ILLINOIS POLLUTION CONTROL BOARD
    June 17,
    1993
    RONALD E. TEX and
    SUSAN
    D.
    TEX,
    )
    )
    Complainant,
    v.
    )
    PCB 90—182
    (Enforcement)
    S.
    SCOTT COGGESHALL and
    )
    COGGESHALL CONSTRUCTION COMPANY,)
    CHESTER BROSS, MIKE BROSS,
    )
    CONSTRUCTION COMPANY,
    )
    )
    Respondent.
    OPINION AND ORDER OF THE BOARD
    (by G. T. Girard):
    On October 29,
    1992,
    the Board entered an interim opinion
    and order finding respondents in violation of Section 901.102(a)
    of the Board’s noise rules.
    (35 Ill. Adm. Code 901.102(a).)1
    The BOard directed respondents to prepare a study of the
    “economic reasonableness and technical practicability of the
    control options outlined by Gregory Zak as well as any additional
    options which it may deem appropriate to reduce the noise
    emissions from the asphalt plant”.
    (10/29/92 at 16.)2
    The
    Board directed the respondents to file such study no later than
    March 15,
    1993,
    and allowed the complainants until April 15,
    1993
    to respond.
    The Board notes that on December 3,
    1992,
    the Board granted
    a motion by the respondent suggesting the death of
    S.
    Scott
    Coggeshall and dismissed S.
    Scott Coggeshall from the proceeding.
    The respondents filed the study on March 15,
    1993.
    Complainant,
    after being granted an extension of time by the Board on April
    22,
    1993,
    filed its response on May 5,
    1993.
    On May 14,
    1993,
    respondents filed a request for leave to file a reply.
    The Board
    hereby grants the motion to file a reply pursuant to 35
    Ill.
    Adm.
    Code 101.241(c).
    1
    The Board directs readers to the October 29,
    1992, Interim
    opinion and Order
    for
    case details which will
    not
    be
    repeated
    herein.
    2
    The Board will cite the October 29,
    1992,
    Interim Opinion
    and Order as “10/29/92 at
    _“;
    the Board will cite the respondents
    report as “R.rep. at
    _“
    and the respondents reply as “R.rply at
    _“;
    the Board will cite the complainants response as “C.res.
    at
    ‘I
    0
    L~3-O
    I 57

    2
    DISCUSSION
    In detemining the proper remedy in an enforcement case, the
    Board must consider the factors set forth in Section 33(c)
    of the
    Environmental Protection Act
    (Act).
    (415 ILCS 5/33.)
    Section
    33(c)
    of the Act provides:
    In making its orders and determinations, the Board
    shall take into consideration all the facts and
    circumstances bearing upon the reasonableness of the
    emissions,
    discharges,
    or deposits involved including,
    but not limited to:
    1.
    the character and degree of injury to,
    or
    interference with the protection of the
    health, general welfare and physical property
    of the people;
    2.
    the social and economic value of the
    pollution source;
    3.
    the suitability or unsuitability of the
    pollution source to the area in which it is
    locate, including the question of priority of
    location in the area involved;
    4.
    the technical practicability and economic
    reasonableness of reducing or eliminating the
    emissions, discharges or deposits resulting
    from such pollution source; and
    5.
    any subsequent compliance.
    The Board has previously considered the Section 33(c)
    factors in this case.
    (See 10/29/93 at 13—15.)
    The Board finds
    that the additional filings submitted pursuant to the October 29,
    1993 Board order provide no new evidence regarding the Section
    33(c)
    factors in this record,
    except for Section 33(c) (iv).
    Therefore, the Board will not reiterate its previous holdings on
    Sections 33(c)(i)(ii)(iii)
    and
    (v).
    The discussion following
    summarizes the parties’ positions regarding the economic
    reasonableness and technical practicability (Section 33(c) (iv))
    of the control options.
    Respondents’ study.
    Respondents retained the services of Dr. Paul Schomer of
    Schomer
    & Associates to study the noise problem at the plant.
    According to respondents the study concentrates on determining
    the predominant noise sources and developing noise mitigation
    01
    L~.3-Q
    158

