ILLINOIS POLLUTION CONTROL BOARD
October
3,
1972
SOUTH SIDE FOUNDRY COMPANY
)
#72—105
v.
ENVIRONMENTAL PROTECTION AGENCY
ENVIRONMENTAL PROTECTION AGENCY
#72-187
v.
SOUTH SIDE FOUNDRY COMPANY
)
MR. PRESCOTT E.
BLOOM, SPECIAL ASSISTANT ATTORNEY
GENERAL,
ON
BEHALF OF ENVIRONMENTAL PROTECTION AGENCY
MR. RICHARD J.
TROY,
ON BEHALF OF SOUTH SIDE FOUNDRY
OPINION AND ORDER OF THE BOARD
(BY MR.
LAWTON):
On March
21,
1972,
in Case #72—105, petition was filed by
South Side Foundry Company
(referred
to throughout this Opinion
as
“petitioner”)
to permit operation of its Peoria foundry in ex-
cess of permissible particulate limits as provided by Regulation.
The Agency recommended that the variance be denied,
or if granted,
that it be subject to the installation of spark arresters,
the
submission of
a firm compliance program within thirty days of the
Board’s decision and the posting of a performance bond.
Waiver
of the 90—day statutory provision for the rendition of a variance
order has been received.
On May 1,
1972,
in Case #72-187, complaint was filed by the
Environmental Protection Agency against South Side Foundry Company
alleging that on or about July
21 and July 22, 1971 and between
January 13, 1972 and the date of filing of the complaint, Peti-
tioner caused,
threatened or allowed the discharge of particulate
matter, gaseous emissions and other contaminants,
in violation
of Section 9(a)
of the Act and Rule 2-2.54 of the Rules and Regu-
lations Governing the Control of Air Pollution
(Air Rules), and
violated Rules
2-2.3 and 2-2.4,
in failing to file a Letter of
Intent and Air Contaminant Emission Reduction Program.
Penalties
in the maximum statutory amount are sought.
5
—
563
On motion of the Agency,
the two proceedings were consolidated
by order of the Hearing Officer.
Hearing was held on August 28,
1972.
Petitioner operates a gray iron metal casting plant in Peoria
employing 25 people.
Melting is done in a four-ton per hour,
36” diameter cupola, averaging approximately seven tons per day.
According to the variance petition, South Side Foundry melts
1,680 tons of metal per year,
uses 8,400 tons of sand annually
in its molding operation and emits 146 pounds per day of parti-
culates, (82 pounds per day of aerosols
defined by petitioner as
containing particulates under
50 microns,
and 64 pounds per day
of suspendable material~.In addition,
1,930 pounds of carbon
monoxide are emitted daily.
All of the foregoing emissions result
from a seven ton per day liquid iron production purportedly accom-
plished during a two-hour per day maximum melting period.
Petitioner has no proposed specific emission control program
to bring itself into compliance with the relevant statutory and
regulatory provisions.
It indicates that it is giving consideration
to four alternative abatement processes:
a wet cap attachment
with baghouse for collecting particulates with afterburners to
reduce CO emissions,
a Venturi—type collector and afterburner,
electric induction-type melters or high efficiency—type gas or
oil reverbatory melters.
Petitioner alleges that 15 months will be needed for studies,
development of casting criteria, choice of method to be pursued,
ordering of equipment and installation.
Neither in its petition
nor in the course of the hearing has petitioner indicated which
method,
if any,
it anticipates adopting,
or what progress has been
made in developing
a program
of compliance, notwithstanding a period
of five months having elapsed between the filing of the variance
petition and the hearing.
The hearing brought out that the foundry
was a family—owned business which enjoyed
a successful operation
for many years prior to 1960,
at which time the foundry became
the victim of severe mismanagement, which it appears to have re-
mained subject to until September of 1971, when management and owner-
ship changes took place,
and petitioner again resumed operation on
a profitable basis.
Mary L. McCarthy testified as a witness for petitioner
(R.8),
She has been president of South Side Foundry Company since July of
1971.
The business had previously been operated by her father and
upon his death in 1954,
by her three brothers.
Ownership of the
business has been entirely within the McCarthy family and included
Mary L. McCarthy as a part owner prior
to her designation as cor-
poration president.
Since taking office,
Miss Mccarthy has sought
the aid of various professionals in endeavoring to remedy the un-
satisfactory operation of the plant, but no definitive program of
pollution control has been embarked upon or as yet proposed.
This
—2—
5—
664
witness testified to the mismanagement of the company by her
brothers,
including the payment of exorbitant salaries and un-
authorized diversion of funds.
Since Miss McCarthy’s assumption
of the corporate presidency,
this situation has ceased, the
company
is presently solvent and in good standing with the Illi-
nois Secretary of State.
