    ILLINOIS POLLUTION CONTROL BOARD
    2
    August 9, 2004
    3
    4
    5 IN THE MATTER OF:
    PROPOSED AMENDMENTS TO:
    6 REGULATION OF PETROLEUM
    LEAKING UNDERGROUND STORAGE TANKS
    7 (35 ILL. ADM. CODE 732)
    R04-22
    (UST Rulemaking)
    8 __________________________________
    9 IN THE MATTER OF:
    PROPOSED AMENDMENTS TO:
    10 REGULATIONS OF PETROLEUM
    LEAKING UNDERGROUND STORAGE TANKS
    11 (35 ILL. ADM. CODE 734)
    R04-23
    (UST Rulemaking)
    12
    13
    14
    The following proceedings were held before the Illinois
    15 Pollution Control Board, August 9, 2004, at the Department
    16 of Natural Resources Building, One Natural Resources Way,
    17 Springfield, Illinois, before Ann Marie Hollo, CSR, RMR.
    18
    19
    20
    21
    Keefe Reporting Company
    11 North 44th Street
    22
    Belleville, Illinois 62226
    (618) 277-0190
    23
    (800) 244-0190
    24
    Keefe Reporting Company
    (618) 244-0190

    2
    1
    APPEARANCES:
    2
    3 OFFICE OF THE ILLINOIS POLLUTION CONTROL BOARD
    James R. Thompson Center, 100 W.
    4 Randolph Street, Suite 11-500
    Chicago, Illinois 60601
    5
    By: Marie Tipsord, Esq.
    6
    Hearing Officer
    7
    ILLINOIS POLLUTION CONTROL BOARD MEMBERS:
    8 G. Tanner Girard, Ph.D, Thomas E. Johnson, Esq.,
    9 AND
    10 Alisa Liu, P.E., Technical Staff Member
    11
    ILLINOIS ENVIRONMENTAL PROTECTION AGENCY
    12 1021 North Grand Avenue East
    Spingfield, Illinois 62794
    13
    By: M. Kyle Rominger, Esq.
    14
    15 Posegate & Denes, P.C.
    111 North Sixth Street, Suite 200
    16 Springfield, Illinois 62701
    By: Claire A. Manning, Esq.
    17
    On behalf of PIPE
    18
    19
    20
    21
    22
    23
    24
    Keefe Reporting Company
    (618) 244-0190

    3
    1
    2
    3
    E X H I B I T S
    4 NUMBER
    MARKED FOR IDENTIFICATION
    ADMITTED
    5
    6 Exhibit 77
    11
    15
    7 Exhibit 78 - 80
    12
    15
    8 Exhibit 81 - 86
    14
    15
    9 Exhibits 87, 88
    17
    17
    10 Exhibit 89
    39
    11 Exhibit 90
    117
    12 Exhibit 91
    118
    13 Exhibit 92
    179
    196
    14 Exhibit 93
    196
    196
    15
    16
    17
    18
    19
    20
    21
    22
    23
    24
    Keefe Reporting Company
    (618) 244-0190

    4
    1
    HEARING OFFICER TIPSORD: Good morning.
    2
    My name is Marie Tipsord, and I have been
    3
    appointed by the Board to serve as hearing
    4
    officer in these kind of proceedings, entitled
    5
    In the Matter of Proposed Amendments to
    6
    Regulations of Petroleum Leaking Underground
    7
    Storage Tanks, 35 Illinois Admin Code 732 and
    8
    734. The docket numbers are R04-22 and 23.
    9
    To my immediate right is Dr. Tanner
    10
    Girard, presiding board member in this matter,
    11
    and to his right is Board Member Thomas
    12
    Johnson. And from our technical staff, we have
    13
    Alisa Liu today. If we have to continue until
    14
    tomorrow, I believe Anand Rao will be joining
    15
    us tomorrow. And we also have Erin Conley here
    16
    today.
    17
    This is the fifth set of hearings to be
    18
    held in this proceeding. The purpose of
    19
    today's hearing is to allow for additional
    20
    testimony from the Illinois Environmental
    21
    Protection Agency and the Professionals of
    22
    Illinois for Protection of the Environment,
    23
    known as PIPE.
    24
    We will begin with the Agency's testimony
    Keefe Reporting Company
    (618) 244-0190

    5
    1
    and by Mr. Clay, and as usual, will be taken as
    2
    it is read; you can summarize it, and we will
    3
    mark it as an exhibit and go directly into
    4
    questioning. After that, after we finish with
    5
    the Agency -- excuse me -- we will ask PIPE to
    6
    present its testimony and be available for
    7
    questions.
    8
    Anyone may ask a question. However, I do
    9
    ask if you raise your hand, wait for me to
    10
    acknowledge you, and after I've acknowledged
    11
    you, please state your name and who you
    12
    represent before you begin your questions.
    13
    I must emphasize for the court reporter's
    14
    sake, you must identify yourself. Please do so
    15
    each time so that to be sure that she's getting
    16
    the right person.
    17
    I will only allow questions to be asked.
    18
    If you begin to testify, as usual, I will have
    19
    you sworn in. I'll politely ask you to state
    20
    your question and move on. We can allow for
    21
    testimony at the end of the day if there is
    22
    time. Please sign up in the back of the room
    23
    if you want to testify.
    24
    Speak one at a time. If you're speaking
    Keefe Reporting Company
    (618) 244-0190

    6
    1
    over each other, the court reporter will not be
    2
    able to get your questions on the record. Note
    3
    that any question asked by a board member or
    4
    staff are intended to help get a complete
    5
    record for the Board's decision, and not to
    6
    express any preconceived notion or bias.
    7
    At the back of the room there are signup
    8
    sheets for both the notice and service list. I
    9
    do want to caution everyone that we're
    10
    still -- we're switching how we are doing
    11
    notice and service lists. The hearing officers
    12
    are no longer in charge of those lists. Those
    13
    lists are being done through the clerk's office
    14
    and on COOL. There are some kinks that need to
    15
    be worked out. If you have signed up on
    16
    R04-22, it doesn't necessarily mean you
    17
    automatically show on R04-23. So when you get
    18
    ready to serve documents on people, please
    19
    compare lists, compare contrasts, and if you
    20
    encounter any difficulties in signing up or any
    21
    inconsistencies between the two lists, please
    22
    notify Sandy Wiley in our Chicago office. She
    23
    is the one who is in charge of keeping track of
    24
    all that stuff. We're trying to get those
    Keefe Reporting Company
    (618) 244-0190