    3
    evaluation of the remedies recommended by Mr. Greg Zak of the
    Agency.
    Dr. Schomer’s study utilizes noise emission measurements
    from the various components of the plant to determine the
    contribution of each component to the overall noise emissions.
    The noise measurements were obtained by monitoring the emissions
    during full plant operation and when gradually decreasing the
    plant operation sequentially by turning off the various plant
    components3.
    (R.rep.
    Exh.
    B at 4.)
    Based on the results of the
    noise monitoring,
    the study concludes that the predominant
    sources of noise from the plant are the bag house blower
    (high
    frequencies)
    and burner operation
    (low frequencies).
    (R.rep.
    Exh.
    B at 7—S.)
    In addition,
    the study notes that the mechanical
    equipment noise is important in the 1000
    2000 Hz range, and the
    fire blower may contribute significantly at certain frequencies.
    (R.rep Exh. B at 7-8.)
    The study also includes a comparison of the noise emission
    levels at full plant operation with the applicable standards
    under the Board regulations.
    The comparison indicates that noise
    levels must be reduced by
    6,
    3,
    7, and
    4 dB at 125,
    1000,
    2000,
    and 4000 Hz bands,
    respectively, to comply with the Board
    Standards.
    (R.rep Exh.
    B,
    Fig.
    11.)
    The respondents’ study includes an evaluation of the
    following options for reducing the noise emission levels from the
    plant:
    1.
    The construction of barrier walls around the
    burner and generator as well as adding a stack
    silencer;
    2.
    Re—engineering of the plant
    (as suggested by
    Gregory Zak);
    3.
    Encapsulating the plant
    (as suggested by Gregory
    Zak); and
    4.
    Moving the plant.
    (R.rep.
    at 2.)
    With regard to the suggestions offered by Mr.
    Zak
    (points
    2
    and 3), Dr. Schomer’s study notes that both options would be very
    expensive.
    According to the study,
    the cost of re—engineering
    (and rebuilding)
    the plant or enclosing the plant in a reinforced
    concrete structure could easily cost $100,000 or more.
    (R.rep.
    ~ The plant components include generator, mechanical equipment
    and material feeds,
    bag house blower, and fire blower.
    0iL~.3~0159

    4
    Exh. B at 10-il.)
    In addition, the study notes that enclosing
    the plant in a reinforced concrete structure without noise
    control would result in very high noise levels within the
    structure.
    Such high noise levels would violate Occupational
    Safety and Health Administration
    (OSHA) noise limits.
    (R.rep.
    Exh. B at 10-11.)
    Further, with regards to the suggestion that
    the plant be moved,
    respondents state the costs to move the plant
    as well as obtaining an alternative site are “not economically
    reasonable”.
    (R.rep.
    at 2.)
    Dr. Schomer’s study recommends that the following steps be
    taken to alleviate the noise levels:
    1.
    Retain the wooden barrier wall installed around
    the generator or replace the same with a more
    permanent structure to minimize the generator
    noise.
    The cost of a new permanent wall is
    estimated to be less than $10,000;
    2.
    Install a stack silencer to reduce the bag house
    blower sound emitting from the stack.
    The cost of
    the silencer is estimated to be in the order of
    $5,000;
    3.
    Install a barrier wall close to the inlet of the
    fire—burner fan to reduce the burner noise.
    The
    cost of the barrier wall will be in the order of
    $10, 000.
    (R.rep. Exh. B at
    12..)
    The study concludes that the recommended solutions are
    technically feasible,
    and the implementation of the same would
    result in significant reduction of the noise levels at the
    complainants’ structure.
    Further, the study notes that
    implementing all the recommendations may not result in overall
    compliance with the Board standards in the 1000 and 2000 Hz bands
    due to mechanical equipment sound.
    (R.rep.
    Exh. B at 13.)
    Finally, Dr. Schomer’s study notes that any further significant
    reductions in the noise levels over the reduction that will be
    realized by the recommended methods would require the re—
    engineering of the plant.
    (R.rep. Exh.
    B at 13.)
    Complainants’ response.
    Complainants ask that the Board “direct that the plant be
    moved as a technically practical and economically reasonable
    means of bringing compliance” with the Board’s regulations.
    (C.res. at 4.)
    In support of the position that moving the plant
    is economically reasonable and technically feasible, the
    complainants provided an affidavit from Michael J. McGillicuddy,
    vice president and Macomb Branch Manager of Illinois Valley
    Li
    I
    4 ~

