ILLINOIS POLLUTION CONTROL BOARD
    March 17,
    1994
    CENTRAL
    CAN
    COMPANY,
    Petitioner,
    v.
    PCB 92—176
    (Permit Appeal)
    ILLINOIS ENVIRONMENTAL
    PROTECTION AGENCY,
    Respondent.
    ORDER OF ThE BOARD
    (by J. Theodore Meyer):
    This matter is before the Board on a joint motion for
    reconsideration,
    filed on March 15,
    1994.
    On March 16,
    1994,
    petitioner Central Can Company filed
    a supplement to the motion
    for reconsideration.
    The parties seek reconsideration of the
    Board’s February 17,
    1994 order directing that all hearings in
    this matter be completed by July
    1,
    1994.
    The parties ask that
    the Board rescind our February 17 order, to allow more time to
    obtain an interpretation from USEPA regarding issues in this
    appeal.
    The motion for reconsideration is granted. The parties have
    presented new information regarding the progress of their
    inquiries to USEPA.
    We continue to believe, however, that
    substantive action on this case cannot be delayed indefinitely.
    Therefore, we order that all hearings in this matter must be
    completed by October
    1,
    1994.
    IT IS SO ORDERED.
    I, Dorothy
    14. Gunn,
    Clerk of the Illinois Pollution Control
    Board, hereby certify that the above order was adopted
    7n the
    /7~-
    day of
    ________________,
    1994, by a vote of
    ~
    Control Board

    Back to top