    7
    1
    worked out, but please be patient and please
    2
    help us out. Thank you.
    3
    Before we begin with both PIPE and the
    4
    Agency, I want to note that on Thursday, August
    5
    5th, Mr. Bill Fleischli contacted me with some
    6
    concerns regarding the Agency's prefiled
    7
    testimony. So before we begin with either the
    8
    Agency or PIPE, we'll allow Mr. Fleischli a
    9
    couple minutes to speak briefly. Mr. Fleischli
    10
    has another meeting later today. So we're
    11
    going to start with him.
    12
    Before we do that, Dr. Girard?
    13
    BOARD MEMBER GIRARD: Good morning. On
    14
    behalf of the Board, I welcome everyone to the
    15
    fifth hearing on the proposal to amend the UST
    16
    rules. We look forward to the testimony and
    17
    questions today. And we hope to be closer to a
    18
    first notice draft here pretty soon. Thank
    19
    you.
    20
    HEARING OFFICER TIPSORD: Thank you.
    21
    Mr. Fleischli, we'll go ahead and have you
    22
    sworn in.
    23
    (Whereupon the witness was sworn.)
    24
    MR. FLEISCHLI: Thank you very much for
    Keefe Reporting Company
    (618) 244-0190

    8
    1
    letting me testify first. I am Bill Fleischli,
    2
    the executive vice-president of the Illinois
    3
    Petroleum Marketers Association. I represent
    4
    the Illinois Petroleum distributors who pay the
    5
    $75 million a year, the environmental fees to
    6
    fund the UST program.
    7
    As our members read the new proposal the
    8
    IEPA has submitted to the Board, our members
    9
    have some real concerns. The new proposal
    10
    would require the use of less stringent cleanup
    11
    objectives for my members' property, while
    12
    requiring that off-site impact be addressed
    13
    using the most stringent regulatory
    14
    requirements. The proposed rule change would
    15
    only allow for the reimbursement to the lower
    16
    standard on site, making the owner pay out of
    17
    pocket additional costs if they choose to
    18
    restore their property to the more stringent
    19
    standard.
    20
    Currently, the fund pays for reimbursement
    21
    costs to clean up the property to comply with
    22
    state statutes. The owner/operator, after
    23
    consulting with their engineers, chooses the
    24
    standard they want to clean -- they want to use
    Keefe Reporting Company
    (618) 244-0190

    9
    1
    to clean their property based on land use and
    2
    land value.
    3
    Now the IEPA wants to mandate they use the
    4
    less stringent standard. And once a No Further
    5
    Action letter is issued to the property, this
    6
    instance will no longer be eligible for the
    7
    fund.
    8
    Should IDOT or future law changes require
    9
    a phase study of the property and contamination
    10
    be found and the property mandated to be
    11
    cleaned up, the property will not be eligible
    12
    for reimbursement for that instance from the
    13
    LUST fund, even though the owner is still
    14
    paying into the LUST fund and the owner would
    15
    be liable and the incident will not be covered.
    16
    This is not fair, nor right, in our estimation.
    17
    The Illinois Petroleum Marketers
    18
    Association is not against the tiered approach
    19
    for cleanups. In fact, we led the industry in
    20
    the state with this approach about 10 years
    21
    ago.
    22
    What is wrong is not allowing the owner of
    23
    the property and the owner of the tanks the
    24
    opportunity to make the right decision for
    Keefe Reporting Company
    (618) 244-0190

    10
    1
    their particular piece of property, and in
    2
    shutting the owner out of the UST insurance
    3
    fund after a No Further Action letter is
    4
    issued, even though they still continue to pay
    5
    into the fund. The IPMA believes this was not
    6
    what the fund was originally set up to
    7
    accomplish. That is, cleaning up contaminated
    8
    property.
    9
    I believe these hearings should be left
    10
    open, and lender and real estate people should
    11
    be asked to testify to the effect this rule
    12
    will have on property values. If this supposed
    13
    shortage in the fund is the reasoning for this
    14
    proposal, then I ask the Agency to join the
    15
    industry to help pass legislation that would
    16
    prevent the Governor and General Assembly from
    17
    taking any more dollars from the fund, and help
    18
    the industry pass legislation that would direct
    19
    the Governor and the General Assembly to pay
    20
    the fund the $35 million they have taken from
    21
    the fund over the last three to five years.
    22
    Thank you, and I'll answer any questions
    23
    you may have at this time.
    24
    HEARING OFFICER TIPSORD: Thank you,
    Keefe Reporting Company
    (618) 244-0190

    11
    1
    Mr. Fleischli.
    2
    Is there any questions? Thank you very
    3
    much.
    4
    BOARD MEMBER GIRARD: Thank you.
    5
    HEARING OFFICER TIPSORD: Before we start
    6
    with the Agency's testimony, too, I do have a
    7
    couple of housekeeping things to take care of.
    8
    The Agency has provided us with a copy of the
    9
    annual report, the 2003 annual report, for the
    10
    leaking underground storage tank program.
    11
    MR. ROMINGER: There's several years in
    12
    there.
    13
    HEARING OFFICER TIPSORD: Oh, I'm sorry.
    14
    There are several years in there. 2003. 2003,
    15
    2001 and 2000, okay. If there's no objection,
    16
    I'm going to take these and mark each as an
    17
    exhibit. We'll start with 2000 and mark that
    18
    as Exhibit 77.
    19
    (Whereby, the Hearing Officer
    20
    marked Exhibit Number 77.)
    21
    HEARING OFFICER TIPSORD: 2001 will be
    22
    Exhibit 78. 2002 will be Exhibit 79. And 2003
    23
    will be Exhibit 80. Those are so marked.
    24
    Keefe Reporting Company
    (618) 244-0190

    12
    1
    (Whereby, the Hearing Officer marked
    2
    Exhibits 78 through 80.)
    3
    HEARING OFFICER TIPSORD: And also Carolyn
    4
    Hesse called me on behalf of CW3M. They're
    5
    going to submit some exhibits. Is there one
    6
    here representing CW3M with those exhibits?
    7
    MR. WEINHOFF: These exhibits are in
    8
    responses to questions by the Agency at the
    9
    June hearings.
    10
    HEARING OFFICER TIPSORD: You need to
    11
    identify yourself.
    12
    THE DEPONENT: Oh, Jeff Weinhoff, CW3M.
    13
    Sorry.
    14
    HEARING OFFICER TIPSORD: That's okay.
    15
    MR. WEINHOFF: I have copies on the back,
    16
    copies of the OSHA regulations that we referred
    17
    to, copies of fire marshal regulations, two
    18
    letters that we refer to that you asked copies
    19
    of, for, and a transcript hearing that we
    20
    referenced, and then calculations for our
    21
    numbers for the other states.
    22
    HEARING OFFICER TIPSORD: Do you have
    23
    another copy up here?
    24
    MR. FLEISCHLI: I've got extra copies.
    Keefe Reporting Company
    (618) 244-0190

    13
    1
    MR. ROMINGER: Does that have the
    2
    reference to the specific regulation regarding
    3
    the --
    4
    MR. FLEISCHLI: It's a copy of which ones?
    5
    MR. ROMINGER: Well, we were wanting a
    6
    specific reference to the specific requirement
    7
    of the number of people on site that you were
    8
    referring to in OSHA.
    9
    MR. FLEISCHLI: I did not put it together.
    10
    Harold put it together. And it's got -- I
    11
    can --
    12
    HEARING OFFICER TIPSORD: You do have a
    13
    copy of them to look at, right? Why don't you
    14
    go ahead and let them take a look. And I'll
    15
    let you take a look at those. And for now,
    16
    I'll go ahead and mark it. And ask if you have
    17
    any objection.
    18
    All right. We'll mark as Exhibit 81 -- I
    19
    think I am up to -- it's a document, the OSHA
    20
    regulations, will be marked as Exhibit 81.
    21
    The office of state fire marshal
    22
    record -- I'm sorry -- regulation will be
    23
    marked as Exhibit 82.
    24
    We have a letter dated February 9, 2004,
    Keefe Reporting Company
    (618) 244-0190

