ILLINOIS POLLUTION CONTROL BOARD
    March 15, 2001
    IBP, Inc.,
    Petitioner,
    v.
    ILLINOIS ENVIRONMENTAL
    PROTECTION AGENCY,
    Respondent.
    )
    )
    )
    )
    )
    )
    )
    )
    )
    )
    PCB 01-88
    (Permit Appeal - Air)
    ORDER OF THE BOARD (by G. T. Girard):
    On November 30, 2000, the parties filed a notice of extension of the 35 day period to
    appeal a decision of the Illinois Environmental Protection Agency (Agency). The extension
    was granted until March 1, 2001.
    This petition for review, filed on March 1, 2001, requests that the Board review
    pursuant to Section 39 of the Environmental Protection Act (415 ILCS 5/39) (1998), an air
    construction permit issued May 23, 2000, by the Agency regarding the facility owned by IBP,
    Inc., located in Joslin, Henry County, Illinois. The Board accepts this matter for hearing.
    Hearings shall be scheduled and completed in a timely manner pursuant to the
    applicable statutory decision deadline or as extended by waiver (see 415 ILCS 5/40(a)(2)
    (1998), 35 Ill. Adm. Code 101.308). Unless otherwise ordered by the hearing officer, the
    Agency shall file the record of its review of the permit application within 30 days of notice of
    the petition. See 35 Ill. Adm. Code 105.116.
    IT IS SO ORDERED.
    I, Dorothy M. Gunn, Clerk of the Illinois Pollution Control Board, hereby certify that
    the above order was adopted on the 15th day of March 2001 by a vote of 7-0.
    Dorothy M. Gunn, Clerk
    Illinois Pollution Control Board

    Back to top