ILLINOIS POLLUTIC:: CONTROL
.
BOARD
April lL, 1971
CITY
OF
MATTOOJ
)
I
)
V.
)
171—8
ENVIRONMENTAL
PROTECTION
AGENCY
)
Opinion of the Board (by
Mr.
Curr~.e):
This is a most depressing case in which the City asks for a
variance because it thought the state was not serious when it
prescribed deadlines for the conctruction of additIonal sewage
treatment facilities.
Lefl any dcubt remain, we declare once
more that the state is indeed serIous about expecting obedIence
to the
lawd
It is high time people reco~n!zedthat the persuasive
demand for
lat: and order applies to polluters as well as to
burglars.
110w municipal and corp~rateofflcials can cluck their
tongues
over
wayward
youth
while
çayiiag no attcntlon to their
own legal responsibilities is beyond our comprehension.
The City of Mattoon operates a seriously overloaded sewase
treatment plant fed by an overloaded sewer system
(B.
86—87,
165).
Secondary treatment is provided to whatever flows the plant
can handle, but additional flows are given only primary treat,ent
(which removes the
larger
hunks)
~r
bypassed
as
raw
sewage
dIrectly
to Xickapoo Creek from the plant or from the sewers themselves
(R.
88—89,
113).
Such overflows
occur
five or six times per
month
(R.
139).
Kickapoo Creek is
a
small
intrastate stream w±thlittle
capacity to assimilate wastes.
The undisputed testimony is that
the creek is seriously polluted below the plant and does not
completely recover for six miles downstream
(R.
186).
Fish have
been missing for years
(R.
179,
191$,
& EPA recommendation);
there are complaints of odors
CR.
168, l72)~the stream is in-
habited by organisms tolerant of pollution
(R.
186, 191—93),
it is troubled by sludge banks, t:ilet tIssue, and fecal materIal
(R. 167).
The EPA without contradictIon attributed these con--
ditions to the Nattoon sewage failit~esCR.
182, 187).
The Environmental Protection Agenty in its recommendation reported
that one
person
lntervlet;ed
sa!t
“he
had seen his cows leave a
standing
position
in
tha
creek
~:cor.
to
wa)k to a nearby
sprln—
fed
pool
in
order
to
obtain
drInk~.ngwate:’.”
1
—441
It was no idle whim, therefore, that prompted the state
Sanitary Water Board in March, 1968 to prescribe that on such
streams as Kickapoo Creek secondary treatment was insufficient
and that bypasses must be eliminated.
The implementation
schedule in Rules and Regulations SWB—111, Rule 1.08 paragraphs
9,
lib, and 111, requires that advanced treatment to produce an
effluent with biochemical oxygen demand (BOD) of ilmg/l and
suspended solids of
5
mg/i must be provided, and bypasses given
primary treatment and chlorination, by July,
l9’72.
In order to
provide interim checkpoints to determine whether progress was
being made, the regulations also reqgired that for cities above
10,000 population (such as Mattoon) plans and specifications be
completed 30 months before the deadline for completion of construction
and construction contracts be awarded 21 months before..
Notice
of these requirements was admittedly received by the City in the
spring of 1968
(R.
160).
The~preparationof plans, the City now agrees, is a task
that can be done within one year, and construction within another.
The City was given by the regulation four years for a job it
concedes can be done in two.
.
Yet today it stands naked before
this Board with no plans or specifications for advanced treat-
ment even begun, much less completed, and with construction
not slated to begin for more than another year in the
t,,ture.
The City acknowledges that it is “slightly” behind schedule and
asks us placidly to approve a new schedule that would allow
the filing, of plans in March 1972, the letting of contracts
in, May 1972, and the completion of facilities in June 1973.
The statute provides for variances only upon a showing by
the petitioner that compliance with the, law would impose an
“arbitrary or unreasonable hardship” (Environmental’Protection
Act, section
35).
