ILLINOIS POLLUTION CONTROL BOARD
    March 11,
    1993
    )
    OLIN CORPORATION,
    )
    Petitioner,
    )
    V.
    )
    PCB 89—30
    )
    (Permit Appeal)
    ILLINOIS ENVIRONMENTAL
    )
    PROTECTION AGENCY,
    )
    )
    Respondent.
    ORDER OF THE BOARD
    (by,
    J.
    C. Marlin):
    This matter is before the Board on a February 23,
    1993,
    motion by the Illinois Environmental Protection Agency
    (Agency)
    for an extension of time to file a response to Olin’s objection
    and motion to vacate closure plan approval.
    Olin has not filed a
    response to the Agency’s motion.
    The Agency cites previously scheduled meetings relative to
    the Agency attorney’s caseload of enforcement cases as the reason
    an extension of time is needed.
    The Agency also states
    in its
    motion that an extension of time will not prejudice Olin since
    the decision deadline has been extended by Olin until October
    1,
    1993.
    The Agency states that it will be able to prepare and file
    a response with the Board within three weeks of the date the
    motion was filed.
    Accordingly, the Agency’s motion for extension
    of time is granted until 4:30 P.M. on March 16,
    1993.
    IT IS SO ORDERED.
    I, Dorothy N.
    Gunn,
    Clerk of the Illinois Pollution Control
    Board, hereby certify that the above order was adopted on the
    /1
    day of
    ,7-)
    a~_-I~--’
    ,
    1993,
    by a vote of
    ~
    Dorothy M. Gu/~n~Clerk
    Illinois Pollution Control Board
    Ut 140-0001

    Back to top