    14
    1
    from the Illinois Environmental Protection
    2
    Agency to Mathias Development Corp, which we
    3
    will mark as Exhibit 83.
    4
    The second letter from the Illinois
    5
    Environmental Profession Agency to LE Anderson
    6
    Brothers Company Oil Company, Inc., we'll mark
    7
    as Exhibit 84.
    8
    MS. MANNING: Excuse me, Ms. Hearing
    9
    Officer. This is Claire Manning with PIPE.
    10
    Are there public copies of those available?
    11
    HEARING OFFICER TIPSORD: He said he had
    12
    several.
    13
    MS. MANNING: Okay.
    14
    HEARING OFFICER TIPSORD: Exhibit 85 is a
    15
    transcript from PCB 97-226 River View FS versus
    16
    IEPA.
    17
    And Exhibit 86 is raw numbers from the
    18
    ETD of other states.
    19
    (Whereby, the Hearing Officer
    20
    marked Exhibits 81 - 86.)
    21
    HEARING OFFICER TIPSORD: Have you had a
    22
    chance to go over those?
    23
    MR. ROMINGER: Yes.
    24
    HEARING OFFICER TIPSORD: Is there any
    Keefe Reporting Company
    (618) 244-0190

    15
    1
    objection?
    2
    MR. ROMINGER: Well, the part 1926, they
    3
    referenced that before, and we asked them to
    4
    provide us a specific citation of that specific
    5
    provision they were talking about. And it
    6
    appears what they have done is sent a whole
    7
    copy of the entire part 1926. So we still
    8
    don't know which part of 1926 they're talking
    9
    about. And we'd just ask that they identify
    10
    that at some point.
    11
    HEARING OFFICER TIPSORD: In their
    12
    comments?
    13
    MR. WEINHOFF: And I guess I misunderstood
    14
    the question, but I'll review it, and we'll
    15
    submit it as a public comment, I guess.
    16
    MR. ROMINGER: Okay.
    17
    HEARING OFFICER TIPSORD: Any other
    18
    objection? Seeing none, we will admit those
    19
    exhibits.
    20
    (Whereby the exhibits were admitted into
    21
    evidence.)
    22
    HEARING OFFICER TIPSORD: I think we're
    23
    ready for you, Mr. Rominger.
    24
    MR. ROMINGER: Since the last hearing, the
    Keefe Reporting Company
    (618) 244-0190

    16
    1
    Agency went back, and we reviewed the
    2
    transcripts of all the previous hearings and
    3
    all of the testimony filed in this proceeding.
    4
    And we've gone through, and there were a lot of
    5
    good recommendations, suggestions and issues
    6
    that came forth as part of that process.
    7
    And Mr. King mentioned at the last
    8
    hearing, we were sort of missing a step in the
    9
    regulatory development that we usually have.
    10
    Once we put the numbers in these rules, they
    11
    were no longer circulated around for comment
    12
    from concern from both our side and people in
    13
    the regulative community.
    14
    So part of the reason these proceedings
    15
    have been so protracted is that that step was
    16
    not done. And that has been taking place
    17
    during these rule-making proceedings.
    18
    As we've done with our first and our
    19
    second errata sheet, we've continued to revise
    20
    our proposal when we saw the need of revision
    21
    or there could be improvements. And that's
    22
    what we've done in our third errata here.
    23
    There's quite a few issues that we thought we
    24
    could include and we've included.
    Keefe Reporting Company
    (618) 244-0190

    17
    1
    So I'll turn it over to Doug. He's going
    2
    to go through the testimony and summarize some
    3
    of the issues that we've covered, and we'll
    4
    have some testimony also.
    5
    HEARING OFFICER TIPSORD: Do you want to
    6
    mark the errata as a separate exhibit of his
    7
    testimony, or do you want to attach it to
    8
    Doug's testimony?
    9
    MR. ROMINGER: I don't think there's a
    10
    preference. It may be easier if we have two
    11
    exhibits.
    12
    HEARING OFFICER TIPSORD: Should we go
    13
    ahead and admit those then? Do you have a
    14
    clean copy for me?
    15
    MR. ROMINGER: Yes. Of the errata?
    16
    HEARING OFFICER TIPSORD: Of both. I must
    17
    admit, I just noticed when I was reading it.
    18
    If there's no objection, we will mark the
    19
    errata sheet as Exhibit 87 and Mr. Clay's
    20
    testimony as Exhibit 88. And there are copies
    21
    available in the back of the room. Seeing
    22
    none, those are so entered.
    23
    (Whereupon the Hearing Officer marked Exhibits
    24
    87 and 88, and same were admitted into
    Keefe Reporting Company
    (618) 244-0190

    18
    1
    evidence.)
    2
    HEARING OFFICER TIPSORD: And we'll have
    3
    you sworn.
    4
    (Whereupon the witness was sworn.)
    5
    MR. CLAY: Good morning. My name is Doug
    6
    Clay. Today I will be providing additional
    7
    testimony in support of the proposal.
    8
    The Agency would like to thank the Board
    9
    for the opportunity to submit these additional
    10
    changes. We would also like to thank all the
    11
    parties who provided comments and
    12
    recommendations during the proceeding.
    13
    Since the last hearing, the Agency has
    14
    reviewed the transcripts of all of the hearings
    15
    held in the rule making and all of the
    16
    testimony filed with the Board.
    17
    Our third errata contains the changes to
    18
    our proposal that we think are appropriate in
    19
    response to questions, comments and
    20
    recommendations that have risen in this rule
    21
    making. Although the Agency's third errata
    22
    sheet contains quite a few changes, we believe
    23
    these change will improve the LUST rules for
    24
    all parties involved in the LUST program.
    Keefe Reporting Company
    (618) 244-0190

    19
    1
    We also have reviewed PIPE's counter
    2
    proposal filed last week. We oppose it to the
    3
    extent it is inconsistent with our proposal.
    4
    Their counter proposal indicates there are
    5
    many -- there may be some confusion in our
    6
    proposal. Gary will be discussing the few
    7
    changes that could be made to clear up this
    8
    confusion.
    9
    First, I would like to cover several
    10
    issues that were raised in the hearing in June
    11
    and July. I will then highlight some of the
    12
    changes proposed in our third errata sheet.
    13
    Issues raised on June 21, June 22 and
    14
    July 6th hearings: There were several claims
    15
    made regarding the time it takes the Agency to
    16
    respond to submittals and requests to reduce
    17
    the time allowed the Agency to review
    18
    submittals. First, the Act provides the Agency
    19
    with 120 days to respond to submittals. Any
    20
    changes to that time frame requires a statutory
    21
    change to the Act.
    22
    Furthermore, reduction of this time frame
    23
    would impact the Agency's administration of the
    24
    LUST program. The greatest factor in the
    Keefe Reporting Company
    (618) 244-0190