We have often made clear that whether the
hardship of compliance is arbitrary or unreasonable can only
be determined by a comparison of the benefits and of the costs.
bf compliance:
“The statutory variance test of unreasonable
hardship is not satisfied by proof of hardship alone; it must
be demonstrated that the hardships of complying with the law
are disproportionately large in comparison to the benefits to
the public of so doing.”
Texaco,’Inc. v.
EPA, #70—29
(I!eb,
17,.
1971).
This is made clear by our procedural rules, which in
Rule llOl(a)(2) require the petitioner to include in his petition
“a descriptio4 of the costs that compliance’would impose on the
petitioner and others and of the injury
tI~iatthe grant of the
variance would impose on the public.”
1—442
The
petition
in
this
case does not comply with the
rules.
It
contains
no
debcription
of
the
injury
that
grant
of
the
variance would impose on the public, and it includes no estimate
of the contaminants discharged, as required by Rule I10l(a)(1).
In light of the evidence developed at the hearing, however, we
shall proceed to consideration of the merIts.
The hardship complained of is that, since the City has
already missed the deadline for the submission of plans
(January
1970) and the letting of contracts (September 1970), it cannot
possibly meet them and that the time remaining before the final
deadline for completion of the facilities is too short to permit
that date to be met either (R.
75).
We have already held, as
should have been obvious, that “one cannot qualify for a variance
simply by ignoring the timetable and starting late.
.
.
.
To
allow a variance on the basis of.
.
(such
allegations would
establish the preposterous proposition that the very, existence
of a violation is a ground for ‘excusing it.”
Decatur Sanitary
District v. EPA,
# 71—37 (March 22, 1971).
The City attempts to avoid this conclusion by arguing that
its delay was excusable.
The record shows that the City was
notified of the SWB—l11 requirements in May, 1968.
Having i4ecently
raised its sewer rates, the City decided to do nothing about
comp.ylng
with ‘the new regulation until it had a year’s experience
to determine the amount of revenue available from the increased
charge, which would affect the extent to which improvements
could be financed out of revenue rather than general obligation
bonds.
The City also sought a federal grant
(R. 31—32, 58).
In 1969 the City employed the consulting firm of Wilson and
Anderson to prepare a report
(due in January 1970) determining
what heeded to be
doile to comply with SWB—lJI (R.
311_35, 60_610.l
1.
Wilson and Anderson were also authorized to proceed with
the construction of primary sedimentation tanks that will
help to alleviate the bypass problem.
Bids have been
let for this construction, and its completion is expected
about September,
1971
(R.
66—67).
1—443
January’ 1970 came and went with no report from Wilson and
Anderson.
In April of that year the City told its consultants
they would have to have the report in by a “very strict” dead-
line or lose the contract; the new deadline was not met either;
in June the firm conceded it could not perform; in Atagust 1970
a second firm was hired, which submitted the desired report
the night before the hearing in this case——in March, 1971 CR.
69—73).
This report does not contain designs for the construction
of the needed facilities; design work is to start now and take
ten months
(R.
1311—36), and construction is to commence after
permits are obtained.
Compliance is ‘expected, as stated above,
by June 1973.
The City attempts to shift the blame for its delay to
its first contractor, Wilson and Anderson.
There is no
doubt that the contractor was derelict in its obligations toward
the City.
But, as we have stated before, the obligation to meet
deadlines
for
abating
pollution
is
that
of
the
City,
and
it
cannot
abdicate
its
responsibility
simply
by
employing
an
independent contractor:
“Other petitioners should, however, be
on notice that lack of delivery, when no efforts are made to
effectuate timely delivery, will not be looked upon favorably
by this Board.
It would be a foolish precedent for this Board
to
establish
that
a
variance
pctiticngr
after
having
dono
nothing to effect delivery may simply transfer the onus for non-
completion of a job to his vendor.”
Marblehead Lime Co. v.
EPA,
1
70—52 (March 17, 1971).
The City says it repeatedly contacted
Wilson and Anderson in an attempt to spur them on (R.
70), but
that is not enough.
