ILLINOIS POLLUTION CONTROL BOARD
    November
    11,
    1971
    MT.
    CARMEL PUBLIC UTILITY
    v.
    )
    PCB 71—15R
    ENVIRONMENTAL PROTECTION AGENCY
    Messrs.
    Albert A.
    Scriber, Albert A.
    ~arnhard,
    and Leonard M.
    Koger,
    Jr.,
    appearing
    for
    Mt.
    Carmel
    Public
    Utility
    Mr. Larry
    Ft. Eaton,
    Special Assistant Attorney General!
    and
    Mr. Delbert D. Haschemeyer,
    Attorney, appearing for
    the
    Environmental Protection Agency
    Opinion of
    the Board
    (by Mr.
    Kissel):
    Mt.
    Carmel Public Utility Company
    (the
    “Utility’)
    ,
    a privately
    owned utility which distributes natural gas and electricity to
    a
    service area in and around
    Mt.
    Carmel,
    Illinois,
    filed
    a
    “Motion
    for
    Re—Hearing on Petition for Varianceu
    with
    the Board on July
    16,
    1971.
    The Utility sought
    a re-hearing of
    a previous case in which the
    Board denied the Utility’s Petition for variance,
    Mt. Carmel Public
    Utility Company
    v.
    Environmental Protection
    :~oency, P03
    71-15,
    dated April
    14,
    1971.
    The Utility sought permission-in
    that case
    to use coal—fired boilers over
    a period of the next ten years, when
    they will
    be
    phased out.
    The Board denied the request generally
    on the basis that Board policy is such that one who discharges
    in
    excess of the regulations,
    as
    was the
    case with
    the Utility’s emis-
    sions
    from the coal-fired boilers,
    that person must have
    a program
    for the installation
    of control equipment, where such equipment
    is
    technically feasible, before
    the Board will grant
    any variances.
    Apparently,
    as
    a result of that decision,
    the Utility has
    now come
    up
    with
    a program to halt the emissions from
    the coal fired boilers.
    A hearing was held on
    the Motion for Re-Hearing on September
    17,
    1971
    in Mt. Carmel,
    Illinois before Medard Narko, Hearing Officer.
    The
    Utility
    has
    three
    coal—fired
    boilers
    which
    are
    in
    omera-
    tion
    ~-
    Units
    1,
    4
    and
    5.
    In
    its
    new
    plan
    the
    Utility
    proposes
    to
    convert
    Boiler
    #5
    to
    an
    oil-fired
    unit
    by
    June
    30,
    .1973,
    and
    to
    burn
    #2
    oil
    in
    that
    converted
    unit.
    Boilers
    #1
    and
    #4
    will
    continue
    to
    be
    used
    until
    June
    of
    1974
    when
    an
    additional
    transmission
    line
    will
    be
    installed
    between
    the
    Mt.
    Carmel
    facility
    and
    a
    generating
    station of Central Illinois Public Service Company
    (CIPCo).
    After
    3
    25

    that Boilers
    #1 and
    #4 will,
    according
    to the company plan,
    be kept
    on cold standby and will
    only be used if there is
    a failure in the
    Utility’s ability to supply power to its customers.
    The Agency’s
    recommendation given at the hearing was that the Utility be required
    to begin installation of
    the conversion of Boiler #5 on October
    1,
    1972,
    rather
    than January
    1,
    l97~, as suggested by the Utility,
    and that the preliminary work,
    like piping and installation
    of
    a
    tank,
    be started immediately.
    Since the last hearing,
    a number of events have occurred, but
    certainly the
    one with
    the most impact on the Utility’s operations
    is
    the signed contract with the Ayrshire Coal Company which
    is con-
    structing
    a coal mine near Keensburg,
    Illinois.
    This contract
    provides
    that the Utility shall provide the mine with electric
    power for
    the next ten years
    (at least),
    the present length of
    the agreement.