    20
    1
    Agency's review time frames is the volume of
    2
    documentation it receives. On the average, the
    3
    Agency receives 30 linear feet of LUST plans
    4
    and reports each month or less -- or more than
    5
    7 feet each week. LUST documents currently
    6
    make up 50 percent of all the documents
    7
    received per month in the Bureau of Land's file
    8
    room. These figures do not include all the
    9
    reimbursement documentation received by the
    10
    LUST claims unit, such as applications for
    11
    payment. There must be an understanding of the
    12
    time and resources needed to review all
    13
    documents we receive. Shortening the Agency's
    14
    review deadline, even if done appropriately
    15
    through a statutory change, would hinder,
    16
    rather than help, the Agency's ability to
    17
    review more quickly.
    18
    Secondly, statements such as -- and quote,
    19
    "Project manager sends a letter at the end of
    20
    the 120 day review period and generally not a
    21
    day before," end quote, is inaccurate.
    22
    The Agency looked at the review times for
    23
    plans and reports from May 2003 to May 2004 and
    24
    review times are as follows: 26.3 percent of
    Keefe Reporting Company
    (618) 244-0190

    21
    1
    all reviews were done in less than 30 days.
    2
    26.1 percent of reviews were done between 30
    3
    and 60 days, 19.7 percent were done between 60
    4
    and 90 days, and 27.9 percent were done between
    5
    90 and 120 days.
    6
    Furthermore, there have been many
    7
    complaints that sometimes it takes up to two
    8
    years to obtain Agency approval. The amount of
    9
    time it takes to approve a plan or report is
    10
    largely dependent upon the quality of the
    11
    submittal. If the initial submittal meets the
    12
    applicable regulations and therefore could be
    13
    approved, the time frames for approval will be
    14
    no more than 120 days. As shown in our numbers
    15
    I just mentioned, in most cases is much less.
    16
    The claim was made in prefiled testimony
    17
    of PIPE: Member firms conduct or provide
    18
    services at nearly all the underground storage
    19
    tank cleanups conducted in the State of
    20
    Illinois.
    21
    Later at the hearing, PIPE presented
    22
    Exhibit 58, which showed 10 unidentified
    23
    consultants working on 893 active LUST sites.
    24
    PIPE will not identify its members and could
    Keefe Reporting Company
    (618) 244-0190

    22
    1
    not provide a breakdown of how many members
    2
    represented each of the different types of
    3
    businesses involved in the remediation of LUST
    4
    sites, but Cindy Davis did indicate that PIPE
    5
    had a total of 20 member firms that are either
    6
    consultants, laboratories, landfills or
    7
    contractors.
    8
    To put these numbers in perspective, the
    9
    Agency would like to offer the following:
    10
    There are over 23,000 LUST sites in the
    11
    LUST program. Over 10,000 of those sites still
    12
    have to be remediated. Of the unremediated
    13
    sites, over 2,300 have had some sort of
    14
    activity in the last two years, submitted a
    15
    plan or report to the Agency.
    16
    There are 375 different consultants that
    17
    have worked in LUST sites in the past five
    18
    years. There are 48 landfills in the state
    19
    permitted to accept LUST soils. There are 668
    20
    haulers permitted to transport LUST
    21
    contaminated soils. There are 89 laboratories
    22
    certified by the Agency to perform analyses
    23
    requiring the LUST program. There are 153 tank
    24
    removal contractors permitted by the Office of
    Keefe Reporting Company
    (618) 244-0190

    23
    1
    the State Fire Marshal. There are numerous
    2
    drillers, excavators, drillers and excavators
    3
    that work in the LUST program. In addition,
    4
    there are thousands of owners and operators who
    5
    are the parties responsible for complying with
    6
    these rules and the parties to be reimbursed
    7
    under the rules for their corrective action
    8
    costs.
    9
    The Agency appreciates PIPE's involvement
    10
    in the rule making. It provides -- it has
    11
    provided many good comments and
    12
    recommendations, which are included in the
    13
    third errata sheet. And we look forward to
    14
    working with PIPE members in the future on
    15
    issues related to the LUST program. However,
    16
    while PIPE has been a very vocal -- has been
    17
    very vocal in these proceedings, the Agency
    18
    would like to point out that it represents only
    19
    a small fraction of the persons involved in the
    20
    LUST program. The Agency has heard, either
    21
    directly or indirectly, that many consultants
    22
    are happy with rules as proposed, and
    23
    specifically have no problems with Subpart H.
    24
    There have been comments about the scope
    Keefe Reporting Company
    (618) 244-0190

    24
    1
    of work for professional consulting services
    2
    not being adequately defined in these rules.
    3
    The Agency does not believe that a detailed and
    4
    defined scope of work for each aspect of the
    5
    leaking underground storage tank cleanup is
    6
    necessary, nor does it -- should it be included
    7
    in these regulations. We agree that there are
    8
    some variabilities from site to site, but this
    9
    variability has been taken into account in the
    10
    Agency proposal. The scope of work is simply
    11
    the work required to perform the task being
    12
    reimbursed, such as preparing and submitting
    13
    the plan or report.
    14
    Several PIPE members commented on the
    15
    Agency's proposed soil conversion factor. We
    16
    believe that the conversion factors that have
    17
    been proposed are appropriate. And I would
    18
    like to emphasize that whatever conversion
    19
    factor the Board adopts, it should be
    20
    consistent throughout the rules.
    21
    At least one person representing -- or
    22
    presenting testimony raised the idea of
    23
    allowing owners and operators access to the
    24
    fund for costs incurred after the completion of
    Keefe Reporting Company
    (618) 244-0190

    25
    1
    remediation and the issuance of a No Further
    2
    Remediation letter. The purpose of allowing
    3
    such access would be to make owners and
    4
    operators more comfortable with the TACO
    5
    regulations. PIPE's counter proposal takes
    6
    this idea farther and asked the Board to allow
    7
    owners and operators back into the LUST program
    8
    and the UST fund for almost any reason.
    9
    The Agency opposes allowing owners and
    10
    operators back into the LUST program and the
    11
    UST fund after the issuance of an NFR letter,
    12
    except as already allowed for sites with MTBE.
    13
    There are over 10,000 releases from USTs
    14
    that still need to be remediated. The Agency
    15
    should be allowed to focus its time and
    16
    resources on sites that have yet to be
    17
    remediated, and not on sites that have already
    18
    received NFR letters that were requested and
    19
    agreed to by the owner/operator.
    20
    According to Exhibit 69 submitted by PIPE,
    21
    most owners and operators already utilized
    22
    alternatives available under TACO as part of
    23
    the remediation. There is apparently already a
    24
    good comfort level with TACO.
    Keefe Reporting Company
    (618) 244-0190