Walter E. Walz testified on behalf of South Side Foundry
Company
(R.27), describing the condition of the foundry as of
May,
1972 as having reached
“the point of no return”
(R.30).
He described the virtual absence of maintenance and housekeeping
procedures and the general sioppy way in which the foundry had
been operated.
In recent months,
some improvement has re-
sulted from gas torch firing of the cupola in lieu of the
previous use of wood firing
(R..35).
This witness discussed several
of the emission control alternatives proposed in the variance peti-
tion.
The wet cap attachment to the baghouse
(R.46,
Pet.
Ex.
2), a
Brown Bovari Coreless-type Melting Furnace
(R.52,
Pet. Ex.
3)
and
a smaller coreless type electric furnace
(R.55, Pet. Ex.
4) were
described in terms of operation and installation.
According to
Waiz,
all proposals would require at least one year for order,
delivery and installation
(R.59).
James
F.
Powell, metallurgist consultant employed by petition-
er, testified on its behalf.
He stated that no spark arrester had
been installed in the stack and that sparks were emitted on occa-
sion from the cupola operation.
The foregoing was the extent of petitioner’s case in support
of its variance petition.
No representation was made that any
specific abatement program would be pursued or what time schedule
of installation petitioner anticipated it would follow in order to
bring its operation into compliance.
Witnesses for the Environmental Protection Agency,
in support
of the enforcement action and in opposition to the variance allow-
ance, included John W.
Tomic
(R.61) who testified that he was the
operator of a gas station approximately 125 feet from petitioner’s
foundry
(R.65),
that he had observed sparks and smoke emanating
from the foundry stack between July of
1970 and July of 1971
(R.64)
and that he refrained from filling automobile gas tanks with gaso-
line during periods when sparks were observed for fear that an explo-
sion might result
(R.66),
During
.a period of several months prior
to the hearing, this witness observed similar emissions approximate—
ly four times per month when particulates dropped on the customer’s
cars
(R.67)
.
Some improvement was noted shortly prior to the hear-
ing.
—3—
5
—
565
Douglas Winters testified on behalf of the Agency
(R.
93).
He operated a tavern in the vicinity of the foundry, which burned
down on October 27,
1971, possibly as a result of sparks emitted
from petitioner’s operation.
Exhibits introduced by the Agency included pictures of peti-
tioner’s stack and alleged emissions from it, ~thich~e~renot
particularly helpful.
Agency Exhibit
7 contains a report of
inspection of petitioner’s foundry made on April
3,
1972 by
R.
C. Wennmacher, an agency employee.
On the basis of standard
emission factors, computed on a seven—ton per day melt,
emissions
were computed at 14.8 pounds per hour against an allowable emis-
sion maximum of 3.54 pounds per hour.
This exhibit was received
without objection and no effort was made to refute it
(R.104).
Petitioner’s
principal defense to the enforcement action was
the incompetent operation existing prior to Mary McCarthy’s selec-
tion as corporate president, which she now appears endeavoring to
improve.
However,
it will be noted that notwithstanding Miss Mc-
Carthy’s assumption of control in 1971,
and her laudable desire
to improve
a bad situation,
nothing has been done to date by way
of a definitive program to bring petitioner’s operation into
compliance, nor has anything by way of defense or extenuating
circumstances been submitted.
While the evidence of nuisance and
particulate violations is somewhat meager, petitioner concedes
that it has failed to file an approved Air Contaminant Emission
Reduction Program and has operated for many years without emission
control equipment of any kind
(R.22,
106).
Likewise, a nuisance
on the community has been demonstrated resulting from spark and
particulate emissions affecting the comfort and safety of persons
and property in the vicinity of the foundry.
The Agency’s contention that sparks from petitioner’s operation
may have caused the fire destroying
a nearby tavern is not complete-
ly convincing on the state of the record.
However, there is no
question that sparks from the foundry have been emitted over a
long period of time and the company does agree to obtain a spark
arrester which we will order installed within two weeks of the
date0f this order.
Violation of particulate regulations is not
denied although evidence of specific numerical measurements mani-
festing violation
is found only with respect to the April
3,
1972
inspection.
While we are not unmindful of the efforts being made by Miss
McCarthy in recent months to correct a bad situation, and are hope-
ful that her present efforts will be rewarding,
the
record does not
furnish us with any defense or adequate extenuating circumstances
with respect to the enforcement action.
—4—
5
—
566
The
Respondent
in
the
enforcement
action
is
a
corporation
which
has
been
in existence throughout the entire period of the
alleged offenses.
There has been a continuity of family ownership
and control.