    The mine will be completely constructed by December
    of
    1972 and its
    need
    for electrical power will reach 10,000 kilo-
    watts within
    18 months after the completion of construction.
    Dur-
    ing
    the construction period the mine will
    use about 1500 kilowatts,
    which will be supplied by the Utility.
    In order
    to be able to get
    the anticipated demand to the mine,
    the Utility
    is planning to con-
    struct
    a
    69
    NV line between the Mt. Carmel station and
    the Village
    of Keensburg.
    This
    line when completed will
    be able
    to deliver
    the estimated peak demand of the mine which,
    as stated,
    is antici-
    pated
    to be 10,000 kilowatts by
    the middle of
    1974.
    The Utility
    already has
    a 12.4
    NV line between the
    Mt.
    Carmel station and
    Keensburq
    which
    will
    be
    able
    to
    deliver
    the
    needed
    electric
    power
    to
    the mine during the construction period.
    The
    69
    NV line to
    Keen~burg will be completed
    by January,
    1973 and will
    cost $240,000.
    In addition to
    the
    69 NV line
    to Keensburg,
    the Utility is
    also planning to construct
    a 138
    NV line from Keensburg to Albion
    where CIUCo has
    a generating station.
    By
    the addition of this
    line,
    which will be completed by June,
    1974,
    the Utility will be able to
    buy power from CIPC0
    for all of
    its customers,
    including
    the mine.
    The Utility has not yet acquired the
    right--of-way
    for
    this line,
    but it e:~pectscompletion
    by 1974 at
    a total cost
    of $260,000.
    Also,
    when
    this line
    is
    completed,
    the Utility says Boilers
    *1
    ai~d #4 will
    no longer be needed except on
    an emergency basis
    (“cold standby”)
    -
    Presently,
    the Utility buys
    power
    from CIPC0
    and this
    is
    trans—
    mitted over
    a 69
    NV between
    Mt.
    Carmel and Lawrenceville.
    This line,
    plus Boilers
    #1
    and
    #4,
    is
    sufficient
    to supply the power necessary
    for the customers
    (including the mine)
    of the Utility during the time
    when Boiler #5
    is
    down
    for
    the
    conversion.

    Now, we must look
    at the program suggested by
    the Utility.
    First,
    the Utility plans to shut Boiler
    #5 down
    in January,
    1973,
    for
    the
    conversion
    of
    that
    unit from
    a coal-fired furnace to
    a
    boiler
    which
    is
    capable
    of
    burninc~ oil
    and
    gas.
    The
    cost
    of
    this
    conversion will be $180,000 and will be commieted by
    the
    Utility’s
    contractor,
    Babcock and wilcox,
    by June
    30,
    1973.
    There seems
    to
    be
    no quarrel with
    the amount of time necessary for the conversion,
    that
    is,
    six months from the
    time when Boiler
    #5
    is shut down,
    but the Agency did make
    the
    point,
    and recommendation,
    that perhaps
    Boiler
    #5 could be shut down
    in
    October,
    1972,
    rather
    than
    January,
    1973.
    The Utility admitted
    that it could buy sufficient power
    from CIPC0 to replace the amount generated by Boiler
    #5, but at an
    increased cost
    if the power
    is purchased in October,
    rather than
    January.
    We think
    the slight cost of buying
    this power earlier
    and thereby starting
    the conversion earlier is worth
    it.
    The
    Utility
    has,
    as
    the previous record points out
    (and this record
    does too), been financially
    successful.
    Total income
    for the year
    ending June
    30,
    1971, was almost $180,000.
    True,there has been
    a
    reducing income for t~e last few veers, but
    the record
    is also
    clear
    that there has been no increase
    in rates
    for some time.
    The
    Utility can afford the slight cost for buying
    the additional mower
    earlier
    so that the peopl2
    of Mt.
    Carmel
    will have three less
    months
    of excessive particulates
    in
    the air
    as
    a result of
    the coal—
    fired
    unit.