    26
    1
    Allowing owners and operators to come back
    2
    into the LUST program and accesses the LUST
    3
    fund would make it even harder to get a handle
    4
    on the fund's outstanding liability.
    5
    And, finally, the Board has already ruled
    6
    in the last LUST rulemaking, Docket R01-26,
    7
    proposed rule, second notice, that absent
    8
    special circumstances, such as MTBE
    9
    contamination, the UST fund should not be used
    10
    to pay remediation costs once the Agency has
    11
    issued an NFR letter. An NFR letter signifies
    12
    that no further corrective action is necessary,
    13
    thus making the use of the UST fund
    14
    unnecessary.
    15
    Issue has been taken with the Agency
    16
    reviewing plans, reports and applications for
    17
    payment that have been certified by a Licensed
    18
    Professional Engineer or Licensed Professional
    19
    Geologist. Some persons have asserted the
    20
    Agency should rely solely on the LPE and LPG
    21
    certification and should not question the LPE
    22
    or LPG's opinions or decisions. These
    23
    assertions assume the LPG and LPE
    24
    certifications have much more of a role in LUST
    Keefe Reporting Company
    (618) 244-0190

    27
    1
    programming than they are given by the Act and
    2
    the rules. Under the Act and the rules, it is
    3
    the party responsible for protecting human
    4
    health and the environment and properly
    5
    administering the UST fund. The Agency's
    6
    review of work conducted at LUST sites is
    7
    necessary to ensure these obligations are met.
    8
    Furthermore, preventing the Agency from
    9
    reviewing documentation certified by an LPE or
    10
    LPG would result in unchecked access to the
    11
    fund. The Act gives the Agency, not the LPE or
    12
    LPG the responsibility to determine whether
    13
    costs submitted for reimbursement are
    14
    reasonable. The Agency has discovered numerous
    15
    examples where an LPE or LPG has certified
    16
    either technical or reimbursement submittals
    17
    that were obviously not in accordance with the
    18
    Act and the regulation.
    19
    And I'd like to just go through a brief
    20
    sampling, a few examples for multiple
    21
    consultants, the plans and reportings that have
    22
    been certified as reasonable by professional
    23
    engineers or professional geologists within the
    24
    last year or so that the Agency believes are
    Keefe Reporting Company
    (618) 244-0190

    28
    1
    unreasonable. This is only a sampling and is
    2
    not included by any means in all instances.
    3
    One, a site investigation plan for minor
    4
    contamination at the site. Four soil borings
    5
    and monitoring wells were proposed to delineate
    6
    the extent of the contamination. A total of
    7
    257 hours were requested, a total budget of
    8
    over $30,000, and personnel costs of over
    9
    $19,000.
    10
    Second. Site investigation plan included
    11
    14 monitoring wells were proposed to delineate
    12
    the extent of the contamination, the submittal
    13
    of the site investigation completion report.
    14
    The total budget was $140,000. 94,000 of that
    15
    was personnel costs. This was actually a
    16
    resubmittal. The initial submittal was for 25
    17
    groundwater monitoring wells to delineate
    18
    extent of contamination. The original budget
    19
    was for $192,000, and it was over $104,000 in
    20
    personnel costs.
    21
    Third example site investigation plan
    22
    consisted of 13 groundwater monitoring wells
    23
    were proposed to delineate the extent of
    24
    contamination. Total budget, $101,000. 63,000
    Keefe Reporting Company
    (618) 244-0190

    29
    1
    in personnel costs.
    2
    Fourth. Site investigation plan included
    3
    12 soil borings, five groundwater monitoring
    4
    wells, preparation of a dig and haul CAP and
    5
    corrective action plan and corrective action
    6
    completion report. A total of $316,000 with
    7
    $68,000 in personnel costs, which included over
    8
    $800 -- 800 hours for project manager,
    9
    environmental protection II, a professional II
    10
    and environmental professional I.
    11
    Preparation of a corrective action plan,
    12
    installation of five borings and five
    13
    monitoring wells for a total of $126,000, a
    14
    hundred thousand dollars in personnel costs.
    15
    A proposal for corrective action plan
    16
    consisting of injection of an oxygen generating
    17
    compound into the subsurface to remediate soil
    18
    and groundwater contamination in place. A
    19
    consultant certified $32 a foot was reasonable
    20
    to inject the chemical. The Agency denied and
    21
    requested justification for the rate. Then the
    22
    plan amendment was submitted and certified that
    23
    included a rate of $16 per foot for the same
    24
    work, which the Agency then approved. This
    Keefe Reporting Company
    (618) 244-0190

    30
    1
    resulted in a cost savings or cost differential
    2
    of $115,000.
    3
    Corrective action plan consisting of a dig
    4
    and haul, collection of samples, collection of
    5
    samples and replacement of five groundwater
    6
    monitoring wells and the performance of the
    7
    biofeasibility study. Total budget, $552,000,
    8
    $142,000 in personnel.
    9
    Corrective action plan, amendment,
    10
    consisting of the preparation of a plan and
    11
    budget for performance of the biofeasibility
    12
    study, which included 28 borings and 30
    13
    injections. Again, this was a pilot study.
    14
    $443,000, and $92,000 in personnel costs.
    15
    A corrective action plan, amendment, to
    16
    excavate 100 cubic yards of soil, collecting
    17
    confirmatory soil samples and install two
    18
    groundwater monitoring wells and prepare a
    19
    highway authority agreement, and record the NFR
    20
    letter. Total of $58,000, $49,000 in personnel
    21
    costs with 436 hours to perform these
    22
    activities.
    23
    In addition, over the years we have seen
    24
    numerous instances of double billing. That is,
    Keefe Reporting Company
    (618) 244-0190

    31
    1
    duplicate submittals of costs that have already
    2
    been paid.
    3
    We've also seen numerous instances of
    4
    requests for payment for ineligible activities,
    5
    such as activities performed prior to the
    6
    existence of the LUST program, activities
    7
    performed prior to the release being reported,
    8
    landscaping activities, removal of animals from
    9
    remediation sheds. And we've even received one
    10
    where a consultant asked to be reimbursed for
    11
    staying at his parents' home.
    12
    Numerous instances where environmental
    13
    professionals have certified that the
    14
    requirements of the rules and Act were
    15
    satisfied and requested a No Further
    16
    Remediation letter. However, the report
    17
    clearly shows these requirements have not been
    18
    met.
    19
    Again, these are just a few examples and
    20
    are not isolated cases, to support the need for
    21
    the Agency to review plans and reports and not
    22
    rely solely on the professional engineer or
    23
    professional geologist's certificates for both
    24
    the technical adequacy and the reasonableness
    Keefe Reporting Company
    (618) 244-0190

