ILLINOIS POLLUTION CONTROL BOARD
July 12, 2001
J.R. & SONS, INC.,
Petitioner,
v.
ILLINOIS ENVIRONMENTAL
PROTECTION AGENCY,
Respondent.
)
)
)
)
)
)
)
)
)
)
PCB 01-130
(UST - FRD)
ORDER OF THE
BOARD (by C.A. Manning):
On July 6, 2001, J.R. & Sons, Inc. (petitioner), filed a petition for review of an Illinois
Environmental Protection Agency (Agency) determination regarding petitioner’s application for
reimbursement of corrective action costs from the Illinois Underground Storage Tank Fund. The
petitioner allegedly incurred such expenses at its facility located at Main and Route 150, Champaign
County, Illinois.
The Board accepts this matter for hearing. The Board’s rules require that the Agency file its
entire record of the corrective action plan within 30 days of notice of the petition. See 35 Ill. Adm.
Code 105.116. Hearings must be scheduled and completed in a timely manner, pursuant to the
applicable statutory decision deadline, or the deadline as extended by waiver. See 35 Ill. Adm. Code.
101.308, 105.114.
Absent any future waivers of the decision deadline, the statutory decision deadline is now
November 3, 2001 (120 days from July 6, 2001); the Board meeting immediately preceding the
decision deadline is scheduled for November 1, 2001.
IT IS SO ORDERED.
Board Member T.E. Johnson abstained.
I, Dorothy M. Gunn, Clerk of the Illinois Pollution Control Board, hereby certify that the above
order was adopted on the 12th day of July 2001 by a vote of 4-0.
Dorothy M. Gunn, Clerk
2
Illinois Pollution Control Board