ILLINOIS POLLUTION CONTROL AGENCY
August
18,
1982
MODINE MANUFACTURING COMPANY,
)
Petitioner,
PCB 79—112
ILLINOIS ENVIRONMENTAL PROTECTION
)
AGENCY,
Respondent.
ORDER OF THE BOARD (by
I.
G.
Goodman):
On July 12,
1982 the
Illinois Environmental Protection
Agency (Agency)
filed a Motion to Dismiss this variance petition
—-
its third such Motion within a year.
On July 20,
1982 Modine
Manufacturing Company (Modine)
filed a Response and Motion for
Additional
Time.
The Agency filed a Response to Modine’s Motion
for Additional Time on July
30,
1982, to which Modine filed
a
Reply on August
3,
1982,
No pre—hearing conferences or public
hearings are scheduled at this time.
This proceeding was initiated with the variance petition
filed by Modine on May 21,
1979.
The Agency’s recommendation
to deny was filed on June
25,
1979.
Two hearings were scheduled
in
1979, but both were continued.
Aside from waivers of the
ninety—day decision period and limited discovery, there is no
record of this matter progressing during 1980.
Two hearings
were scheduled in the first half of 1981, but both were again
continued.
On August 13, 1981 the Agency moved to dismiss this matter.
On August 20,
1981 the motion was denied on the representation
that Modine was preparing an amended variance petition.
Modine
was allowed until September 28,
1981 to file,
or be suject to
dismissal.
A first Amended Petition for Variance was filed on
September 24,
1981.
Modine alleged therein that
it knew of no
available treatment process to relieve its need for variance,
that Rule 4l0(c)(iii)
of Chapter 3:
Water Pollution provided
it an exemption, that variance was sought only until such time
as its site-specific rule change, R79—8,
was finalized,
which
it anticipated would provide permanent relief, and that denial
of the variance requested may result in Modine closing its
facility.
Again, the Agency recommended denial
in its Recom-
mendation filed November
2,
1981.
47-519
2
No further progress is indicated in the Board’s record in
this matter, until the Agency again moved to dismiss on April
9,
1982.
On April 2l~ 1982 Modine responded that it intended to
file a Second Amended
Variance
Petition circumstances having
changed since the First Amended version was filed on September
24,
1981.
Modine alleged that it had proceeded to retain a con-
sultant to study the problem and propose a compliance plan; that
it no longer intended to close its plant due to financial diffi—
culties;
and that it would withdraw~7~~In addition, Modine
stated that additional discharge problems had since been identified
which necessitate additional variance relief,
This Second Amended
version was filed on ?~pri1
27,
1982.
Recognizing that this was the second time Modine had re-
sponded to Agency motions to dismiss with an amended petition,
the Board ordered hearing
in this matter take place no later than
forty-five days after the Agency filed its Recommendation on the
Second Amended version~
The Agency filed a Recommendation to deny
on May 28,
1982.
A pre—hearing conference was scheduled for June
11,
1982 but was cancelled.
Pursuant to the Board Order,
hearing
should have taken place no later than July
12,
1982.
None having
been scheduled,
the Agency again moved to dismiss on July 12,
1982.
The pleadings subsequent to that motion are listed above.
The Second Amended Petition alleges that Modine was develop-
ing a compliance plan with its consultant,
Dr. Patterson, which
will not reach fruition until approximately September,
1983 or
later.
According to Modin&s July 20,
1982 Response to the Motion
to Dismiss,
it is ~foi:Lowinga compliance program involving a
review by Dr. Patterson to develop a compliance program.”
Petitioner Modine apparently misunderstands the purpose and pro-
ceedings
for Variance pursuant to Title IX of the Environmental
Protection Act,
Compliance plans are to be developed prior to
and included
in the variance petitioned, not during its pendency.
This is not to say that
if no solution to the problem is apparent,
the variance requested cannot include a time schedule and com-
pliance plan designed to study and resolve the problem.
Further-
more,
the ninety—day decision period provided in Title
IX is
intended to provide an expeditious evaluation of whether peti-
tioner’s activity harms the environment, as well
as provide
petitioner timely relief.
The Board finds that the variance proceeding,
as
set out
in the Act and Board Procedural Rules, has been misused
in this
case, and that Modine has acted contrary to the April
29,
1982
Board Order.
Modin&s Motion for Additional Time,
filed eight
days after the last possible date for hearing,
is denied and
this matter is dismissed without prejudice.
Petitioner
is
granted leave to refile a variance petition which complies with
Section 104.121 of Chapter
I,
Part
104, Variances (Former
Rule 401) and contains current information and an appropriate
compliance plan.
47-520
3
IT IS SO ORDERED.
Board Member J, Anderson concurred.
I, Christan
L,
Moffett, Clerk of the Illinois Pollution
Control Boa~d,hereby certify that the above Order was ad,qpted
on the
i8”~’
day of
i~-~-
,
1982 by a vote of
~--c~
stan L.
Illinois Pollutio:
Board
47-521