    S
    Paving Company.
    Mr. McGillicuddy states that the cost of moving
    a “Batch type plant”
    is approximately $75,000.
    (C.res.
    Exh. B.)
    Complainants specifically responded to the remaining control
    options as well.
    With regard to encapsulating the plant,
    complainants state:
    “the Schoiner report agrees with Mr.
    Zak that
    encapsulating the plant in concrete is the most expensive and
    least—feasible alternative.”
    (C.res.
    at 2.)
    Regarding re—
    engineering the plant, the complainants state:
    “Mr.
    Schomer
    dismisses,
    in a cursory way, the possibility of re—engineering
    because it would cost over $100,000.00.”
    (C.res.
    at 2.)
    The complainants maintain the Dr.
    Schonier recommends the
    least expensive procedure (that of constructed barrier walls and
    adding a stack silencer), however;
    least expensive is not
    “synonymous with economic reasonableness” according to
    complainants.
    (C.res. at 2.)
    Further, the complainants state:
    “Despite Mr. Schomer’s very considerable training, experience and
    writings qualifying him as an acoustical expert, this very
    considerable technical background does not establish him as an
    economic expert qualified to evaluate the ‘economic
    reasonableness’ of any option from the prospective
    (sic
    of the
    cost of that option compared to the economic benefit to the plant
    to the respondents and the present operator.”
    (C.res. at 3.)
    Complainants also argue that respondents study does not
    address,
    “in other than a conclusory manner”, the economic
    reasonableness of any control measures except in Exhibits C and
    D.
    (C.res. at 3.)
    The complainants then assert that Exhibit D,
    an affidavit by Mike Hillyer,
    “is substantially different from
    the testimony of witness Michael Hillyer”.
    (C.res. at 3.)
    Respondents’ reply.
    Respondents reply that the testimony of Mr. Hillyer did not
    address “site availability for the asphalt plant nor did he
    address costs of site amenities similar to the Deere Road plant
    site”.
    (R.rply at 2.)
    The respondents assert that those costs
    are addressed for the first time in Exhibit D of its report.
    The
    respondents also point out that the Illinois Valley Paving
    Company operates a drum-mix plant while the Coggeshall plant is a
    batch plant.
    (R.rply at 2.)
    The respondent argues that it would
    require
    6 weeks to move the Coggeshall plant and cost $100,000.
    (R.rply at 2.)
    Section 33(c) (iv).
    The Board notes that all the alternatives considered
    in the
    respondent’s noise study appear to be technically feasible.
    However, the Board notes that there
    is a significant difference
    between the implementation cost of the options recommended by the
    respondent and the complainants,
    The option recommended by the
    I
    ~,
    ‘)
    (~
    UI”rU
    U

    6
    respondents’ study, which includes the construction of barrier
    walls and installation of a silencer would cost approximately
    $25,000.
    Whereas, the option supported by the complainants,
    which essentially requires the plant to be moved to another
    location would cost over $100,000.
    The options suggested by Mr.
    Greg Zak, which
    includes encapsulation and re—engineering would
    also cost more than $100,000.
    Therefore, the Board must evaluate
    the economic reasonableness of implementing the various options
    in crafting a remedy.
    The Board notes that both parties seem to agree that
    encapsulating the plant, which has been estimated to cost
    $100,000 is expensive.
    Regarding re-engineering the plant,
    Mr.
    Zak stated that this option
    is not practicable because of the
    cost which would exceed $100,000.
    (Tr. 1/8/92 at 106-110;
    10/29/92 at 14.)
    Dr. Schomer agrees that re-engineering would
    cost over $100,000.
    The complainants offer no evidence to refute
    either Mr.
    Zak or Dr.
    Schomer.
    The respondents’ study includes two different estimates of
    the moving costs.
    The first estimate, which includes the cost of
    moving a “batch” plant to a new site ranges from $60,000 to
    $100,000.
    (R.rep.
    Exh.
    C)
    The Second estimate, which includes
    only the cost of acquiring land, establishing gas service, rock
    base,
    fencing, maintenance buildings and building hook—ups ranges
    from $256,416 to $411,416.
    (R.rep. Exh.
    D.)
    The evidence
    submitted by the complainants indicate that moving the plant
    would cost $75,000.
    (C.res.
    Exh. B.)
    The moving cost reflects
    dismantling, moving, and erecting a batch type plant at a new
    location.
    The complainants estimate that the total cost of
    making the plant operable at the new site would be
    in the range
    of $90,000 to $125,000.
    (C.res. Exh.
    B.) The total cost
    includes,
    in addition to moving cost, the cost of site
    preparation,
    land acquisition, and initial operation.
    The Board
    notes that there is
    a significant difference between the
    estimates of the moving costs provided by the complainants and
    the respondents.
    However, the Board notes that even if it
    considers the lower cost estimate, the cost of moving the plant
    would be in excess of $100,000, which amounts to the same as that
    of encapsulation or re—engineering.
    Therefore, the Board finds moving the plant to be also in
    the same category of the expensive options.
    In view of this, the
    Board finds that encapsulation, re—engineering the plant,
    or
    moving the plant are not economically reasonable remedies.
    The
    Board believes that requiring the implementation of these options
    would place a significant financial burden on the respondents.
    Finally, the option recommended by the respondents, which
    includes the construction of barrier walls and installation of a
    stack silencer would cost in the order of $25,000.
    iJ
    ~~3-Cj
    I 62

