ILLINOIS POLLUTION CONTROL BOARD
    February 16,
    1995
    CLARENDON HILLS BRIDAL
    )
    CENTER (LEARSI
    AND
    COMPANY,
    )
    INC.),
    Petitioner,
    )
    v.
    )
    PCB 93-55
    (UST Reimbursement)
    ILLINOIS ENVIRONMENTAL
    )
    PROTECTION AGENCY,
    )
    Respondent.
    JAMES p. O’BRIEN
    AND
    ROBERT M. BARATTA, JR., CHAPMAN
    & CUTLER,
    APPEARED ON BEHALF OF PETITIONER;
    JAMES G. RICHARDSON AND JOHN BURDS APPEARED ON BEHALF OF THE
    ILLINOIS ENVIRONMENTAL PROTECTION AGENCY.
    OPINION AND ORDER OF THE BOARD
    (by M. McFawn):
    On March
    18,
    1993 petitioner Learsi and Company filed a
    petition seeking review of an underground storage tank
    reimbursement determination issued by the Illinois Environmental
    Protection Agency
    (Agency).
    Petitioner seeks review of the
    Agency’s denial of reimbursement from the Leaking Underground
    Storage Tank (LUST)
    Fund of $331,404.05 in costs.
    BACKGROUND
    Petitioner
    is the former owner of
    a strip mall located at
    445 Ogden Avenue, Clarendon Hills,
    Illinois, known as the
    Clarendon Hills Bridal Center
    (the site).
    In September 1990,
    petitioner was seeking to sell the site, and hired Mostardi-Platt
    Associates
    (Mostardi—Platt)
    to conduct a phase II environmental
    assessment.
    The phase II assessment revealed that a portion of
    the site, constituting approximately 850 cubic yards of soil, was
    contaminated by petroleum, although no underground storage tanks
    (UST5)
    were discovered at the site at that time.
    (Pet.
    Br.
    at
    1—
    2.)
    Remediation of the site began in October 1990.
    Subsequent
    investigation revealed that the extent of contamination was much
    greater than originally estimated by Mostardi-Platt,
    and revealed
    the presence of three USTs.
    Upon discovering the UST5,
    petitioner notified the Emergency Services and Disaster Agency
    (ESDA)
    on October
    12,
    1990 that a release had occurred at the
    site.
    In November 1990, petitioner submitted a corrective action
    plan to the Agency in order to qualify for reimbursement from the
    LUST Fund.
    The plan was approved by the Agency in January 1991.

    2
    (Pet.
    Br. at 3-4.)
    During the remediation process,
    a fourth UST was discovered
    at the site.
    Eventually,
    the four USTs were removed, and all of
    the contaminated soil was excavated, transported from the site,
    and disposed of.
    The remaining soil satisfied the Agency’s
    established cleanup objectives.
    The Agency issued a clean
    closure letter for the site,
    and petitioner sought reimbursement
    of its corrective action costs from the LUST Fund.
    (Pet.
    Br.
    at
    5—6.)
    On January
    24,
    1991,
    the Agency made a preliminary
    determination that petitioner was eligible to access the UST Fund
    subject to a $100,000 deductible.
    (Rec. vol. A at 25.)
    On
    September 3,
    1992,
    the Agency received petitioner’s completed
    application requesting reimbursement from the UST Fund.
    (See
    Pet.
    Ex.
    17 at 1.)
    The Agency issued its final determination of
    eligibility on February 18,
    1993,
    and issued a clarification on
    April
    29,
    1993.
    The parties agree that the issues in this appeal
    are framed by the February 18,
    1993 final determination letter,
    as clarified by the Agency’s April
    29,
    1993 letter.
    (See
    Pet.
    Br. at
    7;
    Resp.
    Br.
    at 3.)
    A hearing in this matter was held on
    November 17, 1993,
    which was continued on the record on the
    following dates: November 18,
    1993, December 15,
    1993, and
    January
    19,
    1994.
    RULE OF GENERAL APPLICABILITY
    To be deemed reimbursable from the UST Fund,
    remediation
    costs incurred must be corrective action costs.
    Section 57.2 of
    the Environmental Protection Act
    (Act)
    (415 ILCS 5/57.2
    (1992))
    now defines corrective action cost as “activities associated with
    compliance with the provisions of Section 57.6 early
    action
    and
    57.7 investigation
    and remediation) of this Title.”
    In October
    1990,
    corrective action was defined as:
    An
    action to stop, minimize, eliminate or clean up a
    release of petroleum or its effects as may be necessary or
    appropriate to protect human health or the environment.
    This includes, but is not limited to, release investigation,
    mitigation of fire and safety hazards, tank removal,
    soil
    remediation, hydrogeological investigations,
    free product
    removal, groundwater remediation and monitoring, exposure
    assessments, the temporary or permanent relocation of
    residents and the provision of alternate water supplies.
    (Ill.
    Rev.
    Stat.
    1989,
    ch.
    111 1/2, par.
    1022.18(e) (1) (C)
    (repealed).)
    Determining whether costs are corrective action costs
    is a
    two-part inquiry:
    first,
    it must be determined whether the costs
    are incurred as a result of action to “stop,
    minimize,
    eliminate,

    3
    or clean up a release of petroleum,” and second,
    it must be
    determined whether those costs are “the result of activities such
    as tank removal,
    soil remediation, and free product removal.”
    Costs must satisfy both requirements to be deemed reimbursable as
    corrective action.
    (Enteririse Leasing Co.
    v. Illinois
    Environmental Protection Agency
    (April
    9,
    1992)
    PCB 91-174,
    132
    PCB 79,
    83.)
    At the time of petitioner’s reimbursement application,
    Section 22.l8b(d) (4) (C)
    of the Act provided:
    4)
    Requests for partial or final payment for claims under
    this Section shall be sent to the Agency and shall
    satisfy all of the following:
    C)
    The owner or operator provided an accounting of
    all costs, demonstrated the costs to be
    reasonable,
    and provided either proof of payment
    of such costs or demonstrated the financial need
    of joint payment to the owner or operator and the
    owner’s or operator’s contractor in order to pay
    such costs.
    (Ill.
    Rev.
    Stat.
    1989,
    ch.
    111 1/2,
    par.
    1022.18b(d) (4) (C)
    (repealed).)
    In Platolene 500,
    Inc.
    v. IEPA
    (May 7,
    1992) PCB 92—9,
    133
    PCB 259, the Board held that the burden of meeting these
    requirements
    is on the party seeking reimbursement.
    (i~
    at 8.)
    The burden is thus on the party seeking reimbursement to
    demonstrate that the remediation costs were for corrective action
    costs and were reasonable.
    DISCUSSION AND DECISION
    Petitioner seeks review of a total of $331,404.05 in costs.
    The Agency denied reimbursement of these costs on the following
    grounds:
    (1)
    costs lacking documentation;
    (2) costs for
    activities which did not constitute corrective action;
    (3)
    costs
    which were incurred prior to notification of ESDA;
    (4)
    costs
    which petitioner failed to demonstrate were reasonable; and
    (5)
    costs which constituted legal defense costs.
    Each of these
    grounds will be examined separately.
    1)
    Costs Lacking Documentation
    Of the $331,404.05 in costs denied by the Agency,
    $298,786.98 were denied as lacking supporting documentation under
    Section 22. 18b(d) (4) (C).
    (See Pet. Ex.
    17 Attachment A at para.
    2.)
    $251,173.78 of these costs represent costs incurred by

