ILLINOIS POLLUTIC:: CONTROL
    .
    BOARD
    April lL, 1971
    CITY
    OF
    MATTOOJ
    )
    I
    )
    V.
    )
    171—8
    ENVIRONMENTAL
    PROTECTION
    AGENCY
    )
    Opinion of the Board (by
    Mr.
    Curr~.e):
    This is a most depressing case in which the City asks for a
    variance because it thought the state was not serious when it
    prescribed deadlines for the conctruction of additIonal sewage
    treatment facilities.
    Lefl any dcubt remain, we declare once
    more that the state is indeed serIous about expecting obedIence
    to the
    lawd
    It is high time people reco~n!zedthat the persuasive
    demand for
    lat: and order applies to polluters as well as to
    burglars.
    110w municipal and corp~rateofflcials can cluck their
    tongues
    over
    wayward
    youth
    while
    çayiiag no attcntlon to their
    own legal responsibilities is beyond our comprehension.
    The City of Mattoon operates a seriously overloaded sewase
    treatment plant fed by an overloaded sewer system
    (B.
    86—87,
    165).
    Secondary treatment is provided to whatever flows the plant
    can handle, but additional flows are given only primary treat,ent
    (which removes the
    larger
    hunks)
    ~r
    bypassed
    as
    raw
    sewage
    dIrectly
    to Xickapoo Creek from the plant or from the sewers themselves
    (R.
    88—89,
    113).
    Such overflows
    occur
    five or six times per
    month
    (R.
    139).
    Kickapoo Creek is
    a
    small
    intrastate stream w±thlittle
    capacity to assimilate wastes.
    The undisputed testimony is that
    the creek is seriously polluted below the plant and does not
    completely recover for six miles downstream
    (R.
    186).
    Fish have
    been missing for years
    (R.
    179,
    191$,
    & EPA recommendation);
    there are complaints of odors
    CR.
    168, l72)~the stream is in-
    habited by organisms tolerant of pollution
    (R.
    186, 191—93),
    it is troubled by sludge banks, t:ilet tIssue, and fecal materIal
    (R. 167).
    The EPA without contradictIon attributed these con--
    ditions to the Nattoon sewage failit~esCR.
    182, 187).
    The Environmental Protection Agenty in its recommendation reported
    that one
    person
    lntervlet;ed
    sa!t
    “he
    had seen his cows leave a
    standing
    position
    in
    tha
    creek
    ~:cor.
    to
    wa)k to a nearby
    sprln—
    fed
    pool
    in
    order
    to
    obtain
    drInk~.ngwate:’.”
    1
    —441

    It was no idle whim, therefore, that prompted the state
    Sanitary Water Board in March, 1968 to prescribe that on such
    streams as Kickapoo Creek secondary treatment was insufficient
    and that bypasses must be eliminated.
    The implementation
    schedule in Rules and Regulations SWB—111, Rule 1.08 paragraphs
    9,
    lib, and 111, requires that advanced treatment to produce an
    effluent with biochemical oxygen demand (BOD) of ilmg/l and
    suspended solids of
    5
    mg/i must be provided, and bypasses given
    primary treatment and chlorination, by July,
    l9’72.
    In order to
    provide interim checkpoints to determine whether progress was
    being made, the regulations also reqgired that for cities above
    10,000 population (such as Mattoon) plans and specifications be
    completed 30 months before the deadline for completion of construction
    and construction contracts be awarded 21 months before..
    Notice
    of these requirements was admittedly received by the City in the
    spring of 1968
    (R.
    160).
    The~preparationof plans, the City now agrees, is a task
    that can be done within one year, and construction within another.
    The City was given by the regulation four years for a job it
    concedes can be done in two.
    .
    Yet today it stands naked before
    this Board with no plans or specifications for advanced treat-
    ment even begun, much less completed, and with construction
    not slated to begin for more than another year in the
    t,,ture.
    The City acknowledges that it is “slightly” behind schedule and
    asks us placidly to approve a new schedule that would allow
    the filing, of plans in March 1972, the letting of contracts
    in, May 1972, and the completion of facilities in June 1973.
    The statute provides for variances only upon a showing by
    the petitioner that compliance with the, law would impose an
    “arbitrary or unreasonable hardship” (Environmental’Protection
    Act, section
    35).
    We have often made clear that whether the
    hardship of compliance is arbitrary or unreasonable can only
    be determined by a comparison of the benefits and of the costs.
    bf compliance:
    “The statutory variance test of unreasonable
    hardship is not satisfied by proof of hardship alone; it must
    be demonstrated that the hardships of complying with the law
    are disproportionately large in comparison to the benefits to
    the public of so doing.”
    Texaco,’Inc. v.
    EPA, #70—29
    (I!eb,
    17,.
    1971).
    This is made clear by our procedural rules, which in
    Rule llOl(a)(2) require the petitioner to include in his petition
    “a descriptio4 of the costs that compliance’would impose on the
    petitioner and others and of the injury
    tI~iatthe grant of the
    variance would impose on the public.”
    1—442