    32
    1
    of costs for corrective action as part of the
    2
    leaking underground storage tank program.
    3
    Members of PIPE have raised the idea of
    4
    creating a new database specifically for the
    5
    purposes of determining rates to adopt in the
    6
    rules. The Agency strongly opposes this idea.
    7
    A mandated burdensome and time-consuming data
    8
    collection effort sends the LUST program in the
    9
    wrong direction. First, it would greatly
    10
    complicate and lengthen the preparation of
    11
    budgets by consultants, thus increasing costs.
    12
    It would also complicate and lengthen the time
    13
    needed to review the budgets by the Agency.
    14
    BOARD MEMBER JOHNSON: Hey, Doug, I keep
    15
    looking through here. Those examples you just
    16
    gave, they're not in your prefiled testimony?
    17
    That was in addition to it?
    18
    MR. CLAY: That's correct.
    19
    BOARD MEMBER JOHNSON: Okay, thanks.
    20
    MR. CLAY: That's correct.
    21
    The UST fund and the Agency resources are
    22
    already taxed, and this proposal would only
    23
    worsen the situation.
    24
    Second, the data submitted would be skewed
    Keefe Reporting Company
    (618) 244-0190

    33
    1
    from the beginning. There is nothing to ensure
    2
    the data submitted would reflect reasonable
    3
    costs.
    4
    And, finally, there is no need for such
    5
    data collection effort because the Agency has
    6
    added bidding provisions to its proposal as a
    7
    means of demonstrating on a site-specific basis
    8
    the costs higher than Subpart H are reasonable.
    9
    Bidding will more accurately reflect the daily
    10
    market prices and will be more responsive to
    11
    market changes.
    12
    Members of PIPE have raised the idea of
    13
    the Agency to provide owners and operates with
    14
    draft denial or modification letters prior to
    15
    decisions denying or modifying the plan of
    16
    report. Members of PIPE have likened this idea
    17
    to Agency review of permits.
    18
    The Agency is opposed to requiring a draft
    19
    denial or modification letter prior to the
    20
    Agency issuing a final decision. Such a
    21
    process would extend review times and is
    22
    counter productive to streamlining the LUST
    23
    program. Unlike permit reviews, the clock on
    24
    the Agency's 120-day review deadline would not
    Keefe Reporting Company
    (618) 244-0190

    34
    1
    stop if the Agency were to issue a draft
    2
    letter.
    3
    Further, the analogy to permit reviews is
    4
    not appropriate. According to the permit
    5
    section; of the permits they issue, only the
    6
    RCRA part B permits, which are construction
    7
    operator permits for hazardous waste treatment,
    8
    storage or disposal facilities, require draft
    9
    permits prior to the final decision.
    10
    It is -- in its counter proposal, PIPE
    11
    requested the Agency be given 45 days to review
    12
    submittals. They also request that the
    13
    submittals be automatically approved if the
    14
    Agency does not respond within 45 days. Both
    15
    the shortened review time and the automatic
    16
    approval are contrary to the Act. As I have
    17
    stated, the Act specifically provides the
    18
    Agency with 120 days to respond to submittals.
    19
    Requiring the response PIPE wants within 45
    20
    days would shorten the statutory review period.
    21
    The Act also specifically provides that
    22
    submittals are denied by operation of law if
    23
    the Agency does not respond within 120 days.
    24
    Title 16 originally provided for approval by
    Keefe Reporting Company
    (618) 244-0190

    35
    1
    operation of law if the Agency did not respond.
    2
    However in 1995, USEPA pulled its authorization
    3
    from the LUST program because in, part, the
    4
    automatic approval was inconsistent with the
    5
    federal program. In response, the legislature
    6
    amended the Act to provide denial by operation
    7
    of law. Allowing approval by operation of law
    8
    would once again threaten the USEPA's
    9
    authorization of the LUST program.
    10
    The idea of a peer review committee has
    11
    been raised by members of PIPE. The Agency is
    12
    opposed to creation of such a committee. The
    13
    Agency gives the Act -- the Act gives the
    14
    Agency the authority and responsibility to
    15
    oversee the LUST program and determine the
    16
    reasonableness of costs reimbursed from the UST
    17
    fund. The Act does not authorize persons
    18
    outside the Agency to review submittals, and
    19
    the decision of such a committee would not be
    20
    appealable to the Board. Only the Agency's
    21
    decision can be appealed to the Board.
    22
    Otherwise -- or outside influences or input on
    23
    Agency's final decision is simply
    24
    inappropriate. Furthermore, routing submittals
    Keefe Reporting Company
    (618) 244-0190

    36
    1
    through such a committee prior to the Agency
    2
    issues a final decision will lengthen and
    3
    review -- lengthen the review process and is
    4
    counter to streamlining the LUST program.
    5
    To help foster and enable greater
    6
    communication between the Agency and other
    7
    parties involved in the LUST program, the
    8
    Agency is proposing a new provision that would
    9
    establish a LUST advisory committee. The
    10
    committee would be made up of representatives
    11
    of interested parties and will meet with the
    12
    Agency on a quarterly basis to discuss the LUST
    13
    program. This committee is modeled after the
    14
    Site Remediation Advisory Committee that was
    15
    established for the Agency's site remediation
    16
    program.
    17
    Another idea raised by PIPE members is to
    18
    allow another method besides Board appeal to
    19
    challenge Agency decisions. The persons
    20
    allowed to oversee the alternative proceedings
    21
    would be selected by committee -- by a
    22
    committee, and the costs of the proceedings
    23
    would be paid out of the UST fund. The Agency
    24
    opposes this idea and is not authorized by and
    Keefe Reporting Company
    (618) 244-0190

    37
    1
    is not consistent with the Act.
    2
    A few issues have been raised regarding
    3
    the applications for payment. One is that the
    4
    requirement that applications for payment
    5
    include proof of payment to subcontractors.
    6
    There has been requests to strike this
    7
    requirement because of hardship of obtaining
    8
    canceled checks. Canceled checks are not the
    9
    only proof of payment that may be submitted.
    10
    Applications for payment may also contain lien
    11
    waivers or affidavits from subcontractors. One
    12
    of these methods of proof of payment should be
    13
    reasonably obtained.
    14
    Proof of payment of subcontractors' costs
    15
    is necessary to show the consultant is entitled
    16
    to handling charges. Handling charges, by
    17
    definition, means administrative insurance and
    18
    interest costs as -- and the reasonable profit
    19
    for procurement, oversight and payment of
    20
    subcontractors and field purchases. If the
    21
    consultant paid the subcontractor's bill, he or
    22
    she is entitled to handling charges. However,
    23
    many consultants have the owner/operator pay
    24
    the subcontractors directly, and therefore are
    Keefe Reporting Company
    (618) 244-0190

    38
    1
    not entitled to handling charges. The Agency
    2
    needs the proof of payment to show the
    3
    contractor paid the subcontractor and is
    4
    therefore entitled to handling charges.
    5
    Testimony was provided by CW3M that the
    6
    average rate for excavation, transportation and
    7
    disposal of contaminated soils awarded by IDOT,
    8
    awarded for IDOT projects was $99.75 cubic
    9
    yard. This comparison is inappropriate.
    10
    Following discussions with IDOT regarding the
    11
    bidding process, the Agency received a letter
    12
    from IDOT dated August 2, 2004 that explains
    13
    the process.
    14
    At the conclusion of the IDOT -- of this,
    15
    IDOT states, and I quote, "Based on the
    16
    information provided during the rule making,
    17
    IDOT's costs should not be used to compare or
    18
    justify costs proposed by the IEPA in this rule
    19
    making," end quote.
    20
    Steve Gobleman of IDOT, who has been
    21
    attending these hearings, has offered to answer
    22
    any questions regarding this letter and IDOT's
    23
    process. And he is here today.
    24
    MR. ROMINGER: We've got a copy to
    Keefe Reporting Company
    (618) 244-0190