‘The City may not idly flail its municipal
fists while its hired help sit~on its hands.
On an April
111
one cannot but wonder what the Internal Revenue Service would
say to a taxpayer who claims his accountant was too busy to
prepare the returns on time.
It was the City’s duty to build
into its contract with its consultant whatever escape and
penalty clauses were necessary to ensure that the contractor performed,
to keep a close watch on the progress of work before the report
was due, and to turn to another workman’promptly when the first
fell down on the job.
The City said in closing argument that
it supposed we could “find fault with the City for not firing
Wilson.and.Anderson sooner.”
(R.
231).
That’s right.
We can and
we do.
Moreover, the City was remiss long before its contractor hit
the canvas.
The City wasted a year during which it made no
progress toward designing advanced treatment facilities’, although
it now acknowledges that it is quite feasible to do design work
while figuring out whore the money for construction is to come
from (R.
106—07).
It entered into a contract for preliminary
study
that
was
to
produce
only
a
general
r!port
by
January
1970,
1—444
the date when final plans and specifications were due.
Thç
deadline for filing plans would not have been met even if
the contractor had done his job.
We find the City’s inat-
tention to its responsibilities is responsible for the proz—
ent violations of the regulations, and thus any hardship it
suffers as a result of those regulations it has brought upon
itself.
The
City
of
Mattoon
is
thus
in
flat
and inexbusable viol-
ation of its obligations ~underSWB—111.
It doS not qualify for
permission to go on violating the law with impunity, as it
has not shown satisfactory progress as the statute requires for
extension of a deferned timetable (section
36
(6)).
Yet, be-
cause the date for submission of plans has already passed,
we must set a new deadline; failure to meet the deadline will
result in additional penalties.
In essence the setting of a
new date amounts to a partial variance, though an undeserved
one.
For while we cannot condone the City’s infractions,
neither can we shut down the treatment plant, as we could
!ith most industrial processes.
To’do so would result in
more rather than less pollution, and thus the cost
or
a clos-
ing would enormouslj exceed the benefits.
Thus we have no
choice but to permit continued operation of the inadequate
plant,
but we must attach a number of conditions(ccct~on36
(a)
)
in
order
that
the
policies
‘of
the
statute
are not sub-
verted.
These conditions are designed, as in prior cases
(e.g., Mprquette Cement I4fg. Co. v. EPA, #70—23 (Jan.
6,
1971); City of Springfield v. EPA,
170—55
(Mar.
31, 1971)
),
to assure compliance as
rapidly
as
possible
and
to
deter
future violations of the law.
To the terms and conditions of
the
order
we
now
turn.
The Agency challenged the City’s estimates of the time
required for brInging the plant into compliance.
While the
City said ten months would be needed for planning, the Agency
said this could be done in fite;
and while the City asked a
year for construction
(after a delay to obtain permits),
the the ~gency said the plant can be built in nine months
(R.223).
It was of course disput’ed by the City’(R.
116).
Both the City’s and the Agency’s estimates were stated simply
as conclusions, with no supporting evidence.
The EPA attemp-
ted to show that the schedule could be advanced by overtIme
work; the City acknowledged that its timetable had been
based on’a normal five—day week, that if special priority
were given extra men could be put on the job, and that the
project “could be speeded up to a certain extent by apply—
ing’overtime work.”
(R.1211_26).
The City also testified
that some overtime work was aready
planned, within the ten
months allotted for design (R.136) and that “there is also
2.
Another federal witness testified that delays could jeo-
pardize the City’s eligibility for federal grart aid
(R.221
22).
It appears that delays have ‘already impaired the City’s
ranking on the federal priorIty list (R.2l0,230).
1—446
the
point
where
you
get
so
many
people
working
on
a
project
that you just can’t absorb them and give them the proper sup—
qrvision”
(K.
126).
We cannot on this record say the CIty has demonstrated
the need for the time
it
requests.