    The
    petition
    in
    this
    case does not comply with the
    rules.
    It
    contains
    no
    debcription
    of
    the
    injury
    that
    grant
    of
    the
    variance would impose on the public, and it includes no estimate
    of the contaminants discharged, as required by Rule I10l(a)(1).
    In light of the evidence developed at the hearing, however, we
    shall proceed to consideration of the merIts.
    The hardship complained of is that, since the City has
    already missed the deadline for the submission of plans
    (January
    1970) and the letting of contracts (September 1970), it cannot
    possibly meet them and that the time remaining before the final
    deadline for completion of the facilities is too short to permit
    that date to be met either (R.
    75).
    We have already held, as
    should have been obvious, that “one cannot qualify for a variance
    simply by ignoring the timetable and starting late.
    .
    .
    .
    To
    allow a variance on the basis of.
    .
    (such
    allegations would
    establish the preposterous proposition that the very, existence
    of a violation is a ground for ‘excusing it.”
    Decatur Sanitary
    District v. EPA,
    # 71—37 (March 22, 1971).
    The City attempts to avoid this conclusion by arguing that
    its delay was excusable.
    The record shows that the City was
    notified of the SWB—l11 requirements in May, 1968.
    Having i4ecently
    raised its sewer rates, the City decided to do nothing about
    comp.ylng
    with ‘the new regulation until it had a year’s experience
    to determine the amount of revenue available from the increased
    charge, which would affect the extent to which improvements
    could be financed out of revenue rather than general obligation
    bonds.
    The City also sought a federal grant
    (R. 31—32, 58).
    In 1969 the City employed the consulting firm of Wilson and
    Anderson to prepare a report
    (due in January 1970) determining
    what heeded to be
    doile to comply with SWB—lJI (R.
    311_35, 60_610.l
    1.
    Wilson and Anderson were also authorized to proceed with
    the construction of primary sedimentation tanks that will
    help to alleviate the bypass problem.
    Bids have been
    let for this construction, and its completion is expected
    about September,
    1971
    (R.
    66—67).
    1—443

    January’ 1970 came and went with no report from Wilson and
    Anderson.
    In April of that year the City told its consultants
    they would have to have the report in by a “very strict” dead-
    line or lose the contract; the new deadline was not met either;
    in June the firm conceded it could not perform; in Atagust 1970
    a second firm was hired, which submitted the desired report
    the night before the hearing in this case——in March, 1971 CR.
    69—73).
    This report does not contain designs for the construction
    of the needed facilities; design work is to start now and take
    ten months
    (R.
    1311—36), and construction is to commence after
    permits are obtained.
    Compliance is ‘expected, as stated above,
    by June 1973.
    The City attempts to shift the blame for its delay to
    its first contractor, Wilson and Anderson.
    There is no
    doubt that the contractor was derelict in its obligations toward
    the City.
    But, as we have stated before, the obligation to meet
    deadlines
    for
    abating
    pollution
    is
    that
    of
    the
    City,
    and
    it
    cannot
    abdicate
    its
    responsibility
    simply
    by
    employing
    an
    independent contractor:
    “Other petitioners should, however, be
    on notice that lack of delivery, when no efforts are made to
    effectuate timely delivery, will not be looked upon favorably
    by this Board.
    It would be a foolish precedent for this Board
    to
    establish
    that
    a
    variance
    pctiticngr
    after
    having
    dono
    nothing to effect delivery may simply transfer the onus for non-
    completion of a job to his vendor.”
    Marblehead Lime Co. v.
    EPA,
    1
    70—52 (March 17, 1971).
    The City says it repeatedly contacted
    Wilson and Anderson in an attempt to spur them on (R.
    70), but
    that is not enough.
    ‘The City may not idly flail its municipal
    fists while its hired help sit~on its hands.
    On an April
    111
    one cannot but wonder what the Internal Revenue Service would
    say to a taxpayer who claims his accountant was too busy to
    prepare the returns on time.
    It was the City’s duty to build
    into its contract with its consultant whatever escape and
    penalty clauses were necessary to ensure that the contractor performed,
    to keep a close watch on the progress of work before the report
    was due, and to turn to another workman’promptly when the first
    fell down on the job.
    The City said in closing argument that
    it supposed we could “find fault with the City for not firing
    Wilson.and.Anderson sooner.”
    (R.
    231).
    That’s right.
    We can and
    we do.
    Moreover, the City was remiss long before its contractor hit
    the canvas.
    The City wasted a year during which it made no
    progress toward designing advanced treatment facilities’, although
    it now acknowledges that it is quite feasible to do design work
    while figuring out whore the money for construction is to come
    from (R.
    106—07).
    It entered into a contract for preliminary
    study
    that
    was
    to
    produce
    only
    a
    general
    r!port
    by
    January
    1970,
    1—444