    4
    petitioner pursuant to its contract with Accurate Pump and Tank
    (Accurate).
    $206,245.53 of that amount was based solely upon a
    per cubic yard rate.
    The remaining $44,928.25 attributed to
    Accurate was supplemented by Agency billing forms which included
    a time and materials breakdown of included costs.
    The remaining
    costs represent costs incurred by petitioner for work done by
    four subcontractors.
    a)
    Accurate Pump and Tank
    Petitioner contends that the Agency is improperly denying
    reimbursement of costs paid to Accurate because petitioner failed
    to demonstrate that the costs satisfied a two-part test requiring
    that they either be:
    1) submitted on Agency forms which require a
    time-and-materials breakdown,
    or
    2)
    competitively bid, with at
    least three bidders, where the lowest bid is chosen.
    (Pet.
    Br.
    at 7.)
    Petitioner asserts that this test is merely an Agency
    policy,
    and that there is nothing in writing which indicates that
    such a breakdown was required.
    (Pet.
    Br.
    at 9.)
    Petitioner
    asserts that its contract with Accurate was based on a per—cubic—
    yard rate,
    not a time and materials basis,
    as would be required
    by the Agency forms.
    (Pet.
    Br.
    at 8.)
    Petitioner contends that
    contracting on a per—cubic—yard basis was
    a
    standard industry
    practice.
    (Pet.
    Br.
    at
    10;
    see
    testimony of John Hayes Tr.
    at
    4.1.)
    The Agency asserts that the supporting documentation
    petitioner provided for these costs did not meet the requirements
    of Section 22.l8b(d)(4)(C).
    (See
    Pet.
    Ex.
    17 Attachment A at
    para.
    2;
    Resp.
    Br. at 6.)
    Although Accurate provided invoices
    for the costs, the Agency asserts that the invoices did not
    contain sufficient information to demonstrate that the costs were
    reasonable.
    (Resp.
    Br.
    at 8.)
    The Agency asserts that a per—
    cubic—yard rate alone does not provide the information necessary
    for the Agency to determine whether the costs that went into the
    rate were appropriate and reasonable,
    and that a time and
    materials breakdown is necessary for the Agency to make this
    determination.
    The Agency points out that it did allow
    reimbursement of those costs where petitioner demonstrated the
    costs were reasonable response costs
    in Agency forms with a time
    and materials breakdown.
    (Resp. Br. at 9.)
    We find that the Agency
    is properly requiring applicants to
    the Fund to demonstrate that submitted costs are properly
    reimbursable.
    As stated above,
    based on Board precedent, the
    burden is on applicants to demonstrate that incurred costs are
    related to corrective action, properly accounted for, and
    reasonable.
    The Agency has not limited petitioner to a
    demonstration of reasonableness based on time and materials.
    Rather, the Agency would allow petitioner to demonstrate the
    reasonableness of corrective action costs through a competitive
    bidding process.
    Thus, the Agency has expanded,
    not restricted,

    5
    the means by which a party can demonstrate the reasonableness of
    costs.
    Competitive Bidding.
    Petitioner asserts that the Accurate
    costs should be reimbursed because petitioner obtained two bids
    for the work.
    (Pet.
    Br.
    at 12.)
    Petitioner contends that it
    received a bid from Mostardi-Platt for $90 per cubic yard,
    and a
    bid from Accurate for $64 per cubic yard,
    which petitioner
    accepted,
    and which was subsequently reduced to $60 per cubic
    yard.
    Mr.
    David Israel, the principal of Learsi, testified at
    hearing that Mostardi-Platt submitted the $90 per cubic yard bid.
    (Tr.
    at 192.)
    As further support for the $90 per cubic yard
    bid, petitioner attempted to introduce into evidence at hearing a
    hand—written note written on the cover of
    a soil boring
    investigation.
    The hearing officer denied its admission on the
    grounds that it constituted hearsay.
    (Tr.
    at 194—196.)
    Mr. Israel also testified that Mr. John Hayes of GSC
    Environmental obtained a $64 per cubic yard bid from Accurate
    Pump
    & Tank on behalf of petitioner.
    (Tr.
    at 198.)
    As evidence
    of this bid,
    at hearing petitioner introduced into evidence the
    contract with Accurate.
    (Pet.
    Ex.
    1.)
    This contract had not
    been submitted to the Agency prior to the Agency’s final
    determination.
    (Tr.
    at 33.)
    Mr. Israel further explained that
    the rate was later reduced to $60 per cubic yard when petitioner
    realized that the extent of contamination was greater than
    initially estimated; no documentation was submitted to the Agency
    indicating this change in rate.
    In response, the Agency asserts that none of this evidence
    that petitioner proceeded under a competitive bid process was
    submitted to the Agency prior to the Agency’s final
    determination.
    (Resp.
    Br. at 15, Tr. at 643-644.)
    The Agency
    asserts that it received neither the $90 per cubic yard rate nor
    the $64 per cubic yard rate bid prior to its final determination.
    The Agency further contends that the hand-written note does not
    contain sufficient information to constitute a bid.
    Finally, the
    Agency contends that three bids are generally required under a
    competitive bid process
    in order to demonstrate that the lowest
    bid was reasonable.
    (Resp.
    Br.
    at 15; Tr.
    at 642.)
    While it may be possible for a claimant to demonstrate that
    a two-bid competitive bidding process is reasonable, we find that
    petitioner did not do so in this case.
    Petitioner did not submit
    any information to the Agency concerning a competitive bidding
    process prior to the Agency’s final determination.
    Furthermore,
    even if the evidence concerning the $90 per cubic yard rate is
    considered despite its inadmissibility as hearsay, that
    information is simply insufficient to demonstrate that it
    constituted a competitive bid.
    Finally, petitioner had not even