As
the
burden
is
on
the
petitioner to prove the time needed for any delay in compli-
ance (Sections 31 (c),
37),
we shall order the CIty to submit
complete plans by September 1, 1971, as requested by the
Agency,...and to meet- the July 1, 1972 deadline for completion
of the facilities required by SWB—l~I. The City will be free
as those dates approach to seek additictal time t~pondetailed
proof that it has applied every available resource to getting
the job done and that the time is too short.
We shall insist
at that time on receiving detailed work records demonstra-
ting the number of men employed on the design and construc-
tion tasks and the number of hours wor~:ed. The CIty has
said its time estimates are based on a fIve—day week;
It
wjll be incumbent on the City to show it has devoted that
much time and more to getting back on schedule.
:~
ensure
that it does we shall re;uire, as the statute provides when
a delayed, compliance date is set (sectI~ns33(b),
36(a),),’
the posting of a bond or other security In the amount of
$10,000, to be forfeited upon a finding by this Board that the
City has ‘faIled wlthc’ut satisfactory exc’ise to comply with
the terms of this order.
There is much talk in the record about the çroblems of
financing the necessary improvements.
The City has pussy—
footed about in a continuing effort to determine how much of
the financing can be done by revenue bonds, how zttch will.
be paid for by federal and state grants, and what remains to
be financed out of general oblIgation bends.
Kickapoo Creek
cannot wait. for these delIberations to be resolved.
Under
section
116
of the Act we have authority to order the sale of
bonds, including gencral obligation bonds, to finance improve-
ments requIred by Board order, without regard.to any
refer-
endum
or
to
any ‘statutory limits on bo:~dedindebtedness.
See
League of Women Voters v.
North Shore Sanitary DIstrict,
supra.
We think that remedy is approprIate here.
We add
that any suggestIon by the City that the uncertaIn availa-
bility of federal funds excuses delay in constructIon is
unfounded.
The point’was well stated by Mrs. Donald Wykis,
who testified in opposItion to the grant of a variance on
behalf of’the League of Women Voters of :~:attoon:
Municipalities were and are respon!ible for meeting the
deadlines wtth ~r :~Ithcutthe aId :f state
t?
federal
assistance.
The intent ot the Fe~oraland State Water
Quality Standards and the position of the League i5
simple:
The polluter is responsible for cleaning up
his own mess.
(11.206).
1-446
Accordingly, the CIty will be ordered to issue, no later than
July 15, 1971, revenue’or general obligation bonds in such
amount as may be necessary to pay for the improvements required
by SWB—l11.
Federal and state funds may be used later to rein—
burse the City for its expenditures, if they are made’avail—
able; but the City must proceed with its own funds at once.
The City argues that is should be relieved from the harsh
effects of a ban on new sewer connections that”the Environ-
mental Protection Agency has imposed as a result of its offen-
ses.
Specifically, it is pointed out that Kraft Foods is con-
structing a large frozen food plant at Mattoon and that the
City has’proralsed to acdept wastes from that plant for addi-
tional treatment in its sewage facilities
(11.38, 78—82).
We recognize that any delay in the opening of the factory
wguld be unfortunate, but it is the City that has not kept its
promise to Kraft; for tj~eCity knew years ago that it had to
upgrade its facilities, .and it had no reason to believe it
could accept additional wastes without doing so.
Additional
wastes fed to inadequate facilities, as we recently stressed
in League of Wozen,Voters v. North Shore Sanitary District,
970=7
(March
31, 1971), mean additional pollution.
The law
says pollutIon shall be reduced, not increased.
The sorry
state of Kickapoo Creek Indicates that no additional waste
load to that stream can be tolerated until advanced treatment
is provided and the interceptors expanded.
It is not enough
that Kraft is panning
to retain its wastes during storm
periods so that they do not add to the overflow problem
(11.153).
The existing ~econdaryfacilIties do not adequately protect
the creek Øuring dry weather eIther, and until, the City is
back on schedule IS may not add more waste to an already inade-
quate system.