    the date when final plans and specifications were due.
    Thç
    deadline for filing plans would not have been met even if
    the contractor had done his job.
    We find the City’s inat-
    tention to its responsibilities is responsible for the proz—
    ent violations of the regulations, and thus any hardship it
    suffers as a result of those regulations it has brought upon
    itself.
    The
    City
    of
    Mattoon
    is
    thus
    in
    flat
    and inexbusable viol-
    ation of its obligations ~underSWB—111.
    It doS not qualify for
    permission to go on violating the law with impunity, as it
    has not shown satisfactory progress as the statute requires for
    extension of a deferned timetable (section
    36
    (6)).
    Yet, be-
    cause the date for submission of plans has already passed,
    we must set a new deadline; failure to meet the deadline will
    result in additional penalties.
    In essence the setting of a
    new date amounts to a partial variance, though an undeserved
    one.
    For while we cannot condone the City’s infractions,
    neither can we shut down the treatment plant, as we could
    !ith most industrial processes.
    To’do so would result in
    more rather than less pollution, and thus the cost
    or
    a clos-
    ing would enormouslj exceed the benefits.
    Thus we have no
    choice but to permit continued operation of the inadequate
    plant,
    but we must attach a number of conditions(ccct~on36
    (a)
    )
    in
    order
    that
    the
    policies
    ‘of
    the
    statute
    are not sub-
    verted.
    These conditions are designed, as in prior cases
    (e.g., Mprquette Cement I4fg. Co. v. EPA, #70—23 (Jan.
    6,
    1971); City of Springfield v. EPA,
    170—55
    (Mar.
    31, 1971)
    ),
    to assure compliance as
    rapidly
    as
    possible
    and
    to
    deter
    future violations of the law.
    To the terms and conditions of
    the
    order
    we
    now
    turn.
    The Agency challenged the City’s estimates of the time
    required for brInging the plant into compliance.
    While the
    City said ten months would be needed for planning, the Agency
    said this could be done in fite;
    and while the City asked a
    year for construction
    (after a delay to obtain permits),
    the the ~gency said the plant can be built in nine months
    (R.223).
    It was of course disput’ed by the City’(R.
    116).
    Both the City’s and the Agency’s estimates were stated simply
    as conclusions, with no supporting evidence.
    The EPA attemp-
    ted to show that the schedule could be advanced by overtIme
    work; the City acknowledged that its timetable had been
    based on’a normal five—day week, that if special priority
    were given extra men could be put on the job, and that the
    project “could be speeded up to a certain extent by apply—
    ing’overtime work.”
    (R.1211_26).
    The City also testified
    that some overtime work was aready
    planned, within the ten
    months allotted for design (R.136) and that “there is also
    2.
    Another federal witness testified that delays could jeo-
    pardize the City’s eligibility for federal grart aid
    (R.221
    22).
    It appears that delays have ‘already impaired the City’s
    ranking on the federal priorIty list (R.2l0,230).
    1—446