    6
    submitted evidence of the bid it ultimately accepted prior to the
    Agency’s final determination.
    We find that petitioner did not
    provide sufficient evidence of a competitive bid process to the
    Agency to demonstrate that the costs paid to Accurate were
    reasonable.
    Per—Cubic Yard Rate.
    Petitioner also argues that it
    demonstrated that the $64 per cubic yard rate was a reasonable
    per-cubic-yard rate.
    (Pet.
    Br.
    at 12-13.)
    In support of this
    proposition, petitioner presented the testimony Mr. John Hayes,
    an environmental consultant who was employed by GSC
    Environmental,
    a consulting firm petitioner retained to provide
    technical assistance with the remediation project.
    Mr. Hayes
    testified that $64 per cubic yard constituted a reasonable rate
    (Tr.
    at 50),
    and testified that the work was actually performed.
    Accurate provided invoices for the work performed which were
    submitted to the Agency.
    Petitioner also offered the testimony
    of Steven E.
    Nelson, an independent environmental contractor,
    who
    testified as to the reasonableness of the $64 rate.
    (Tr.
    at
    373.)
    The Agency asserts that the supporting documentation for the
    denied costs did not meet the requirements of Section
    22.18b(d) (4) (C)
    and failed to establish that the costs billed to
    petitioner were reasonable.
    The Agency does not dispute that a
    common industry practice is to contract for excavation, removal
    and disposal of contaminated soil on a per—cubic—yard basis.
    However, the Agency asserts that a per—cubic—yard rate alone
    in
    not sufficient to demonstrate that the rate is reasonable;
    it
    must be supported by a time and materials breakdown of the costs
    included in the per-cubic-yard rate.
    Mr. Doug Oakley testified
    on the Agency’s behalf that a time and materials breakdown is
    necessary for the Agency to determine the reasonableness of
    remediation costs,
    such as personnel costs, equipment costs, and
    profit.
    (Resp.
    Br.
    at
    14;
    Tr.
    at 644—647.)
    Furthermore, the Agency asserts that it is commonly known in
    the industry that a per-cubic-yard rate is insufficient to
    demonstrate reasonableness of costs.
    In fact,
    the Agency points
    out that petitioner’s own expert witness, Mr. John Hayes,
    testified that a per—cubic—yard rate alone does not demonstrate
    that the rate is reasonable,
    and that
    it is commonly known in the
    industry that the Agency requires a time and materials breakdown
    of the costs included in the per cubic yard rate.
    (Resp.
    Br. at
    13—14; Tr.
    at 386—389,
    426.)
    We affirm the Agency’s denial of reimbursement of the
    $206,245.53 sought by petitioner which was not supported by a
    time—and—materials breakdown.
    These costs were not identifiable
    or supported by anything more than the total amount represented
    as paid in the inventory of checks and the total amount of the
    Accurate invoices.

    7
    Additional Accurate Costs.
    The Agency denied an additional
    $44,928.25
    in costs charged by Accurate for failure to submit
    proper documentation.
    Although these additional costs were
    identified in billing forms which provided a time-and-materials
    breakdown, the Agency denied reimbursement for the following
    reasons:
    1)
    $1,625.00 for a duplicate billing form for February 6,
    1991, where two billing forms were submitted for the
    same personnel on the same date;
    (2)
    $318.75 reported on a February
    6,
    1991 billing form
    where the weekly worksheet did not support the
    information contained on the summary sheet;
    (3)
    $40.00 reported on a billing form for the period of
    January 28,
    1991 through February 5,
    1991, which
    contained a mathematical error;
    (4)
    $195.00 reported on a billing form for the period of
    June 3,
    1991 through June 30,1991, where the drill rig
    hours
    on the weekly work sheet did not support the
    drill rig hours on the summary sheet;
    (5)
    $42,749.50 reported on a billing form from Accurate for
    work performed by Terry Robb Cartage, where Accurate
    billed petitioner and added a 15 percent service
    charge, despite the fact that petitioner had been
    billed directly.
    (Resp.
    Br.
    at 17.)
    Petitioner provided no additional argument that these costs
    should be reimbursed, relying instead on its argument that the
    entire amount should be reimbursed based on the reasonableness of
    the per-cubic—yard rate.
    Therefore, we uphold the Agency’s
    determination denying reimbursement of these costs.
    In sum, we find that petitioner did not demonstrate the
    reasonableness of the $206,245.53 in submitted costs which were
    not supported by a time and materials breakdown.
    We further hold
    that these costs were not shown to be reasonable through a
    competitive bidding process.
    Furthermore, the additional costs
    attributed to Accurate in the amount of $44,928.25 are denied for
    lack of evidence and argument by petitioner.
    We therefore uphold
    the Agency’s determination denying reimbursement of these
    combined costs.
    b)
    Investigation Costs of Nostardi-Platt
    Petitioner seeks review of the Agency’s denial of $3,277.00
    in costs incurred for work performed by Mostardi-Platt.

    8
    Petitioner provided the Agency with an invoice for $6,554.00,
    and
    a check for $3,277.00,
    half the amount.
    Petitioner claims that
    the other half was deducted from the sales escrow in connection
    with the sale of the site,
    since the total cost was split equally
    between petitioner and the purchaser.
    (Tr. at 237
    238.)
    Petitioner asserts that it is therefore entitled to reimbursement
    of $3,277.00.
    (Pet.
    Br.
    at 26—27.)
    The Agency denied the costs associated with soil
    contamination investigation performed by Mostardi-Platt on the
    grounds that these costs lacked supporting documentation.
    The
    Agency asserts that the invoice submitted is a lump sum bill,
    and
    that it cannot determine what services comprised the
    investigation, the personnel involved and their qualifications,
    or the rate at which the services or personnel were billed.
    (Resp.
    Br.
    at
    19.)
    We find that petitioner has not provided sufficient
    documentation to demonstrate that these costs constituted
    reasonable corrective action costs.
    Petitioner’s arguments
    concerning payment of the invoice do not address the
    reasonableness of the costs contained in the invoice.
    Accordingly, we affirm the Agency’s denial of $3,277 in costs
    paid to Mostardi-Platt.
    c)
    Consultant/Oversight Costs of Sun Eco Systems,
    Inc.
    Petitioner seeks reimbursement of $300 for costs paid to Sun
    Eco Systems,
    Inc.
    (Sun Eco)
    for consulting and oversight
    services.
    Petitioner asserts that it submitted an invoice from
    Sun Eco which stated that it was for an on—site project overview
    on November
    1,
    1990.
    (Pet.
    Br. at 28; Pet.
    Ex.
    15; Ag.
    Rec. Vol.
    B at 172.)
    Furthermore, Mr.
    Israel,
    the principal of Learsi,
    testified at hearing that a consultant named Philip Mode was
    “brought
    in to assess the whole situation”
    when the project was
    beginning.
    (Tr. at 243-244.)
    The Agency denied the $300 in costs paid to Sun Eco on the
    grounds that petitioner failed to provide sufficient
    documentation.
    The Agency asserts that the Sun Eco invoice did
    not indicate who performed the service,
    their area of practice or
    expertise, their billing rate,
    or the specific services provided.
    (Resp.
    Br.
    at 18.)
    We find that petitioner did not provide the Agency with
    sufficient documentation of the services performed and associated
    costs for the Agency to determine whether they constituted
    reasonable corrective action costs.
    Accordingly, we affirm the
    Agency’s denial of $300 for costs paid to Sun Eco Systems,
    Inc.