    7
    The Board finds that the noise control methods recommended
    by the respondents to be an economically reasonable and
    technically feasible approach to reduce the noise problems at the
    plant.
    The Board notes that the this option costs relatively
    less than the other expensive alternatives discussed above, but
    achieves a significant reduction in the noise levels.
    The Board
    recognizes that implementing the recommended option may still
    result in a violation of Section 901.102 standards by
    1 to
    2 dB
    in the 1000 and 2000 Hz bands.
    However, considering the cost
    implications, the Board believes that the respondents’
    recommended option is the most appropriate solution.
    CONCLUSION
    Although complainants request that the Board direct that the
    plant be moved, the Board is reluctant to direct such a step in
    this case.
    As stated in the October
    29,
    1992, Opinion, the plant
    is in a suitable location in an area zoned for industry.
    The
    Board finds that moving the source at a cost of over $100,000 to
    be economically unreasonable.
    Therefore,
    after studying all the options the Board finds
    that construction of barrier walls and the addition of a stack
    silencer are economically reasonable and technically practicable
    solutions which will bring respondent into compliance.
    However,
    the Board notes that if the respondent is still
    in violation of
    Section 901.102 standards after implementation of the measures,
    the respondent could be liable for civil penalties under the Act,
    absent site—specific relief.
    ORDER
    Respondents shall take,
    at a minimum, the following steps to
    alleviate the noise emissions from the asphalt plant located in
    Macomb, Illinois:
    1.
    Replace the existing wooden barrier wall around the
    generator with a more permanent structure;
    2.
    Install a 24” by 72” stack silencer such as the
    Industrial Acoustic Company’s IAC Model SL3 silencer;
    and
    3.
    Construct a barrier wall as close to the inlet of the
    fire-burner fan as feasible.
    The barrier wall shall be
    at least 2.5 feet taller than the top of the opening
    for the burner
    in the end of the drum.
    The length of
    the wall shall be three times its height and it shall
    be centered at the burner.
    The barrier wall shall be
    01
    L3-0
    163

    8
    made of sound absorbing material such as SoundBlox~or
    IAC Moduline~
    IT IS SO ORDERED
    Board Member R.
    C.
    Fleinal dissents.
    Section 41 of the Environmental Protection Act (415 ILCS
    5/41
    (1992)) provides for the appeal of final orders of the Board
    within 35 days.
    The Rules of the Supreme Court of Illinois
    establish filing requirements.
    (See also 35 Ill. Adm. Code
    101.246, Notion for Reconsideration.)
    I, Dorothy M. Gunn,
    Clerk of the Illinois Pollution Control
    Board, hereby certify that the above opinion a
    order was
    adopted on the
    /7~Z
    day of
    ____________________
    1993, by a vote of
    ~,-/
    ~
    A~’
    ~borothy
    M.
    Gi~in, Clei~k
    Illinois Polijition Control Board
    1)
    ~.3-OI 6~.

    Back to top