ILLINOIS POLLUTION CONTROL BOARD
    February 14,
    1973
    CITY OF EAST
    ST.
    LOUIS
    P03 72—393
    ENVIRONMENTAL PROTECTION AGENCY
    CONSOLIDATED
    VILLAGE OF SAUGET
    v.
    )
    PCB 72—396
    P03 72—407
    ENVIRONMENTAL PROTECTION AGENCY
    OPINION AND ORDER OF
    THE BOARD
    (by Mr.
    Dumelle):
    This case involves three separate petitions
    for variance which
    have been consolidated.
    Hearing was held on the consolidated
    matter on December
    18,
    1972.
    East St. Louis requests
    a variance from Rule
    404
    (a)
    (i)
    of
    the
    Illinois Water Pollution Regulations which requires
    that
    no
    effluent
    to the Mississippi River shall exceed
    30 mg/i BOD5
    or
    37
    mg/i suspended solids after December
    31,
    1973.
    They now operate
    a primary sewage treatment plant consisting
    of
    sedimentation for
    removal of solids
    and skimming
    for floating matter.
    The materials
    so removed
    are pumped into two sludge thickening tanks,
    then pumped
    to vacuum sludge dryers and then removed
    to
    a
    landfill.
    The
    influent to the plant averages eighteen million gallons per day
    (MGD)
    consisting of 65
    industrial waste, 25
    domestic sewage and 9
    infiltration.
    The plant serves the area within the city limits of
    East St.
    Louis which has
    a population
    of
    82,000.
    The plant also
    serves a number of industries, the largest of which are manufacturing
    and meat packing plants.
    The effluent is discharged directly to the
    Mississippi River.
    The East St. Louis operating report for September,
    1972 shows the
    BOD level at 150 mg/i and the suspended solids at 180 mg/l.
    Samples
    taken
    by
    the Agency on July 28, 1972 show
    55 mg/l BOD,
    280 mg/l sus-
    pended solids and 460,000/100 ml fecal coiiform.
    Samples taken by
    the Agency on September
    6,
    1972 show 110 mg/i BOD,
    80 mg/i suspended
    solids and 7700/100 ml fecal coliform,
    7
    —93

    On November
    3,
    1971 East St. Louis entered into an agreement
    with an engineering consultant to determine preliminary and final
    engineering designs for a secondary waste treatment
    system.
    A
    preliminary engineering report was submitted in September,
    1972
    and the final plans are expected in March,
    1973.
    The Village of Sauget requests two variances.
    One is similar
    to East St. Louis in that it also seeks relief from Rule 404
    (a)
    (1)
    of the Water Pollution Regulations
    (72-396) and the other
    (72-407)
    requests an extension of the variance granted in PCB71—287 related to
    the installation of secondary treatment facilities.
    The latter
    petition also requests an extension of the November 15, 1972 dead-
    line provided in paragraph 1
    (b)
    of the Order for completion of
    final engineering design to January 15,
    1973.
    They also request an
    extension of the bond forfeiture date to January
    25,
    1973.
    The Sauget plant provides only primary treatment and has a
    design average flow of
    32 MGD.
    It discharges directly to the
    Mississippi
    River.
    The average daily flow is
    20 MGD which is 99
    industrial.
    The
    plant serves the area within the Village limits
    which has a population of 220 persons.
    The industrial load has a
    population equivalent of
    320,000.
    There are six industries tribu-
    tary to the plant, the largest of which
    is Monsanto Chemical Company.
    Effluent samples taken by
    the
    Agency on February
    1,
    1972 show
    180 mg/i SOD,
    38
    mg/i
    suspended solids and less than 100/100 ml fecal
    coliforni.
    The May 10, 1972 Agency samples show
    75 mg/i BOD,
    42 mg/i
    suspended solids and 10/100 ml fecal coliform.
    The August 29,
    1972
    Agency samples
    show 100 mg/i BOD and 65 mg/i suspended solids.
    The
    August sample also
    showed
    other
    concentrations of iron
    (8.4 mg/i)
    lead
    (0.1 mg/i), mercury
    (.007 mg/i),
    zinc
    (1.5 mg/i),
    ammonia
    nitrogen
    (42 mg/i)
    and a low pH
    (3.5).
    Sauget~sengineering consultant completed its Phase IIA process
    design work on July 15,
    1972.
    A formal written contract for Phase
    IIB engineering services was entered into with the same consultant
    on September 29,
    1972.
    Except as relates
    to the November 15, 1972
    interim deadline, Sauget has appeared to comply with the conditions
    of the December 21 and 30, 1971 Board Orders in PCB71-287.
    That
    Order provided, among other things that Sauget complete its final
    engineering design by November 15, 1972 and that they post a bond
    of $50,000
    to be forfeited if the deadline was not met.
    They are
    now requesting
    a two month extension until January 15,
    1973.
    Inasmuch
    as Sauget has made substantial progress on its program in the past
    year we will grant the short extension requested.
    The bond will now
    apply to the extended January 15, 1973 date.
    —2—
    7—94

    The petitioners are participants
    in
    the Southwestern
    Illinois
    Metropolitan Area Planning Commission
    (SIMAPC) which
    is charged with
    development of the area’s official water quality management plan.
    There are alternative plans for regionalization of
    the
    area
    in which
    the petitioners are located.
    From investigation of those plans
    it
    appears that
    a delay in construction of the required facilities may
    well occur.
    A six month,
    $50,000 study is currently being conducted
    to determine the feasibility of treating combined wastes f~romEast
    St. Louis, Sauget, Lansdowne and Cahokia.
    Preliminary results of
    the
    study have indicated that those combined wastes do appear to be biologic
    ally treatable.
    Under the regional plan,
    each
    of
    the primary treatment
    plants would be retained with their effluents being transported to
    the
    regional secondary plant.
    As an alternative to
    a regional secondary system the petitioners
    would build their own secondary plants.
    The results of the SIMAPC
    feasibility study will determine which alternative to take.
    The peti-
    tioners, however, are currently developing plans for their own secondary
    plants
    in the event that such alternative becomes more feasible after
    the
    study
    is completed.
    As
    to the relative costs involved,
    it is es-
    timated
    that the capital cost of a regional plant would be $21 million
    as compared to
    $29 million total
    for separate plants.
    It
    is also
    estimated that over the life of the regional plant’s operation and
    maintenance,
    savings of around $30 million could be expected over what
    it would cost to operate and maintain separate plants.
    We
    find that in either event the December 31, 1973 completion date
    will not be achieved.
    Inasmuch as there has been significant progress
    made up until now and also since the petitioners have made commitments
    to continue that progress we will grant a one year variance from Rule
    404 (a) (i)
    of the Water Regulations.
    We should note that at the hearing
    a representative of the Federal EPA also suggested that under the cir-
    cumstances
    a variance should be granted.
    This opinion constitutes the Board’s findings of fact and conclu-
    sions of law.
    ORDER
    1.
    The Village of Sauget
    is granted an extension until January
    15,
    1973
    from the interim date of November 15,
    1972 for completion of
    its
    final engineering plans
    as specified in PCB71-287 orders dated
    December 21 and
    30, 1971.
    The bond is also extended to January 15,
    1973.
    2.
    The interim order entered herein on February 6,
    1973
    is hereby
    incorporated into this order and made
    a part
    hereof.
    I, Christan L.
    Moffett, Clerk of the Pollution Control Board, hereby
    certif
    that the a~oe Opinion and Order was adopted by the Board on
    the
    ____
    day of~
    ,
    1973, by a vote of
    ~
    to
    O
    —3—
    7
    95

    .
    .

    Back to top