    9
    d)
    Ashly Trucking Company
    Petitioner seeks reimbursement of $7,670.00 in costs paid to
    Ashly Trucking Co.
    (Ashly).
    Petitioner asserts that it submitted
    invoices indicating that the charges were for trucking services,
    and specified the cost per load.
    (Pet.
    Br. at 23; Ag. Rec Vol. B
    at 151
    -
    160.)
    Petitioner also provided cancelled checks
    totalling $7,670.00, the full amount of the invoice.
    (Pet.
    Br.
    at 24; Ag. Rec Vol.
    B at 165
    -
    167.)
    Petitioner further asserts
    that the testimony of Mr.
    Israel and Mr. Hayes at hearing
    demonstrated that the costs were reasonable.
    Mr. Hayes had
    testified that he was present at the Site when Ashly was
    delivering the backfill, and expressed his opinion that the rates
    charged by Ashly were reasonable.
    (Tr.
    at 105.)
    Mr. Israel had
    testified about payment of the invoices and debiting of the
    appropriate account.
    (Pet.
    Br.
    at 23,
    Tr. at 235
    -
    236.)
    The Agency denied $7,670.00
    in costs paid to Ashly based on
    lack of supporting documentation.
    (Resp.
    Br.
    at 17-18.)
    The
    Agency asserts that,
    although the submitted invoices provided
    information such as dates,
    ticket numbers, truck numbers, and
    units,
    the Agency’s accountant,
    Ms.
    Levine,
    could not determine
    what service had been provided.
    (Tr. at 439-440.)
    She therefore
    could not determine whether the costs were reasonable,
    or were in
    fact corrective action costs.
    Furthermore, the Agency asserts
    that the petitioner never informed the Agency of the purpose of
    the costs prior to its final decision.
    (Resp. Br.
    at 18.)
    We find that petitioner failed to provide documentation that
    the costs paid to Ashly were reasonable corrective action costs.
    While petitioner demonstrated at hearing that the costs were for
    transportation of backfill,
    this demonstration was not made to
    the Agency prior to its final determination, and the Agency was
    therefore justified in finding that the costs were not adequately
    documented.
    In several prior UST Fund reimbursement cases, beginning
    with Sparkling Spring Mineral Water Co.
    v. Illinois Environmental
    Protection Agency (August
    26,
    1993)
    PCB 92-203, and continuing
    through Chuck
    & Dan’s Auto Service v. Illinois Environmental
    Protection Agency (August
    26,
    1993)
    PCB 92-203, the Board has
    admitted evidence which was not contained in the Agency record.
    This evidence was admitted because the Agency had not promulgated
    regulations identifying for petitioners the type of information
    necessary to complete a reimbursement application.
    The Board
    reasoned that without such regulations, petitioners could not
    anticipate what information the Agency would require, and
    therefore petitioners should be allowed to supplement the record
    in order to clarify why a disputed cost should be reimbursed.
    This was a departure from the evidentiary rule applied in permit
    appeal cases, wherein the Board reviews only the record below.
    (Sparkling Spring Mineral Water at 4,
    citing
    Joliet Sand
    & Gravel

    10
    v.
    PCB,
    163 Ill.App.
    3d 830,
    516 N.E.2d 955,
    958
    (3d Dist.
    1987)
    .)
    However, the facts in the present case warrant the
    application of the evidentiary rule followed in permit appeals.
    Notwithstanding the absence of Agency regulations, petitioner
    knew or was obligated to know that, at a minimum,
    it was required
    to demonstrate that the disputed cost was for corrective action.
    Section 22.18(b)
    of the Act clearly states that an owner or
    operator can only recover from the Fund the costs of corrective
    action.
    The initial burden on the party seeking reimbursement is
    to demonstrate that the remediation costs satisfy the definition
    of corrective action.
    (Platolene 500,
    Inc.
    v. IEPA
    (May 7,
    1992)
    PCB 92-9,
    133 PCB 259 at 7.)
    The information submitted
    concerning trucking costs was insufficient to demonstrate that
    the cost was for corrective action.
    The invoices submitted
    contained no information as to what task the truck performed.
    Such information is critical to the Agency’s determination
    whether a cost is for corrective action.
    Absent that
    information, the Agency would have been remiss
    if
    it would have
    released monies from the UST Fund.
    We therefore affirm the
    Agency’s denial of $7,670.00 in costs paid to Ashly Trucking.
    e)
    August Sievers and Sons Company
    Petitioner seeks reimbursement of $3,227.20 in costs paid to
    August Sievers and Sons Company (Sievers).
    Petitioner asserts
    that it submitted an invoice for these costs which specifically
    states the invoice
    is for services rendered to “backfill and
    compact clean fill in tank hole.”
    (Pet.
    Br. at
    24, See Pet.
    Ex.
    4, Ag. Rec.
    vol.
    B at 168.)
    Petitioner also points out that
    petitioner provided a cancelled check to August Sievers for
    $3,227.00,
    the total amount of the invoice.
    Furthermore, Mr.
    Israel testified about payment of the invoices and debiting of
    the appropriate account.
    (Pet.
    Br.
    at 23,
    Tr.
    at 232
    234.)
    The Agency denied reimbursement of these costs on the
    grounds that the bill was
    a lump sum bill.
    (Resp.
    Br. at 19.)
    The Agency asserts that the invoice does not indicate what type
    of backfill was used,
    or what personnel or equipment were needed
    to perform the work,
    or the rate at which the work was billed.
    There was therefore insufficient information to determine the
    reasonableness of the costs.
    (See Tr.
    at 441.)
    We find that petitioner did not provide the Agency with the
    information necessary to determine whether the charges for the
    services which made up the total were reasonable.
    We therefore
    affirm the Agency’s denial of $3,227.20 for costs paid to August
    Sievers and Sons Company.

