ILLINOIS POLLUTION CONTROL BOARD
March
15,
1973
)
CITY OF NASHVILLE
)
)
)
v.
)
PCB 72-275
)
)
ENVIRONMENTAL PROTECTION AGENCY
)
)
OPINION AND ORDER OF THE BOARD
(by Mr.
Dumelle)
This
is a petition for variance from Rule 405 of the Illinois
Water Pollution Regulations which requires that no effluent shall
exceed 400 fecal
coliforms per 100 ml after July
31,
1972.
Hearing
was held on September
15,
1972.
The existing treatment facility at Nashville consists of
a single
stage stabilization pond with a design capacity of
3,600 population
equivalents.
The facility treats wastes from residents and commer-
cial businesses
in the City.
It processes
approximately 300,000
gallons of waste water per day.
The City estimates
that the treat-
ment process has
a 75
efficiency and that the effluent discharged
is
151 pounds per day of suspended solids and 128 pounds per day
of BOD.
The effluent is discharged directly to Nashville Creek,
tributary to Crooked Creek.
At
times Nashville Creek
is reported
to have no flow.
(R.43).
On December
9,
1971,
samples
of the effluent taken by the
Agency showed 92 mg/i
BOl),
44 mg/l suspended solids and 800,000/100 ml
fecal coliform.
On February
15,
1972,
samples showed 130 mg/i BOD,
37 mg/i suspended solids and 120,000/100 ml
fecal coliform.
On
June
16,
1972,
samples showed
55 mg/i
BOD,
150 mg/i suspended solids
and 26,000/100
ml fecal
coliform.
On July 14,
1972,
samples showed
75 mg/i
1301),
160 mg/i suspended solids and 60,000/100 ml fecal
coliform.
The Agency inspector who took the samples
testified that
the fecal coliform levels were higher than from most treatment
facilities.
The engineering consultant for the City testified that
the levels measured by
the Agency would create
a potential for
disease producing organisms
to be
in
the waters.
(R.64).
The
Lity
is planning
to upgrade
its facility by adding two
additional
s~ng1ecell stabilization ponds
to be connected in series
to the present pond.
The system will
also include
a permanent
ChIOTi
n;~t
ion
faci
ii ty for effluent disenfect ion.
The
expected
completion date for the project
is December,
1973
-2-
Some of
the delay has been caused by the City’s inability
to purchase the land needed for the proposed facility.
Negotiations
for a certain tract of land began in October,
1970.
The negotiations
proved unsuccessful and finally in August,
1972
the City Council
voted
to file
a condemnation suit
for the desired property.
We
do
not know anything further about the status of that case.
Also in
August,
1972
the City Council directed the City Attorney to prepare
a revenue bond issue for $450,000.
The City has
applied for both
State and Federal
grant funds
for the project but will be able
to
finance the project on its own if necessary
(R.34-S).
The main issue
in
this
case
is whether the City should be
excused
from the installation of temporary chlorination facilities.
The evidence is clear that such facilities can technically be
accomplished within the present City system.
Engineering data
indicate that the temporary facility could be constructed in the
present stabilization pond.
It would have
to be protected from
flooding but it certainly could be done.
Most of the temporary
facility would be salvageable upon completion
of the permanent
facility.
The chlorination unit itself would not have to be
relocated,
only the detention tank.
The net loss
on the temporary
facility would be only ~7,000.
The facility would take six months
to complete.
We do not
find
the
evidence
adequate
to
support
a variance.
The
City
has not shown in any significant way that the $7,000 loss would
impose an unreasonable hardship on itself.
The fecal coliform
levels are high and do not justify
the prevention
of
a $7,000 loss.
Furthermore,
at this point
it seems unrealistic that
the expected
December,
1973 completion date for the permanent installation will
be met.
As
far as we know,
neither
the land purchase nor the
local
financing
has
been
completed
as
of
this
time.
In addition,
the Board takes
judicial notice of
a proceeding
filed before it on March
7,
1973 by
the Director of the Environmental
Protection Agency
(R.73-4).
This proceeding states that federally-
funded projects will be delayed for approximately one year because
regulations and guidelines have not been published.
Since
the
Director’s
letter also states that the start of construction without
a grant would render the municipality ineligible for reimbursement
from Federal funds
it would appear that Nashville would not want
to
finance the entire $120,000 cost of the lagoon system itself lest
it lose $90,000
(75)
in Federal funds.
A delay
seems reasonable
beyond December 1973 and 1)ecember 1974 would become
a more likely
completion date.
Another issue here
is
that of the City’s diligence after the
hearing was conducted.
The City did not submit the 91-page
transcript
to the Board until January
10,
1973,
four months after
the hearing.
We
feel that such delay was unreasonable under the
7
2~O
-3-
circumstances.
If we would have been able
to decide this
case
in October or November,
1972 there would have been around fourteen
months between this and the expected completion date of December,
1973 for the permanent facility.
Figuring the six-month period
necessary
to complete the temporary chlorination facility, it
could have been
in operation by May,
1973
at
the latest.
From May 1973
to December 1974
is
19 months.
The $7,000
cost,
even though appearing high,
is
low when spread over
this period.
We are bothered by the lack of information from Nashville
on the bacterial levels
in Nashville Creek.
While bacterial
dieoff does occur
in the lagoon,
the levels
of fecal coliform
as discharged are far above the standard.
Do people swim, wade
or canoe
in Nashville Creek or North Creek?
We do not know on
this record.
Nor do we know the bacterial levels resulting in
these creeks after mixing.
Nashville with
a population
of 3,027
cannot be expected to put on
a sophisticated case but
it could
have
done more.
We would also urge Nashville
to review the
testimony in
a related case with regard
to installing temporary
chlorination facilities
in very short time periods.
(City of
Granite City
v.
EPA, PCB 72-184,
371, February 27,1973).
We deny
the variance without prejudice to a new proceeding
if more adequate
proofs are available.
This opinion constitutes the Board’s findings
of fact and
conclusions
of law.
ORDER
The petition for variance
is denied without prejudice.
I, Christan
L. Moffett,
Clerk of the Illinois Pollution
Control Board,hereby~certify the above Opinion and Order were
adopted on the
j
day
of March,l973 by
a vote of
~‘—o
~(~
~LC
~
71)
~
Christan
L. Moffett/~lerk
Illinois Pollution ~ntrol
Board
7
—
281