,
1972)
We know from the record that at least some portion of
the past delay in Silvis’s case has resulted from the con-
troversy over whether to go it alone or to go in with East
Moline.
So far as we can tell this controversy has been in
entirely good faith.
Whether it was justifiable to take
so many years to resolve it,
or whether that is the whole
explanation, we cannot say from the record.
Moreover,
our
policy has been that money penalties against municipalities
should be kept generally low in order to preserve sCarce
funds for corporate purposes and to avoid penalizing innocent
citizens for the omissions of their government.
See City of
Springfield v.
EPA, #70-55 (March 31,
1971)
.
Whatever we
might do if this case had been presented to us
on the
basis of a full hearing for our initial evaluation, we do
not think the absence of a penalty under all these circum-
stances is so unreasonable as to require us
to reject a
consent order arrived at by all parties.
Accordingly we approve the proposed order as it has been
presented to the Board.
ORDER
1.
That the City of Silvis is now and has been for some
time in violation of the Environmental Protection Act in that
it caused water pollution within the State of Illinois, by
discharging untreated or improperly treated sewage into the
Rock River,
and that it failed to meet construction deadlines,
all in violation of Section 12(a)
of the Illinois Environ-
mental Protection Act, and SWB—ll, Rule 1.08(10) (b)
,
(11) (b),
12,
14 and 15, but seeks to immediately bring itself into
compliance by the construction of an interceptor sewer main
from its present collection system to the East Moline sewage
collection system at a point in said system previously con-
structed for that purpose by the City of East Moline,
in the
manner described below.
5
—
207
—4—
2.
That the Permit #1972—AA—26
—
Log #1653—71 previously
issued to the Respondent City of Silvis on January 10,
1972,
allowing the City to up-date its existing treatment facilities
in the
Village of Carbon Cliff, will be rescinded upon
compliance by the Respondent City of Silvis with all provisions
of this Order.
3.
The City of Silvis is ordered to submit, to the
Environmental Protection Agency on or before the 15th day of
March,
1973,
final plans and specifications for the construction
of the interceptor main from its own collection system to the
connection provided in the East Moline sewage disposal system,
and the City is ordered to make whatever provisions or changes
may be necessary to comply with all applicable regualtions
within a reasonable time from the request therefor.
4.
That the City of Silvis is ordered to complete con-
struction of the proposed interceptor main by December 31,
1973,
that date on which the City of East Moline is required
by regulation
to have upgraded its present disposal facilities,
providing secondary treatment.
Provided, however, that if the
City of East Moline shall apply for and receive a variance
extending the time for which
to provide secondary treatment,
and if such varinace includes a date later than December
31,
1973,
for the completion of the construction and addition
of primary treatment facilities, which shall be required as
part of the secondary treatment facility construction, the
City of Silvis shall complete the construction of the inter-
ceptor main no later than that extended date.
5.
The City of East Moline shall make all necessary
attempts to comply with the State requirements regarding the
upgrading of its present sewage treatment facilities, in-
cluding the increase in capacity of its facilities with
primary treatment, and the addition of secondary treatment.
Should the City of East Moline require any time beyond the
present date of December 31,
1973,
for completion of its
secondary treatment facilities,
it shall apply for an
appropriate variance from the Pollution Control Board
to do
so.
However,
in all events,
the City of East Moline shall
make every effort to complete the increased capacity of its
facilities with primary treatment and chlorination at
a date
no later than December 31,
1973.
If such primary treatment
facilities are completed no later than December 31,
1973,
then the City of Silvis shall be required to complete the
construction of its interceptor main no later than that
date.
In short, the City of Silvis shall be required to
complete the construction of its interceptor main by a date no
later than that date upon which
the City of East Moline shall
complete the construction of
its new, increased capacity
sewage treatment facilities with primary treatment;
and
5— 208
—5—
that the City
of East Moline shall make every possible effort
to see to it that such facilities are constructed no later than
December 31, 1973;
and in any event should a date later than
that be required,
an appropriate variance shall be sought
for such extended date by all appropriate parties.
6.
The cost
of
the proposed construction by the City
of Silvis and by the City of East Moline shall be paid out
of funds on hand available for such purposes, or out of the
general
funds of such municipality not otherwise appropriated.
if funds on hand or unappropriated are insufficient for the
purposes of complying with this Order, the necessary funds
shall be raised by the issuance of either general obligation
or revenue bonds.
If the estimated cost of the steps necessary
to be taken by the City of Silvis and by the City of East
Moline to comply with this Order is such that the bond issue
necessary to finance’ the project would not raise the total
outstanding bonded indebtedness of the City of Silvis and
the City of East Moline, respectively,
in excess of the limit
imposed upon such indebtedness by the Constitution of the
State
of Illinois,
the necessary bonds may be issued as
a
direct obligation
of such municipality and retired pursuant to
general law governing the issue of such bonds.
No election
or referendum shall be necessary for the issuance of bonds
under this paragraph.
The funds made available by the issuance
of direct obligation or revenue bonds,
as herein provided,
shall constitute
a Sanitary Fund and shall be used for no other
purpose than for carrying out such order or orders of the
Board.
7.
To insure compliance with this Order,
the City of
Silvis and the City of East Moline, respectively,
shall
submit to the Agency their Performance Bonds in the amount of
Ten Thousand ($10,000.00)
Dollars each without corporate
surety, signed by
the
appropriate municipal officials under
a Resolution authorizing its execution and providing for a
forfeiture of said bond,
or that portion thereof,
as directed
by the Pollutioi-i Control Board on any subsequent hearing
ordered for such purpose.
8.
That the Cities of Silvis and East Moline have
previously made application with the Environmental Protection
Agency for State and Federal grants to construct the proposed
sewage treatment and handling facilities.
The Cities of Silvis
and East Moline shall immediately upon the adoption of this
Order, resubmit or amend,
as necessary,
their applications
for both State and Federal grants to insure that
the
ordered projects may receive prompt consideration.
That the
Agency shall consider or reconsider such grant applications,
or amendments thereto, on file or to be filed and shall assign
said projects the highest appropriate priority under existing
criteria.
5
—
209
—6—
9.
The City of East Moline agrees and binds itEelf to
provide service for the treatment of domestic wastes ~nd
sewage to the City of Silvis in
a way which
is consistent with
the requirements of the State regulations, and consi~centfurther
with all terms of this Order, by
a date no later than the
completion of
the interceptor main from the City of Silvis to the
City of East Moline’s sewage treatment plant, and the completion
of the new primary treatment facilities by the City of East
Moline whichever shall come later.
10.
The Cities of
Silvis and East Moline shall not permit
the construction of any ne~isewers or other source of waste
to their facilities, or any increase in the strength or con-
centration of waste discharged to their facilities unless per-
mitted so
to do, either by variance or otherwise.
11.
That the Environmental Protection Agency acknowledges
mitigating circumstances
in the delay by the City of Silvis in
bringing itself into compliance with the Environmental Protection
Act and all other applicable State regulations and acts.
That
said City has cooperated fully in all hearings and pre-hearing
conferences
in an attempt to arrive at the best possible solution,
and It Is Therefore Ordered by the Board that no fine or other
sanction be levied against the Cityof Silvis.
I, Christan Moffett, Clerk of the Pollution Contro~öoard, certify
that the Board adopted the above Opinion this
c~c?
day of
\ugust,
1972, by a vote of
?—c~)
5
—
210