    11
    2) Costs Not Considered Corrective Action
    a)
    Pumping and Disposal of Water
    After petitioner discovered the USTs at the site,
    in order
    to become eligible to seek reimbursement from the UST Fund,
    petitioner prepared and submitted to the Agency a corrective
    action plan in the second week of November 1990.
    The corrective
    action plan was approved in January 1991.
    During this time
    period,
    8—10 feet of run—off water collected in the excavation,
    with a total volume of approximately 80,000 gallons.
    (Pet.
    Br.
    at 15; see testimony of John Hayes,
    Tr. at 63.)
    Petitioner seeks
    reimbursement of $28,655.70 in costs incurred in pumping and
    disposing of this water as a special waste.
    (Pet.
    Br. at 15.)
    Petitioner requested approval to discharge the water through
    the sewer system.
    (Agency Rec.
    vol.
    D at 119.)
    The Agency
    informed petitioner that a discharge permit would be needed, and
    that the permitting process would take approximately 60-120 days.
    (See Agency Rec.
    vol. D at 134.)
    An April
    1, 1991 report from
    GSC Environmental
    (GSC)
    directed to Angela Tin at the Agency,
    indicates that the Village Engineer from the Village of Clarendon
    Hills would allow the discharge if a permit was obtained from the
    Agency.
    (~~)
    Despite the fact that the Agency and Village approved the
    discharge of the collected run-off to the sewer pending
    petitioner’s receipt of a discharge permit, petitioner elected to
    have the water pumped out and treated as a special waste.
    (See
    Ag.
    Rec. Vol C pt.
    2 at 639.)
    The April
    1,
    1991 report from GSC
    indicates that petitioner elected to pump and treat the water as
    a special waste in order to avoid the delay associated with
    obtaining a permit.
    (Agency Rec.
    vol.
    D at 134.)
    Petitioner argues that applying for a permit to discharge
    into a sewer is a very long and costly process,
    and is not a
    practical or reasonable alternative for managing rainfall
    accumulated in an excavation.
    (Pet.
    Br. at 17; Tr.
    at 376.)
    Petitioner presented the expert testimony of Mr. Nelson that such
    permit applications are often denied, since there is always the
    possibility of residual contamination.
    (Tr.
    at 376.)
    Petitioner
    also argues that the water presented a safety concern since
    someone could be harmed if they fell into the excavation, and
    since the sides of the excavation could collapse.
    (Pet.
    Br. at
    16; Tr. at 67,
    375.)
    Petitioner further states that the costs
    were corrective action costs since,
    as admitted by the Agency,
    the excavation could not proceed with the water in the
    excavation.
    (Pet.
    Br.
    at 16; see testimony of John Hayes,
    Tr. at
    64, testimony of Jay Hamilton;
    Tr. at 581.)
    The Agency denied reimbursement of these costs,
    saying that
    they didnot constitute corrective action costs.
    (Pet.
    Ex.
    17

    12
    Attachment A para.
    7.)
    Petitioner’s own testing shows that the
    water was clean,
    and did not need to be disposed of as a special
    waste.
    (See April
    1,
    1991 Report by GSC to Angela Tin, Ag.
    Rec.
    Vol D at 137.)
    Furthermore, the Agency had agreed to
    petitioner’s request to dispose of the water through the sewer,
    which would have been less expensive than pumping and treating as
    a special waste.
    (See testimony of Steven
    E. Nelson, Tr.
    at 403
    -
    404; testimony of Jay Hamilton at 566.)
    This would have required
    that petitioner obtain a discharge permit.
    The record shows that
    the, Village of Clarendon Hills engineer would allow the discharge
    of water if such a permit was obtained.
    The record shows that
    processing a permit application was expected to take 60-120 days.
    (R.
    Vol.
    D at 134.)
    We find unpersuasive petitioner’s argument that the water
    presented a safety concern which required immediate action.
    The
    excavation had been fenced, and had already been sitting dormant
    for approximately two months.
    Furthermore, the record
    demonstrates that there was a reasonable and less expensive
    alternative to pumping and treating the water as a special waste,
    and that it would have been less expensive to dispose of it
    through the sewer.
    The record indicates that the Village
    Engineer would allow the discharge if approved by the Agency, and
    that petitioner had obtained Agency approval.
    Petitioner only
    needed a discharge permit, which could have obtained in
    approximately 60-120 days.
    We find that the Agency properly
    denied the cost, of disposing of this water as a special waste,
    since disposing of the water as a special waste did not
    constitute corrective action.
    b)
    Sewer Repair
    Petitioner seeks reimbursement of $842.83 incurred in
    repairing and capping a storm sewer.
    (Pet.
    Br. at 19.)
    Petitioner asserts that these costs constituted corrective action
    costs,
    since the repair minimized,
    eliminated,
    or stopped the
    potential flow or migration of contaminants.
    (~~)
    Petitioner
    points out that Mr. Hamilton admitted under cross—examination
    that if the storm sewer had been left unrepaired,
    it was possible
    that contamination could have entered the storm sewer and
    migrated to other places on the site,
    or even off—site.
    (Pet.
    Br. at 19, see Testimony of Jay Hamilton,
    Tr. at 598.)
    The Agency denied the sewer repair costs on the grounds that
    they did not constitute corrective action costs.
    (Pet. Ex.
    17
    Attachment A para.
    8; Testimony of Jay Hamilton at 569.)
    The
    Agency asserts that there
    is no evidence that any contamination
    ever entered the sewer, and that
    it is mere speculation on
    petitioner’s part that such migration of contamination could,
    occur.
    (Resp.
    Br. at 25.)
    The Agency also argues that
    petitioner failed to demonstrate that the sewer was not damaged
    during petitioner’s removal activities.
    (~~)