    We will, therefore,
    rec~uirethat the Utility shut down
    Boiler
    #5
    on October
    1,
    1972 and complete the conversion by March
    30,
    1973,
    rather than June
    30,
    1973.
    The second phase of the proJram is the completion of the
    69
    NV
    line between Mt. Carmel
    and
    Keensburg.
    The schedule
    for completion
    is January
    1973,
    and this
    seems
    from
    the testimony the best that the
    Utility can do.
    The third phase of the program
    is
    the construction
    of the
    138
    K’! line between Keensburg
    and Albion,
    connecting the CIPCo plant
    to the mine and
    the Mt.
    CarmeJ
    plant.
    The
    line
    is
    to be completed
    by the middle of
    1974, which seems
    a
    long way
    off.
    Since
    the
    Utility
    is committed
    ~
    the construction
    of this
    line,
    it would
    seem that
    they should proceed “post haste” and complete
    it.
    We recog-
    nize that
    the
    right-of-ne:
    oust
    be
    established
    and that the Utility
    must
    work
    closely
    ‘b
    ti:
    Cc
    in
    having
    the
    line
    constructed.
    But
    we
    think
    that
    it can do built
    faster
    and
    therefore
    will
    require
    that
    the Utility exercise
    every
    effort
    to complete the line before June
    of 1974.
    We wi1
    require
    reports
    from the Utility to both the
    Board
    and
    the
    Agency
    to
    advise
    both
    groups
    of
    the
    progress
    being
    made
    to
    speed
    up
    construction
    Of
    this
    line.

    The
    fourth
    phase
    of
    the
    Utility’s
    program
    revolves
    around
    Boilers
    #1
    and
    #4.
    The
    Utility
    does
    not
    plan
    to
    put any control
    equipment
    on these two remaining boilers.
    The plan is to keep
    them
    in
    full
    operation
    until
    the
    138
    NV line
    is
    installed and
    operating
    which,
    the
    Utility
    has
    said,
    will
    not
    be
    until
    June,
    1974,
    but
    which
    this
    Board
    has
    required
    the Utility to make every
    effort
    to
    complete
    earlier.
    Thus,
    if
    the
    138
    NV
    line
    is completed
    earlier,
    Boilers
    #1
    and
    #4
    will
    be
    taken
    off
    the
    line
    earlier.
    We
    agree
    that
    from
    the
    testimony
    Boilers
    #1 and
    #4
    are necessary to
    operate
    until
    the
    138
    Ky
    line
    is
    completed,
    which
    at
    the
    latest
    will
    be
    June,
    1974.
    The
    concern,
    however,
    of
    the
    Board
    is
    the
    Utility’s
    use
    of
    the
    boilers
    after
    the
    138
    K’!
    line
    is
    completed.
    The Utility plans to keep
    the boilers on “cold standby”
    for
    an
    indefinite
    period
    of
    time.
    This
    means
    that
    the
    boilers
    will
    be
    used
    in
    case
    the
    Utility
    does
    not
    have
    adequate
    power,
    either
    produced or purchasable,
    to supply the demands of its customers.
    It is possible,
    then, under
    the Utility’s program that the boilers
    will be
    used after June of 1974 without any emission controls.
    The Utility did state that in
    1974 it
    “may decide” to install
    control equipment
    on the boilers.
    However,
    this Board
    feels that
    if the boilers are to be operated after June
    30,
    1974,
    or when
    the
    138
    NV
    line is completed, whichever occurs first,
    for
    reason,
    including
    “cold
    standby”,
    the
    boilers
    should
    be
    operated
    so
    as not to violate the regulations
    governing
    the
    control
    of
    air
    pollution.
    Based upon previous testimony,
    this means that control
    equipment must be installed and operating at that time to reduce
    the
    particulate
    emissions.