    39
    1
    provide for the record.
    2
    HEARING OFFICER TIPSORD: Yeah, let's go
    3
    ahead and mark that as an exhibit. We'll mark
    4
    the Illinois Department of Transportation
    5
    August 22, 2004 letter to Mr. Clay as Exhibit
    6
    89. If there's no objection, seeing none, it's
    7
    marked as Exhibit 89.
    8
    (Whereby, the Hearing Officer
    9
    marked Exhibit Number 89.)
    10
    MR. CLAY: Now I'd like to go through the
    11
    actual changes that we are proposing in the
    12
    Agency's third errata sheet.
    13
    The first change on the July 6, 2004
    14
    hearing, PIPE requested clarification on how
    15
    proposed Part 734 would be applied to releases
    16
    subject to Public Act 92-0554, but reported
    17
    prior to the effective date of Part 734. In
    18
    response, the Agency proposes to
    19
    change -- proposes a change that recognizes the
    20
    work already performed at a site, even though
    21
    the work may not exactly match the requirements
    22
    of 734.
    23
    In addition, the Section is changed to
    24
    provide the costs approved in a budget prior to
    Keefe Reporting Company
    (618) 244-0190

    40
    1
    the effective date of Part 734 will be
    2
    reimbursed according to the amounts approved in
    3
    the budget.
    4
    The second change. In response to
    5
    comments, the Agency proposes to amend the
    6
    definition of half day, one half day equals
    7
    four hours. The Agency further proposes to
    8
    remove the two half days per calendar day
    9
    limitation so that more -- that two half days
    10
    can be reimbursed in a single calendar day.
    11
    Third change. Members of PIPE have
    12
    pointed out correctly that much of the Agency's
    13
    review of work performed at the site is based
    14
    solely on the report it receives and not on
    15
    direct observation of activities. However, the
    16
    Agency does not receive advanced notice of when
    17
    field activities are being -- will be taking
    18
    place. The Agency agrees that direct oversight
    19
    of field activities is very valuable in certain
    20
    circumstances. To help the Agency identify
    21
    sites for field activities should be directly
    22
    observed. And to help and plan for such
    23
    oversight, the Agency proposes to add wording
    24
    that would allow the Agency to require
    Keefe Reporting Company
    (618) 244-0190

    41
    1
    notification of field activities.
    2
    Fourth change. To help foster and enable
    3
    greater communication between the Agency and
    4
    other parties involved in the LUST program.
    5
    The Agency proposes new sections that establish
    6
    a LUST advisory committee. The committee would
    7
    be made up of representatives of interested
    8
    parties and will meet with the Agency on a
    9
    quarterly basis to discuss the LUST program.
    10
    The committee is modeled after the Site
    11
    Remediation Advisory Committee that was
    12
    established through the Agency's Site
    13
    Remediation Program.
    14
    Fifth change. Members of PIPE have
    15
    expressed concern over the proposed language of
    16
    the LPE and LPG certification. In response,
    17
    the Agency proposes to amend certification so
    18
    that a professional who is certifying only to
    19
    the standards and practices of his or her
    20
    profession.
    21
    Sixth change. Members of PIPE requested
    22
    that allowances be made for situations where
    23
    early action soil samples cannot be collected
    24
    in the location specified in the rules. In
    Keefe Reporting Company
    (618) 244-0190

    42
    1
    response, the Agency proposes to allow
    2
    alternate locations for samples and
    3
    circumstances required.
    4
    Seventh change. To address problems where
    5
    removal of free product that exceeds one-eighth
    6
    of an inch depth is impractical, the Agency
    7
    proposes to add language to the extent -- to
    8
    the maximum extent practicable back into
    9
    732.203(a) and 734.215(a). PIPE asked that
    10
    free product removal will be required only when
    11
    necessary to address health and safety issues.
    12
    Relaxing free product removal to such a
    13
    standard would make the Board's rules
    14
    inconsistent with federal rules and therefore
    15
    jeopardize USEPA authorization of the LUST
    16
    program.
    17
    PIPE also asks the Board to delete its
    18
    board notes from this section and throughout
    19
    these rules. The Agency believes that these
    20
    notes are helpful to owners and operators to
    21
    further clarify the Board's rules, and
    22
    disagrees with PIPE's proposal.
    23
    The eighth change. There was several
    24
    comments from members of PIPE and the American
    Keefe Reporting Company
    (618) 244-0190

    43
    1
    Council of Engineering Companies, ACEC,
    2
    regarding the prescriptive nature of stage one
    3
    site investigations. In response to their
    4
    comments and recommendations, the Agency
    5
    proposes to amend Section 734.315(a) so that it
    6
    contains simplified samples requirements. The
    7
    amended stage one investigation is based on
    8
    ACEC's stage one site investigation submitted
    9
    in Dan Goodwin's testimony, which is Exhibit
    10
    74.
    11
    Ninth change. Members of PIPE have
    12
    expressed concerns over knowing how many
    13
    alternative technologies must be compared in a
    14
    budget when alternative technology is proposed.
    15
    The Agency believes that comparison of two
    16
    other alternative technologies is sufficient.
    17
    Therefore it proposes to require such a
    18
    comparison.
    19
    The tenth change. Members of PIPE
    20
    objected to requiring the submission of
    21
    laboratory certifications in applications for
    22
    payment. In response, the Illinois EPA
    23
    proposes to delete this requirement.
    24
    The eleventh change. In order to help
    Keefe Reporting Company
    (618) 244-0190

    44
    1
    ensure UST fund money as used in a most
    2
    cost-effective manner, the Agency proposes
    3
    changes that will require owners and operators
    4
    to seek reimbursement to utilize certain
    5
    aspects of TACO.
    6
    First, the Agency proposes to limit
    7
    payment from the fund to costs that achieve
    8
    cleanup to Tier 2 objectives. TACO is designed
    9
    so that cleanup to the Tier 2 objective is
    10
    equally protected as cleanup to the Tier 1
    11
    objective, which is generally more expensive.
    12
    The second change is to the use of TACO,
    13
    is to require the use of a groundwater
    14
    ordinance as an institutional control if the
    15
    ordinance has already been approved by the
    16
    Agency and is available.
    17
    The twelfth change. CW3M raised concerns
    18
    about the consequences of a proposed provision
    19
    that could make consultant fees ineligible when
    20
    re-sampling is due to laboratory error. In
    21
    response to these concerns, the Agency proposes
    22
    to delete that provision.
    23
    Thirteenth change. CW3M raised concerns
    24
    about certain routine maintenance costs being
    Keefe Reporting Company
    (618) 244-0190