    13
    We find that petitioner has demonstrated that the repair and
    capping of the sewer constituted corrective action.
    Petitioner
    was not required to demonstrate that migration had occurred in
    order for the repair to be considered corrective action.
    Petitioner could demonstrate that the costs were corrective
    action costs by showing that the sewer created the potential for
    migration of contaminants.
    We hold that petitioner
    is entitled
    to reimbursement of $842.43 incurred
    in the repair and capping of
    the sewer.
    c)
    Site Sweeping
    Petitioner asserts that the $349.20 incurred for sweeping
    the site should have been reimbursed,
    since they constitute
    mitigation of a safety hazard.
    (Pet.
    Br.
    at 19
    20.)
    Petitioner further argues that some of the soil removed in
    sweeping the site may have been affected by contamination, even
    if the levels were below cleanup objectives.
    (Pet.
    Br. at 19.)
    The Agency denied reimbursement of the site sweeping costs
    on the, grounds that they did not constitute corrective action
    costs.
    (Pet.
    Ex.
    17 Attachment A para.
    8.)
    The Agency asserts
    that there
    is no evidence that sweeping and cleaning the site
    stopped, minimized, eliminated or cleaned up the release of
    petroleum
    at
    the site.
    (Resp.
    Br. at 25.)
    The Agency asserts
    that the Enterprise Leasing test focuses on whether the activity
    itself is corrective action,
    not whether
    it is the result of
    corrective action, and that petitioner has failed to demonstrate
    that the activity is corrective action.
    (~~)
    We find that petitioner failed to demonstrate that the costs
    incurred to sweep and clean the site were corrective action
    costs.
    There is no evidence that sweeping and cleaning the site
    stopped, minimized,
    eliminated, or cleaned up the release of
    petroleum.
    The safety hazards presented by a “dirty,
    disorgarüzed site” are not the kinds of risks the LUST Fund was
    intended to address.
    Sweeping the site constitutes a restorative
    action, beneficial to the property owner and society, and not a
    corrective action, stopping or minimizing a release of petroleum.
    d)
    Demurrage
    Petitioner asserts that it should have been reimbursed for
    $280 in demurrage costs, paid to Beaver Oil Company,
    Inc., which
    were billed at $70 per hour for four hours.
    (Pet.
    Br.
    at 20
    -
    21; Ag. Rec. Vol.
    C pt.
    2 at 688,
    691.)
    Petitioner asserts that
    the demurrage fees were charges for the time a truck was required
    to stay at the site while it was removing water from the
    excavation.
    (Pet.
    Br. at 20; Testimony of John Hayes,
    Tr. at 88-
    89.)

    14
    The Agency denied reimbursement of the demurrage costs on
    the grounds that they did not constitute corrective action costs.
    (Pet.
    Ex.
    17 Attachment A para.
    9..)
    The Agency defines demurrage
    costs as “a charge assessed for detaining a freight car,
    truck,
    or other vehicle beyond the free time stipulated for loading or
    unloading.”
    (Resp.
    Br. at 25.)
    In her testimony,
    Grace Levine
    referred to demurrage fees as “standby charges.”
    (Tr. at 467.)
    The Agency asserts that Beaver Oil Company, Inc., which assessed
    the fees,
    interpreted demurrage fees
    in the same manner.
    The
    Agency points out that an October 30,
    1990 Beaver Oil invoice for
    a load of oil, water and sludge, and a load of heavy mud, charged
    no demurrage fee for loading these substances,
    so that the term
    demurrage cannot refer to the time spent actually pumping out the
    materials.
    (Resp.
    Br. at 26; Agency Rec Vol.
    C pt.
    2 at 684.)
    Furthermore the Agency asserts that,
    if demurrage charges
    were in fact costs incurred for the time the material was
    actually being removed, the demurrage fees do not correlate with
    the amount of materials removed.
    For example, the pumping of
    2000 gallons of used oil and water incurred two hour of demurrage
    fees, while the pumping of 3000 gallons and 5500 gallons incurred
    only one hour each of demurrage fees.
    (Resp.
    Br.
    at 26;
    see Ag.
    Rec. Vol. C pt.
    2 at 688,
    691.)
    The Agency acknowledges that,
    pursuant to Platolene 500,
    Inc.
    v.
    IEPA
    (May 7,
    1992) PCB 92-9,
    certain standby charges can be related to corrective action.
    However, the Agency asserts that petitioner did not provide
    sufficient details concerning the delays to justify
    reimbursement.
    We find that petitioner has failed to demonstrate that the
    demurrage fees were corrective action costs.
    Petitioner has
    failed to explain the inconsistencies which would result if its
    definition were adopted.
    Furthermore, petitioner has failed to
    adequately explain the delays in order to justify reimbursement.
    We therefore affirm the Agency’s denial of $280 for demurrage
    costs.
    e)
    Lost Barricades
    Petitioner asserts that it should be reimbursed $180
    incurred for lost barricades.
    (Pet.
    Br. at 21.)
    Petitioner
    asserts that these costs were incurred as part of the corrective
    action at the site.
    (i~) The Agency denied these costs on the
    grounds that they do not constitute corrective action costs.
    (Pet.
    Ex.
    17 Attachment A para.
    10.)
    At hearing, Ms. Grace
    Levine testified that equipment rental
    is reimbursable, but
    equipment purchase is not, since equipment purchase is not
    necessary for corrective action.
    (Tr. at 467
    468.)
    We affirm the Agency’s denial of $180 for lost barricades,
    on the grounds that these costs do not constitute corrective
    action costs.

