ILLINOIS POLLUTION CONTROL BOARD
    October
    3,
    1972
    JOHN W. BENDER
    )
    v.
    )
    #
    72—324
    ENVIRONMENTAL PROTECTION AGENCY
    Opinion
    & Order of the Board
    (by Mr. Currie):
    Mr.
    Bender seeks permission to connect
    a new single
    family dwelling
    to a Waukegan sewer.
    Connections to all
    sewers in the North Shore Sanitary District were forbidden
    by our order of March 31, 1971
    (League of Women Voters
    v.
    NSSD,
    #70-7,
    1 PCB 369).
    Mr. Bender began excavating
    for his home October 11,
    1971,
    the foundation was erected
    November
    1,
    and construction
    is now at least 75
    complete.
    In cases in which construction was begun before the
    connection ban was imposed, we have generally allowed variances
    because of the commitment of substantial resources
    in
    good faith reliance on the expectation of ability to connect,
    and because of the danger of vandalism or other damage to
    an unoccupied structure.
    See, e.g., Illinois National Bank
    of Springfield v.
    EPA,
    #72—307,
    5 PCB
    (Oct.
    3,
    1972)
    On the
    other hand, we have held that one who proceeds to
    construct
    a home with knowledge that a connection ban has
    been imposed assumes the risk that the ban will not be lifted
    in time for him to connect when he desires;
    to hold other-
    wise would allow a builder to avoid the ban simply by defying
    it.
    Cook v.
    EPA,
    #72-178,
    5 PCB
    (Aug.
    29, 1972).
    Mr. Bender concedes that he took a calculated risk when
    he began construction with knowledge that no connection could
    be had until the ban was lifted.
    However, he argues, the
    ban was initially imposed on the basis of inadequate facilities
    for treating sewage once it reached the plant:
    It seemed logical
    to me that by the time
    I would be
    in need of
    a sewer the Districtvs treatment plants
    would be upgraded to the point where the ban would be
    relaxed.
    As he observes, this prediction was correct, since our orders
    of January
    31 and March
    2,
    1972
    (North Shore Sanitary District
    v,
    EPA, #71—343,
    3
    PCB 541 and 697) did in fact authorize the
    District to allow additional connections on the basis of
    treatment plant improvements,
    What he did not foresee when
    he began construction was that our later decision would
    5—591

    —2--
    limit relief from the ban on the ground that certain sewers,
    later designated by
    the Agency, were inadequate to transport
    their present waste loads to the plant for treatment:
    I applied for
    one
    of these permits from the Sanitary
    District but was informed by letter
    5 June 1972 that my
    lot was in an area of the city on which the Environmental
    Protection Agency had placed a ban.
    This sewer ban
    was placed on Waukegan
    21 April 1972.
    My house was
    about 75
    complete on this 21st day of April 1972.
    As a technical matter,
    it would be possible for us to
    take the position that the original connection ban has never
    been lifted with regard to the sewers in question, although
    the reason for forbidding connections has changed.
    But the
    outcome of this case should depend upon the Detitioner’s
    legitimate expectations and not upon technicalities as to
    whether there was one ban or two.
    The risk Mr. Bender
    voluntarily assumed was the risk that treatment plant improve-
    ments would be delayed, not that an unforeseen and unrelated
    problem with the adequacy of the sewer itself might inter-
    vene.
    His expectations with regard to the transport problem
    were just the same as they would have been if there had
    never been a ban based on the treatment problem.
    Only a single house, with limited wastes,
    is involved.
    Mr. Bender has expended considerable personal effort in building
    it in his spare time.
    He has alleged substantial and credible
    hardships resulting from double housing payments and the
    nonuse of substantial savings if the house must stand empty.
    His neighbors have filed a petition asking that we grant the
    variance to protect the neighborhood
    from vandalism.
    We believe we should take the above facts, none of which
    are disputed,to indicate that Mr. Bender commenced construction
    before he had reason to know of the present cause of his in-
    ability to connect; that he assumed the risk only of a de-
    lay in treatment plant improvements; and that we should
    allow the variance under the doctrine of the Illinois National
    Bank case cited above.
    We note that we were most favorably impressed by Mr. Ben-
    der’s forthright and forceful presentation of his own case
    before the Board.
    ORDER
    John W. Bender is hereby granted a variance to permit
    connection of his home at 339 Pioneer Road,
    Waukegan,
    to the
    appropriate municipal
    sewer.
    5
    --
    592

    —3--
    I, Christan Noffett, Clerk of the Pollution Control Board,
    certify tha~tthe Board adopted the above Opinion
    & Order
    this
    ~
    day of October, 1972, by a vote of
    ~
    C
    ~7
    /
    5
    593

    Back to top