    the
    point
    where
    you
    get
    so
    many
    people
    working
    on
    a
    project
    that you just can’t absorb them and give them the proper sup—
    qrvision”
    (K.
    126).
    We cannot on this record say the CIty has demonstrated
    the need for the time
    it
    requests.
    As
    the
    burden
    is
    on
    the
    petitioner to prove the time needed for any delay in compli-
    ance (Sections 31 (c),
    37),
    we shall order the CIty to submit
    complete plans by September 1, 1971, as requested by the
    Agency,...and to meet- the July 1, 1972 deadline for completion
    of the facilities required by SWB—l~I. The City will be free
    as those dates approach to seek additictal time t~pondetailed
    proof that it has applied every available resource to getting
    the job done and that the time is too short.
    We shall insist
    at that time on receiving detailed work records demonstra-
    ting the number of men employed on the design and construc-
    tion tasks and the number of hours wor~:ed. The CIty has
    said its time estimates are based on a fIve—day week;
    It
    wjll be incumbent on the City to show it has devoted that
    much time and more to getting back on schedule.
    :~
    ensure
    that it does we shall re;uire, as the statute provides when
    a delayed, compliance date is set (sectI~ns33(b),
    36(a),),’
    the posting of a bond or other security In the amount of
    $10,000, to be forfeited upon a finding by this Board that the
    City has ‘faIled wlthc’ut satisfactory exc’ise to comply with
    the terms of this order.
    There is much talk in the record about the çroblems of
    financing the necessary improvements.
    The City has pussy—
    footed about in a continuing effort to determine how much of
    the financing can be done by revenue bonds, how zttch will.
    be paid for by federal and state grants, and what remains to
    be financed out of general oblIgation bends.
    Kickapoo Creek
    cannot wait. for these delIberations to be resolved.
    Under
    section
    116
    of the Act we have authority to order the sale of
    bonds, including gencral obligation bonds, to finance improve-
    ments requIred by Board order, without regard.to any
    refer-
    endum
    or
    to
    any ‘statutory limits on bo:~dedindebtedness.
    See
    League of Women Voters v.
    North Shore Sanitary DIstrict,
    supra.
    We think that remedy is approprIate here.
    We add
    that any suggestIon by the City that the uncertaIn availa-
    bility of federal funds excuses delay in constructIon is
    unfounded.
    The point’was well stated by Mrs. Donald Wykis,
    who testified in opposItion to the grant of a variance on
    behalf of’the League of Women Voters of :~:attoon:
    Municipalities were and are respon!ible for meeting the
    deadlines wtth ~r :~Ithcutthe aId :f state
    t?
    federal
    assistance.
    The intent ot the Fe~oraland State Water
    Quality Standards and the position of the League i5
    simple:
    The polluter is responsible for cleaning up
    his own mess.
    (11.206).
    1-446

    Accordingly, the CIty will be ordered to issue, no later than
    July 15, 1971, revenue’or general obligation bonds in such
    amount as may be necessary to pay for the improvements required
    by SWB—l11.
    Federal and state funds may be used later to rein—
    burse the City for its expenditures, if they are made’avail—
    able; but the City must proceed with its own funds at once.
    The City argues that is should be relieved from the harsh
    effects of a ban on new sewer connections that”the Environ-
    mental Protection Agency has imposed as a result of its offen-
    ses.
    Specifically, it is pointed out that Kraft Foods is con-
    structing a large frozen food plant at Mattoon and that the
    City has’proralsed to acdept wastes from that plant for addi-
    tional treatment in its sewage facilities
    (11.38, 78—82).
    We recognize that any delay in the opening of the factory
    wguld be unfortunate, but it is the City that has not kept its
    promise to Kraft; for tj~eCity knew years ago that it had to
    upgrade its facilities, .and it had no reason to believe it
    could accept additional wastes without doing so.
    Additional
    wastes fed to inadequate facilities, as we recently stressed
    in League of Wozen,Voters v. North Shore Sanitary District,
    970=7
    (March
    31, 1971), mean additional pollution.
    The law
    says pollutIon shall be reduced, not increased.
    The sorry
    state of Kickapoo Creek Indicates that no additional waste
    load to that stream can be tolerated until advanced treatment
    is provided and the interceptors expanded.
    It is not enough
    that Kraft is panning
    to retain its wastes during storm
    periods so that they do not add to the overflow problem
    (11.153).
    The existing ~econdaryfacilIties do not adequately protect
    the creek Øuring dry weather eIther, and until, the City is
    back on schedule IS may not add more waste to an already inade-
    quate system.
    Kraft may find alternative means of handling its
    wastes until the City is able to treat them properly, or it’
    may accept the fact that the City’s delay has caused the company
    to postpone its opening.
    What legal remedies Kraft may have
    against the City it 15 not for us to say.
    It is not. without
    significance that the sewer ban places an important’incen—
    tive upon the City to get the job done as quickly as is possIble.
    ,In order to assure diligence it is desirable to make dili-
    gence in the interest of the City as well as of the suffering
    public.
    We agree with the Agency that the issue of a permit for
    Kraft
    is not before us,,since the issuance of permits is the
    Agency’s responsibility.
    We hold that the hardship to Kraft
    because of the continuIng sewer ban does not justify increas-
    ing the pollution of Klckapoo Creek, and, as in prior cases
    (League of Women Voters v. North Shcre Sanitary District,
    supra; EPA v. Village of Glendale Heights,’ #70—8 (February 17,
    1971)), we order that no new sewer connections shall be madt
    until the project gets back on schedule.
    1—447