    15
    f)
    Parking Lot Lighting
    Petitioner seeks reimbursement of $10,127.46
    in costs
    incurred
    in replacing parking 1~tlighting fixtures.
    (Pet.
    Br.
    at 25
    26.)
    The Agency denied these costs on the grounds that
    they do not constitute corrective action costs.
    (Pet.
    Ex.
    17
    Attachment A para.
    11.)
    Paragraph 11 of the Agency April 29,
    1993 clarification only
    states that $127.46 is denied in reimbursement.
    (Pet.
    Ex.
    17
    Attachment A para.
    11.)
    Petitioner asserts that the Agency
    should be bound by the $127.46 figure, pursuant to Clinton Co.
    Oil Co.
    v. Illinois Environmental Protection Agency
    (March 26,
    1992, and June 4,
    1992)
    PCB 91-163.
    Furthermore, petitioner
    contends that the dismantling and reassembling of the lights was
    necessary to perform the remedial action at the site.
    (Pet.
    Br.
    at 26; see testimony of John Hayes,
    Tr.
    at
    79.)
    The Agency asserts that the $127.46 figure was an obvious
    typographical error,
    and that it intended to deny the full
    amount.
    (Pet.
    Br. at 27.)
    The Agency states that it would have
    been impossible for
    it to have separated $127.46 out of the
    total,
    since petitioner provided only
    a lump sum bill.
    The
    Agency further points out that total amount to be reimbursed
    listed in both the April
    29,
    1993 and the reimbursement voucher
    prepared for the site confirm that $10,
    127.46 was the
    appropriate figure.
    The Agency argues that it should not be
    bound by such an obvious typographical error.
    The Agency further
    argues that Clinton County Oil does not address typographical
    errors, and that it is therefore inapplicable and does not
    require that the Agency be bound by such an error.
    The Agency asserts that, pursuant to Platolene 500,
    Inc.
    v.
    IEPA
    (May 7,
    1992)
    PCB 92-9,
    it
    is clear that installation of the
    parking lights constituted a restorative action, and did not
    constitute corrective action to stop or minimize
    a release of
    contamination.
    (Resp. Br.
    at
    27
    -
    28.)
    The Agency states that t
    would have paid for dismantling of the light poles and their
    reassembly if the dismantled components had been used.
    (Resp.
    Br. at 27
    -
    28; Testimony of Jay Hamilton,
    Tr. at 574
    -
    575.)
    We find that the Agency is not bound by an obvious
    typographical error in its clarification letter.
    There is no
    danger that petitioner would have been misled to believe that
    only a portion of the costs were denied, since petitioner
    provided only a lump sum bill,
    and did not provide the Agency
    with.a breakdown of costs.
    Furthermore, we find that the Agency
    is correct in characterizing these costs as restorative actions,
    which pursuant to Platolene 500, are not reimbursable.
    Installation of the lights did nothing to stop minimize or
    prevent a release of petroleum.
    Accordingly, these costs were
    properly denied.

    16
    3)
    Pre-Notification Expenses
    The Agency denied a total of $14,213.96 in costs which were
    incurred prior to notification of ESDA (pre-notification
    expenses):
    $5,330.58 in costs associated with consulting
    services provided by GSC, and $8,883.38 for work performed by
    Accurate.
    (Pet.
    Ex.
    17 Attachment A para.
    3.)
    The Agency
    asserts that,
    pursuant to Section 22.28b(d) (4) (D)
    of the Act,
    costs incurred prior to notification of ESDA are not eligible for
    payment.
    Petitioner asserts that the Agency is improperly relying on
    language which does not appear in the Act until the remediation
    at the site had been completed
    -
    language which became effective
    September 6,
    1991
    (Pub.
    Act 87-323).
    (Pet.
    Br.
    at 22-23.)
    The statutory language in effect at the time petitioner
    submitted its application read:
    (4)
    Request for partial or final payment for claims under
    this Section shall be sent to the Agency and shall
    satisfy all of the following:
    (D)
    The owner or operator notified the State of the
    release of petroleum in accordance with applicable
    requirements;
    Petitioner asserts that this requirement was eventually
    satisfied, and that the costs should therefore be reimbursed.
    (Pet.
    Br., at 22
    -
    23.)
    As the Board explained in North Suburban Development
    Corporation
    (December 19,
    1991),
    PCB 91—109,
    128 PCB 263,
    272:
    Contrary to North Suburban’s assertions
    the
    revised
    language of Pub. Act 87-323
    does not reflect a new
    statutory initiative
    to exclude pre—notification expenses.
    The old language would have excluded all remediation costs
    when ESDA was not notified within
    24 hours, even if ESDA was
    notified more than 24 hours later but before remediation
    costs were incurred.
    The new language makes it clear that
    costs incurred after notification can be compensated even if
    the 24—hour notification requirement is not met.
    Since pre—
    notification costs are excluded under both the old and the
    new statutory language, this argument is misplaced.
    (See also Kronon Motor Sales,
    Inc.
    v. IEPA (January 9,
    1992),
    PCB
    91—138,
    affirmed
    609 N.E.
    2d 678.)

    17
    We find that this explanation
    is applicable and
    petitioner’s argument
    is without merit.
    We therefore affirm the
    Agency’s denial of the pre—notification expenses.
    4)
    Manifest Charges $37.50.
    Petitioner seeks reimbursement of $42.50 for the preparation
    of five special waste manifests by Beaver Oil.
    (Pet.
    Br. at
    18.) Petitioner asserts that the $37.50 charge reflects the
    charge, for the execution,
    filling out and processing of the waste
    manifest that is required to accompany the special waste.
    (Pet.
    Br.
    at 18; see Testimony of John Hayes,
    Tr.
    at 89.)
    Beaver Oil
    charged petitioner $8.50 per manifest for this service.
    (Pet.
    Br.
    at 18; Ag.
    Rec. Vol C pt.
    2 at 684,
    688,
    691.)
    The Agency allowed reimbursement of
    $5 and denied
    reimbursement of $37.50 of these charges
    (Pet.
    Ex.
    17 Attachment
    A para.
    6), allowing only $1 per manifest, which
    is the price the
    Agency charges for the actual manifest document.
    (Resp. Br. at
    23.)
    The Agency asserts that the information contained in each
    manifest appears to be the same on each form, and should have
    only taken 2-3 minutes to complete.
    (Resp.
    Br.
    at 24.)
    The
    quantity of substance on each form is hand—written, and the only
    other information that changed between forms were signature and
    date.
    (~~)
    Furthermore, the information could have been
    completely handwritten, requiring even less effort.
    (~)
    The
    Agency also points out that other companies that completed the
    manifests did not charge
    a completion fee.
    (~~)
    The Agency
    asserts that charging a fee to complete the manifest is not
    reasonable in light of the minimal efforts required to perform
    the task.
    (~~)
    We find that petitioner failed to demonstrate that this cost
    was reasonable as submitted.
    We agree with the Agency that the
    minimal efforts required to complete the form do not justify the
    $8.50 per manifest fee.
    The Agency’s denial of $37.50 is
    affirmed.
    5) Handling Charges
    The Agency denied $253.42 associated with the handling
    charges for certain subcontracted services related to site
    sweeping and sewer repair,
    ($1,192.03),
    lost barricades
    ($180)
    deinurrage costs
    ($280) and manifest costs ($37.50).
    (Pet.
    Ex.
    17
    Attachment A para’.
    1.)
    Because we have affirmed the Agency’s
    denial of the site sweeping costs,
    lost barricade costs and
    demurrage costs, we affirm the Agency’s denial of the related
    handling costs.
    Because we have reversed the Agency’s denial of
    $842.83 in sewer repair costs, we reverse the Agency’s denial of
    the related handling costs.
    Petitioner is entitled to
    reimbursement of $127.25 in handling costs.