Kraft may find alternative means of handling its
wastes until the City is able to treat them properly, or it’
may accept the fact that the City’s delay has caused the company
to postpone its opening.
What legal remedies Kraft may have
against the City it 15 not for us to say.
It is not. without
significance that the sewer ban places an important’incen—
tive upon the City to get the job done as quickly as is possIble.
,In order to assure diligence it is desirable to make dili-
gence in the interest of the City as well as of the suffering
public.
We agree with the Agency that the issue of a permit for
Kraft
is not before us,,since the issuance of permits is the
Agency’s responsibility.
We hold that the hardship to Kraft
because of the continuIng sewer ban does not justify increas-
ing the pollution of Klckapoo Creek, and, as in prior cases
(League of Women Voters v. North Shcre Sanitary District,
supra; EPA v. Village of Glendale Heights,’ #70—8 (February 17,
1971)), we order that no new sewer connections shall be madt
until the project gets back on schedule.
1—447
Finally, the City quite blatantly suggested
t’~at it
did
not think the deadlines were meant to be met:
There
has
been
a
change
of
policy
in
this
State
in
my
opinion.
And
perhaps
it’s
right.
I’m
not
crIticizing
the
change
of
policy,
but
I
think
now
the
State
is
say-
ing
you
have
to
do
this
when
not
too
long
ago
they
were
much
more
willing
to
go
along
with
you,
on
an
extension
of
time
and
of.thi
deadlines
that
have
been
established.
(11.237.
See
also
11.
92—95).
The
laws
are
meant
t:
be
obeyed.
Those
who
flout
them
must
be
made
an
example
to
deter
others
from like conduct.
The City will be ordered to pa:: a penal-
ty of $1000.
This
opinion
constitutes
the
Board’s
findings
of
fact
and conclusions of law.
ORDER
1.
The City of Mattoon is hereby’ c:’dered tt
submit
to
the Environ.ental Protection Agency, on c~before September
1, l97l,’final plans and specifications for the fa3llities
required to bring its suwa~ecollection ~nd treat::ent facill—
tiea into compliance wIth Rules and Regulations s::~—i11.
2.
‘The City of Mattoon is hereby ordered to complete
the construction of the facilitIes specifled in paragraph 1
of this order no later than July 1, 1972.
3.
The City of Nattoon shall post with the Environ-
mental Protection Agency, on or before
iCay
111, l9’l, a bond
or other security in a form to be determIned by the Agency,
in the amount of $10,000, such sum to be forfeite,i to the
State ,of Illinois in the event that the CIty does not comply
with the provisions of this order, as fotznd by the Pollution
Control Board in,a supplementary proceeding.
1$.
The City of Mattoon shall, on or before Juli 15,
1971, issue without referendum such revenue bonds
and/or
general obligation bonds as may be necess&ry to fInance the
design and construction of facilities specified In paragraph 1
of this order.
5.
The City of Mattoon shall complete the ~onstructIon
of the primary sedimentation tanks for rethacti-on of bypasses
by Septertber 1,1971
6.
The City of Mattoon shall not permit the c’onnoctlon
of any new sewers or other sources of waste to its facili-
ties, or any increase in the strength or concent:’~:Ionof
wastes discharced to its facilitIes, untt3 it dert,,’n.flrates to
the Agency that it is in full compliance with the require—
1—448
ments
of SWB—l~-I with
respect
to overloads,
bypasses,
and
the
provision
of advanced waste treatment.
7.
The City of ilattoon shall pay
to the State
of Illinois,
on or before Say i~4,97l,
the
sum
of ~iOOO
as
a
penaJt:i for
violation
of
the water Dollution regulation:; saecify1n~date:
for
the
submission
of
plans
and
the
~ettinp
of contracts
for
construction
of
sewage
treatment
facilities.
I
Regina
E.
Ryan,
certify
that
the Board
has aunroved the
above
opinion
this
14
____of
Anril
,
1971
2)
~
~
I
~/
:1
/
~-,
1_
449