An assessment of penalty against the corporation
would enable it to take such steps against its former officers
and others as would be appropriate to receive reimbursement from
those who have been guilty of the flagrant disregard of pollution
control regulations.
While Miss McCarthy has been a corporate
officer for a relatively short time,
she has been a stockholder
for many years and the family has been in ownership throughout the
entire period of violation.
The factual situation in the present case is~not like that in
Environmental Protection Agency v. Lindgren Foundry Co.,
#70-1,
1 PCB 11, September 25,
1970, where we declined to impose penal-
ties because the corporation, at the time of trial, was owned by
an entirely different entity than those who were responsible for
the violations proven.
Here,
there has been continuity of owner-
ship over the entire period of violation.
With respect to petitioner’s petition for variance,
the record
is completely devoid of any substantive testimony or evi4ence
enabling us to justify a grant of such relief.
Petitioner has
present~dno specific program nor plan of installation upon which
even /alimited departure from the Regulations could be~premised.
In Øücago-Dubuque Foundry Corporation v. Enviranme~ntalProtection
Agency,
#71—130,
2 PCB 65,June
28,
1971; we denied a variance petition
because of the absence of a definitive compliance program.
We
must do the same in the present case.
On the state of the record, we assess a penalty in the amount
of $3,000.00 for failure to submit a Letter of Intent and an Air
Contaminant Emission Reduction Program
(Rules 2—2.3 and 2-2.4)
and
for violation of particulate regulations
(Rule 2-2.54)
as well
as the causing of air pollution in violation of Section 9(a)
of
the Environmental Protection Act.
In arriving at this penalty figure,
we have given consideration primarily to the company’s long and un-
justified delay in taking action of any nature to abate its pollution-
al discharge and its failure to have
a program of compliance, at this
late date.
The
original petition for variance was filed in March
of 1972, over six months ago, yet nothing appears in the record to
indicate that petitioner
is any further along with an emission abate-
ment program than it was when the original petition for variance
was filed.
We direct the company to submit a program of compliance within
30 days of the date of this
Order, expressly setting forth a method
of abatement control which the company will pursue and the dates
5
—
567
on which installation will be completed.
We will require that a
bond in the amount of $10,000.00 be filed’with the Environmental
Protection Agency assuring that this program will be submitted.
We order the installation of a spark arrester within two weeks of the
date of
this Order.
We shall retain jurisdiction of this case for
such other and further orders as may be appropriate in the pre-
mises.
This opinion constitutes the findings of fact and conclusions
of law of the Board.
IT
IS
THE
ORDER of the Pollution Control Board:
1.
The petition for variance of South Side Foundry Company
is denied.
2.
Penalty in the amount of $3,000.00
is assessed against
South Side Foundry Company for violations of Rules 2-2.3,
2-2.4 and 2-2.54 of the Rules and Regulations Governing
the Control of Air Pollution, because of South Side
Foundry Company’s failure to file a Letter of Intention
and Air Contaminant Emission Reduction Program, and ex-
ceeding particulate regulations, all as provided in said
Regulations and for the causing of air pollution in viola-
tion of Section 9(a)
of the Environmental Protection Act.
Penalty payment by certified check or money order shall
be made payable to the State of Illinois, Fiscal Services
Division,
Illinois Environmental Protection Agency,
2200 Churchill Drive, Springfield,
Illinois 62706.
3.
South Side Foundry Company shall submit to the Board and
the Agency within
30 days from the date of this Order,
a
specific program for Air Contaminant Emission Control and
abatement of particulate and carbon monoxide emissions
from its foundry operation, including a specific program
of purchase, acquisition and installation of equipment,
to
bring its foundry operation into compliance with all rele-
vant regulations and statutory provisions relative to the
control of air pollution.
4.
South Side Foundry Company shall provide a bond in the
amount of $10,000 payable to the Environmental Protection
Agency and mailed to Fiscal Services Division, Illinois
Environmental Protection Agency,
2200 Churchill Drive,
Springfield,
Illinois 62706.
The bond shall be in
form
satisfactory to the Agency and shall guarantee that the
program of compliance required by paragr~ph3
of this
Order shall be submitted in the time provided and in the
form required.
—6—
5
—
568
5.
The
company
shall
install
a
spark
arrester
in
its
stack
preventing
any
emission
of
sparks
into
the
atmosphere, within two weeks from the date hereof.
6.
The Board retains jurisdiction for such other and
further orders as are appropriate, based upon the
foregoing provisions of the Order.
I~christan Moffett, Clerk of the Illinois Pollution Control Board,
certify that the above Opinion and Order was a~optedon the
____
day of
~-~~-~L_
,
1972, by a vote of
~
to
C’
~
—7—
5
—
569