    Finally, the City quite blatantly suggested
    t’~at it
    did
    not think the deadlines were meant to be met:
    There
    has
    been
    a
    change
    of
    policy
    in
    this
    State
    in
    my
    opinion.
    And
    perhaps
    it’s
    right.
    I’m
    not
    crIticizing
    the
    change
    of
    policy,
    but
    I
    think
    now
    the
    State
    is
    say-
    ing
    you
    have
    to
    do
    this
    when
    not
    too
    long
    ago
    they
    were
    much
    more
    willing
    to
    go
    along
    with
    you,
    on
    an
    extension
    of
    time
    and
    of.thi
    deadlines
    that
    have
    been
    established.
    (11.237.
    See
    also
    11.
    92—95).
    The
    laws
    are
    meant
    t:
    be
    obeyed.
    Those
    who
    flout
    them
    must
    be
    made
    an
    example
    to
    deter
    others
    from like conduct.
    The City will be ordered to pa:: a penal-
    ty of $1000.
    This
    opinion
    constitutes
    the
    Board’s
    findings
    of
    fact
    and conclusions of law.
    ORDER
    1.
    The City of Mattoon is hereby’ c:’dered tt
    submit
    to
    the Environ.ental Protection Agency, on c~before September
    1, l97l,’final plans and specifications for the fa3llities
    required to bring its suwa~ecollection ~nd treat::ent facill—
    tiea into compliance wIth Rules and Regulations s::~—i11.
    2.
    ‘The City of Mattoon is hereby ordered to complete
    the construction of the facilitIes specifled in paragraph 1
    of this order no later than July 1, 1972.
    3.
    The City of Nattoon shall post with the Environ-
    mental Protection Agency, on or before
    iCay
    111, l9’l, a bond
    or other security in a form to be determIned by the Agency,
    in the amount of $10,000, such sum to be forfeite,i to the
    State ,of Illinois in the event that the CIty does not comply
    with the provisions of this order, as fotznd by the Pollution
    Control Board in,a supplementary proceeding.
    1$.
    The City of Mattoon shall, on or before Juli 15,
    1971, issue without referendum such revenue bonds
    and/or
    general obligation bonds as may be necess&ry to fInance the
    design and construction of facilities specified In paragraph 1
    of this order.
    5.
    The City of Mattoon shall complete the ~onstructIon
    of the primary sedimentation tanks for rethacti-on of bypasses
    by Septertber 1,1971
    6.
    The City of Mattoon shall not permit the c’onnoctlon
    of any new sewers or other sources of waste to its facili-
    ties, or any increase in the strength or concent:’~:Ionof
    wastes discharced to its facilitIes, untt3 it dert,,’n.flrates to
    the Agency that it is in full compliance with the require—
    1—448

    ments
    of SWB—l~-I with
    respect
    to overloads,
    bypasses,
    and
    the
    provision
    of advanced waste treatment.
    7.
    The City of ilattoon shall pay
    to the State
    of Illinois,
    on or before Say i~4,97l,
    the
    sum
    of ~iOOO
    as
    a
    penaJt:i for
    violation
    of
    the water Dollution regulation:; saecify1n~date:
    for
    the
    submission
    of
    plans
    and
    the
    ~ettinp
    of contracts
    for
    construction
    of
    sewage
    treatment
    facilities.
    I
    Regina
    E.
    Ryan,
    certify
    that
    the Board
    has aunroved the
    above
    opinion
    this
    14
    ____of
    Anril
    ,
    1971
    2)
    ~
    ~
    I
    ~/
    :1
    /
    ~-,
    1_
    449

    Back to top