ILLINOIS POLLUTION CONTROL BOARD
June
9,
1971
ELECTRIC WHEEL CO.
V.
)
BCE
#
71—55
ENVIRONMENTAL PROTECTION AGENCY
Opinion of
the Board
(by Mr. Currie):
Electric Wheel operates an iron foundry in Quincy whose
particulate emissions exceed those allowed by
the Rules and
Regulations Governing the Control of Air Pollution.
The company’s
program for bringing its emissions into compliance
(ACERP)
was approved
by the Air Pollutior Control Board
in 1969,
with
a compliance date
of April,
1972.
The company petitions for approval of
a modification of this
program,
saying it now expects compliance by December
31,
1971.
Because it seemed unlikely we would
find
a need
to shut
the company
down this close to the end of
a three—year program approved by
our
predecessors
and pursued with more than
good
faith,
we did not
schedule
a hearing, believing
the case could easily be resolved on
the basis of the Agency’s recommendation.
But the Agency made no recommendation on
the merits;
it
requested
us
to hold
a hearing,
on
the ground the petition did not allege facts
sufficient
to enable us
to make an informed decision.
Had we received
this request in reasonable time,
we should of course have held
a
hearing.
The Agency is entitled to put its case,
and to put the
petitioner
to its proof.
But the petition was filed on March 19
and the Agency’s motion was not filed until May
24
--
two months
later
and less than thirty days before the date on which, under
the 90-day statutory limit,
the Board mustdecide
the case.
By
the time we were asked to hold
a hearing it was oractically impossible
for us
to do
so.
And we are left with no guidance yet from the
Agency as to how the case should be decided.
The statute requires
the Agency
to file
its recommendations
“promptly”
(Section 37),
and we
urge that it do
so
inthe
future.
Not only is this necessary if
the Board is
to act upon
a full
record
within
the statutory period, which is difficult enough
at best,
Both
the petitioner and
the public have
a right to expect
a prompt
decision; any unnecessary delay can only serve to defer
the correction
of pollution and
to discredit the control program.
in the absence of
a hearing,
and
on the basis
of the only
information before us,
we think the petitioner has established that
the revised program is
a decided improvement on
the one approved in
1969.
While
an ACERP must,
like any other variance,
be renewed
annually on
a showing of adequate progress
(section
36
(b))
,
and
while we have authority
to reexamine, when asked to renew an ACER?,
the entire question whether the hardships of immediate compliance
1
—
689
(i.e., shutting down)
seriously outweigh the benefits
(see EPA
v.
Commonwealth Edison Co.,
#
70—4, February
17,
1971), we will not
automatically assume
the Air Pollution Control Board was
in error
in approving the original program.
We are always prepared to receive
evidence
that it was, given time
to hold
a hearing.
But we give some
weight here,
as
we have before
(see Sandoval Zinc
Co.
v,
EPA,
#
71-10,
April
14,
1971),
to the fact of APCB approval
and to the company’s
good faith reliance in carrying out
the approved program.
Giving the precedent of
the APCB approval due weight;
considering
the short time remaining before compliance,
the fact that the old
cupola will be progressively
less used during the debugging period
that is
to begin within the coming week,
the nontoxic nature of the
emissions,
the company’s location in an industrial
zone,
and the
fact that a denial of this renewal would put over 100 employees out
of work,
and in the absence of any contrary evidence, we
think the
variance should be granted subject to certain conditions.
This opinion constitutes
the Board’s findings of
fact and
conclusions
of law.
ORDER
Electric Wheel
Co.
is hereby granted permission
to emit
particulate
air contaminants
from its cupola in Quincy,
Illinois,
subject to the following conditions:
1)
This variance shall terminate December
31,
1971,
2)
Electric Wheel
Co. shall conform to all conditions
of its
Air Contaminant Emission Reduction Program approved by the
Air Pollution Control Board
in 1969,
including the filing
of progress reports.
3)
The emission of contaminants
shall not be increased during
the period of this variance.
4)
The company shall adhere
to the following schedule of
improvements
as described in its petition:
a)
installation complete and new equipment to begin
operation by June
15,
1971;
b)
Shutdown of existing cupola melting furnace, by
December
31,
1971,
5)
After June
15,
1971
the company shall make maximum use
of
the new equipment consistent with debugging requirements
and shall utilize the present cupola melting furnace only
to the extent necessary to avoid
a reduction in pre—existing
production levels during debugging,
6)
The company shall post with
the Agency before July
15,
1971,
a bond or other security in the amount of $20,000, which
shall be forfeited in the event the terms of this order
are violated.
I,
Regina E.
Ryan, Clerk of the Board, certify
4h~t
the Board adopted
the above Opinion and Order this
~day
of
_________,
1971.
y
~
~//
-
-
1
—
691