This matter comes before the Board on a petition filed on
July
10,
1992.
Since the filing of the petition, respondent has
filed
several motions for extension of time to file the Agency
record in this matter, citing on-going negotiations between
respondent and petitioner.
On August
3,
1992, petitioner filed
an open waiver of the decision date.
On April 23,
1993, the
parties filed a joint status report and motion to extend time to
file record.
The parties anticipate that this matter will be
resolved by the adoption of rulemaking R93-9.
R93-9,
In the
Matter Of:
Omnibus Cleanup of the Volatile Organic Material RACT
Rules Applicable to Ozone Nonattainment Areas:
Amendments to 35
Ill.
Athn.
Code Parts
203,
211,
218 and 219,
is a “fast—track” air
rulemaking being conducted pursuant to the expedited procedures
of Section 28.5 of the Environmental Protection Act
(415 ILCS
5/28.5).
Among other things, the proposed rulemaking includes
practices for cooling towers, which are at issue in this appeal.
The
Board anticipates adopting R93—9 by December of 1993.
The
parties request that respondent be given until December 30,
1993,
to file the Agency record.
The parties have committed to submit
additional status reports to the Board within 120 days of the
issuing of this Order.
The Agency’s motion to extend the time in which to file the
Agency
record in this matter until December 30,
1993,
is hereby
granted.
The parties are directed to file a status report
concerning this matter to be received by the Board on
or
before
September
6,
1993.
IT IS SO ORDERED.
1_~I
r)
U~L~~UU
I,
Dorothy M.
Gunn, Clerk of the Illinois Pollution Control
Board, hereby certify that the above order was adopted on the
__________
day of
_________________,
1993,
by a vote of
7/
~
~
~
Dorothy M.
~nn,
Clerk
Illinois Po~ution Control Board
O~L~2-OO2L~.