    18
    6)
    Legal Fees of Ross
    & Hardies
    The Agency denied reimbursement of $68,679.55 in costs paid
    to the law firm of Ross
    & Hardies on the grounds that they
    constituted legal defense costs.
    (Pet.
    Ex.
    17 Attachment A para.
    5.)
    Paragraph
    5 of the denial letter further states that,
    pursuant to Section 22.28b(e) (1) (C)
    of the Act,
    legal defense
    costs include legal costs for seeking payment under Section
    22.18(b).
    Petitioner is appealing the denial of
    $10,000 of these
    costs which were incurred in connection with petitioner’s appeal
    of the O’ffice of the State Fire Marshal’s revocation of the
    registration of the tanks at the site.
    (Pet.
    Br.
    at 28
    -
    29; see
    testimony of David Israel, Tr.
    at 206
    207,
    251
    252.)
    Petitioner asserts that these costs are not legal defense
    costs as defined in 35 Ill. Adm. Code 731.192, which defines
    legal defense costs as:
    any expense that an owner or operator or provider of
    financial assurance incurs
    in defending against claims or
    action brought,
    By USEPA or the State to require corrective action or
    to recover the costs of corrective action;
    By or on behalf of a third party for bodily injury or
    property damage caused by an accidental release; or
    By any person to enforce the terms of
    a financial
    assurance mechanism.
    (Note: this regulation was repealed in April,
    1992.)
    Petitioner relies on City of Roodhouse v. IEPA (September
    17, 1992)
    PCB 92-31, wherein the Board took notice of the
    definition of the term “legal defense costs” contained in 35 Ill.
    Adm. Code 731.192 for guidance in interpreting its meaning in the
    UST reimbursement context.
    (See City of Roodhouse at 19.)
    The Agency responds that City of Roodhouse is
    distinguishable,
    in that the costs in that case were found to be
    corrective action costs.
    (Resp.
    Br.
    at 23.)
    The Agency asserts
    that in the present case,
    the costs were not corrective action
    costs,
    in that they were not incurred to stop, minimize,
    eliminate,
    or clean up a release of petroleum or its effects as
    may be necessary or appropriate to protect human health and the
    environment.
    The Agency points out that petitioner was required
    to clean up the site whether or not petitioner was entitled to
    access the Fund.
    (Id.)
    We affirm the Agency’s denial of these costs on the grounds
    that they were legal defense costs which did not constitute

    19
    corrective action costs.
    In City of Roodhouse, the Agency had
    denied reimbursement of legal costs connected with obtaining an
    alternate water supply, which was specifically listed as
    corrective action.
    Here,
    Petitioner seeks reimbursement for
    costs incurred in obtaining registration of tanks,
    an activity
    which is not corrective action.
    We distinguish Roodhouse on the
    grounds that,
    in Roodhouse, the legal costs were incurred in
    connection with corrective action costs.
    In the present case,
    the legal costs incurred in appealing the registration of tanks
    with the OSFM clearly do not constitute corrective action costs,
    in that they are not incurred to stop, minimize, eliminate,
    or
    clean up a release of petroleum or its effects.
    Therefore, we
    find that it is inappropriate to apply the definition contained
    in 35 Ill. Adm. Code 731.192.
    Furthermore, The Agency’s April
    29,
    1993 clarification letter informed petitioner that the costs
    were being denied because they did not constitute corrective
    action costs,
    and that legal costs incurred
    in for seeking
    payment under Section 22.28(b) were not reimbursable as
    corrective action costs.
    While the standard language contained
    in the April
    29,
    1993 incorrectly referenced language contained
    in Section 22.28(e) (1) (C) which was not
    in force at the time
    petitioner submitted its application in order to support the
    denial, the fact that this was not a reimbursable cost was
    entirely correct.
    CONCLUSION
    For the reasons set forth above,
    we find that the Agency
    properly denied reimbursement of $330,434.37 of the $331,404.05
    in contested costs.
    We further hold that petitioner
    is entitled
    to additional reimbursement of $969.68:
    $842.43 for costs
    incurred in the repair and capping of the sewer,
    and $127.25 for
    handling charges on those sewer repair costs.
    This opinion constitutes the Board’s findings of fact and
    conclusions of law in this matter.
    ORDER
    1.
    The Board hereby affirms the Agency’s February 18,
    1993
    final determination,
    as clarified by its April
    29,
    1993
    letter,
    in denying reimbursement to petitioner,
    Learsi, for
    the following costs:
    A.
    $298,786.98 for costs lacking supporting documentation;
    B.
    $28,655.70 for costs associated with clean water
    pumping,
    since these costs are not corrective action
    costs;
    C.
    $349.20 for costs incurred for site sweeping,
    since
    these costs are not corrective action costs;

    20
    D.
    $280.00 for costs associated with demurrage,
    since
    these costs are not corrective action costs;
    E.
    $180 for costs associated with lost barricades,
    since
    these costs are not corrective action costs;
    F.
    $10,127.46 for costs associated with wiring lights;
    since these costs are not corrective action costs;
    G.
    $14,213.96 for costs incurred prior to notification of
    ESDA;
    H.
    $37.50 for manifesting costs,
    since petitioner failed
    to demonstrate that the costs were reasonable;
    I.
    $126.17 for handling charges on denied costs; and
    J.
    $10,000 in legal defense costs for which petitioner
    sought review.
    2.
    The Board hereby reverses the Agency’s February 18,
    1993
    final determination,
    as clarified by its April
    29,
    1993
    letter,
    in denying reimbursement to petitioner
    for the
    following costs:
    A.
    $842.43 for costs incurred
    in the repair and capping of
    a sewer; and
    B.
    $127.25 for handling charges on those sewer repair
    costs.
    IT IS SO ORDERED.
    Section 41 of the Environmental Protection Act (415 ILCS
    5/41
    (1992))
    provides for the appeal of final Board orders within
    35 days of the date of service of this order.
    The Rules of the
    Supreme Court of Illinois establish filing requirements.
    (See
    also 35
    Ill. Adm. Code 101.246.
    “Motions for Reconsideration”.)
    I,
    Dorothy M.
    Gunn,
    Clerk of the Illinois Pollution Control
    Board,
    hereby cert~,ifythat the ab~çeopinion and order was
    adopted on the
    ~
    day of
    ~
    1995,
    by a vote
    of
    ‘7—~
    .
    Il
    Control Board

    Back to top