    Thus,
    we
    do
    not
    prohibit
    .the omeration
    of the boilers after the aforementioned dates, but we do prohibit
    the
    illegal operation of those boilers at that
    time,
    The Utility
    has adequate time between now and
    1974 to plan
    for the installa-
    tion of control equipment
    if
    the Utility feels
    that operation of
    the boilers, even as reserves,
    is
    necessary
    after
    1974.
    Thus,
    the Utility will be granted
    a variance subject to the
    conditions
    detailed
    above.
    One
    other
    point
    must
    be
    dealt
    with.
    The
    Utility
    has
    con-
    sistently taken the position that
    its
    boilers
    do
    not
    violate
    the
    existing particulate emission standard.
    We
    heard this
    in the first
    variance case
    and said
    that the Utility did,
    in fact,
    violate the
    regulations.
    Again
    in
    this
    proceeding,
    the Utility attempted to
    prove
    that
    it
    was
    not
    violating
    the
    particulate
    emission
    standard.
    The hearing officer denied
    the Utility the right
    to produce such
    evidence and we agree with the hearing officer’s ruling.
    The
    Utility had already had its opportunity
    to raise
    the question before,
    3
    28

    and we disagreed with
    it at that
    time.
    It was not a proper sub-
    ject of this hearing.
    The Utility sought
    a variance
    so that it
    could violate the
    law.
    If
    it truly believed that it was not
    violating
    the regulations,
    no variance would be necessary.
    Ap-
    parently,
    the Utility doesn’t want to take
    a chance.
    This opinion constitutes
    the Board’s findings of fact and
    conclusions of law.
    ORDER
    Based upon the testimony and exhibits in the record,
    the
    Board hereby orders that
    the variance requested by
    the Utility be
    and
    is hereby granted from the particulate emission standards and
    Section
    9(a)
    of
    the Environmental Protection Act,
    subject to the
    following terms
    and conditions:
    1.
    This variance shall continue
    for
    a period of one year
    from this date.
    If the Utility wants
    a continuance
    of this variance
    it shall file
    a petition for renewal
    of the variance within ninety
    (90)
    days prior
    to the
    date
    the variance expires.
    The Board may authorize
    a
    hearing on that supplemental petition and shall make
    such further order as it deems necessary at that time.
    2.
    The Utility shall proceed with
    the following program:
    (a)
    The Utility shall complete the conversion
    of Boiler #5 from
    a coal-fired boiler to
    a
    boiler fired by oil
    and natural gas by
    March
    30,
    1973;
    (b)
    The Utility shall complete the
    69
    K’! line
    from Mt.
    Carmel to Keensburg by January,
    1973;
    (c)
    The Utility shall exert every effort to com-
    plete
    the 138
    K’! line
    from Keensburg to
    Albion before June,
    1974.
    In that respect
    the Utility shall
    file quarterly reports
    with
    the Board and
    the Agency, beginning on
    December
    1,
    1971, which reports shall detail
    the efforts made by
    the Utility to expedite
    the completion of the 138
    K’! line herein des-
    cribed;
    and
    3—29

    (d)
    The Utility shall not operate Boilers
    #1
    and
    #4
    in
    violation
    of
    the
    particulate
    regulations after the installation of the
    138
    K’! line referred to
    in paragraph
    4,
    or June
    30, 1974, whichever occurs
    first.
    3.
    The
    Utility
    shall
    post
    a
    bond
    in
    a form approved by
    the
    Agency
    to
    guarantee
    performance
    of
    the
    conditions
    of the granting of this variance.
    Said bond shall be
    in the amount of $500,000.
    4.
    Failure
    to
    comply
    with
    any
    of
    the
    conditions
    of
    this
    variance shall result in the revocation of the grant
    of this variance.
    I,
    Christan Moffett, Acting Clerk of
    the Illinois Pollution
    Control Board, certify that
    the Board adopted the above Opinion
    and Order on
    this
    ~/
    day
    of November,
    1971.
    ~
    ~,
    Christan Moffett,
    Acting
    Clerk
    3~)

    Back to top