    45
    1
    made ineligible by a proposed provision. In
    2
    response, the Agency changed those provisions
    3
    to make routine maintenance costs eligible for
    4
    reimbursement if they are approved in a budget.
    5
    Fourteenth change. Members of PIPE have
    6
    raised concerns over the addition of record
    7
    retention provisions. These concerns appear to
    8
    be centered around the audit language repeated
    9
    from the Act. The proposed section is intended
    10
    to be used for review of documents related to
    11
    the payments from the UST fund, such as time
    12
    sheets, subcontractors' invoices, chain of
    13
    custody documents, backup documentation for
    14
    costs submitted for payment. The Agency merely
    15
    needs to ensure that the records related to
    16
    reimbursement submittals are retained for
    17
    certain periods of time so they can be
    18
    reviewed, if necessary. With the new
    19
    streamlining process, many of these documents
    20
    will no longer be submitted to the Agency. Due
    21
    to the concerns raised by members of PIPE, the
    22
    Agency proposes to delete the statutory
    23
    auditing language and retain only the
    24
    provisions that are based on record retention
    Keefe Reporting Company
    (618) 244-0190

    46
    1
    provisions in other Board and Agency
    2
    regulations. Copies of those provisions were
    3
    submitted to the Board in Exhibit 16.
    4
    Payment of corrective action costs from
    5
    the UST fund is the distribution of public
    6
    money, and the Agency must be able to properly
    7
    account for such public money. The proposed
    8
    record retention provisions will bring the LUST
    9
    program in line with other Board and Agency
    10
    regulations that deal with the distribution of
    11
    public money and will aid in the proper
    12
    accounting of public money in the UST fund.
    13
    Because hundreds of millions of dollars in
    14
    public monies are distributed through the UST
    15
    fund, far exceeding amounts governed by many
    16
    other Board and Agency regulations, there is an
    17
    even greater need for record retention
    18
    provisions in the LUST rules.
    19
    Sixteenth change. Several concerns were
    20
    raised over reimbursement amounts for personnel
    21
    costs. In response, the Agency proposes the
    22
    following changes to its proposal:
    23
    A. Allowing one half day of field work
    24
    and -- excuse me. Allowing one half day of
    Keefe Reporting Company
    (618) 244-0190

    47
    1
    field work and field oversight for each leaking
    2
    underground storage tank that is removed, up to
    3
    10 half days.
    4
    B. Concerns were raised about the costs
    5
    of site investigation at high priority sites
    6
    under 732. In response, the Agency proposes to
    7
    add the same language and costs as provides for
    8
    site investigation under 734.
    9
    C. Concerns were raised over the costs
    10
    for additional well survey work required under
    11
    the new rules. In response, the Agency
    12
    proposes to add separate maximum payment amount
    13
    for this work.
    14
    D. Concerns were raised over
    15
    reimbursement of travel time. Members of PIPE
    16
    recommended the travel time be broken out and
    17
    reimbursed separately from the half day rate
    18
    due to its variability from site to site. In
    19
    response, the Agency proposes to remove travel
    20
    time from the half day rate and reimburse it
    21
    according to a sliding scale based upon the
    22
    distance from the consultant's office to the
    23
    site.
    24
    E. Concerns were raised about the costs
    Keefe Reporting Company
    (618) 244-0190

    48
    1
    associated with plan revisions that are needed
    2
    as a result of unforeseen circumstances that
    3
    arise after a plan and budget have been
    4
    approved. In response, the Agency proposes to
    5
    allow $640 for a plan and budget amendments
    6
    required because of unforeseen circumstances.
    7
    This amount is based on eight hours' personnel
    8
    time.
    9
    Seventeenth change. Concerns have been
    10
    raised about setting maximum reimbursement
    11
    amounts in the rules. In addition, the idea of
    12
    bidding, which is used in several other states,
    13
    has been raised as a possible method of
    14
    determining reasonable amounts for
    15
    reimbursement. In response, the Agency
    16
    proposes to add provisions that would allow
    17
    maximum amounts set forth in these rules to be
    18
    exceeded if a minimum of three bids are
    19
    obtained. If such -- in such cases, the amount
    20
    of the lowest bid would be an amount allowing
    21
    for reimbursement purposes, unless it is lower
    22
    than the maximum payment amount set forth in
    23
    these rules. The bidding provisions do not
    24
    specify who is to do the bidding. The Agency
    Keefe Reporting Company
    (618) 244-0190

    49
    1
    anticipates that in most cases the bidding will
    2
    be done by the primary consultant.
    3
    The Agency believes that the bidding
    4
    process will generally improve the process of
    5
    proposed rules. First, it allows an exceedance
    6
    over the maximum rates if the lowest of the
    7
    bids exceed those rates. Bidding will allow
    8
    the rules to be responsive to site-specific
    9
    conditions and cause -- that cause an increase
    10
    in costs, such as greater hauling distances to
    11
    landfills and higher field cost.
    12
    Second, costs based on bids will
    13
    accurately reflect market price, making the
    14
    rules immediately responsive to price
    15
    fluctuation.
    16
    Third, there is less of a need for Agency
    17
    approval of unusual and extraordinary expenses
    18
    or the need to determine at what point the
    19
    costs substantially exceed the maximum payment
    20
    amounts. Instead, the costs can be bid out,
    21
    and the lowest bid will be considered
    22
    reasonable.
    23
    Fourth, there is no need to gather new
    24
    information to establish a new database
    Keefe Reporting Company
    (618) 244-0190

    50
    1
    specifically for the purposes of determining
    2
    maximum reimbursement amounts, which could be
    3
    extremely burdensome to both consultants and
    4
    the Agency and result in great delays in
    5
    adopting these rules.
    6
    Finally, bidding will help the Agency
    7
    track market rates and adjust maximum payment
    8
    amounts in the rule when necessary. If we see
    9
    certain costs are continually bid out and
    10
    coming in higher than the maximum payment
    11
    amount allowed in the rules, we will know it's
    12
    time to review the rules and adjust those
    13
    amounts through a rule making. The proposed
    14
    bidding provisions do prohibit the bids from
    15
    certain parties. This is to ensure that
    16
    third -- that true third party bids are
    17
    obtained. However, the bidding provisions also
    18
    provide lowest bidder does not have to be used,
    19
    only the amount of the lowest bid. Another
    20
    person may be hired to perform the work, and
    21
    the rules specifically provide that parties
    22
    prohibited from bidding may perform that work.
    23
    The bidding provisions allow -- the bid
    24
    provisions also require that all bids received
    Keefe Reporting Company
    (618) 244-0190

    51
    1
    must be submitted to the Agency. This is to
    2
    avoid situations, for example, where five bids
    3
    are obtained, and the three bids are submitted
    4
    to the Agency are the three highest. If more
    5
    than the minimum three bids are obtained, the
    6
    amount allowed for reimbursement is intended to
    7
    be the lowest of all bids, not just three.
    8
    Finally, the rules anticipate consultants
    9
    to obtain bids from persons who are properly
    10
    qualified to do the work. They are not
    11
    expected to obtain bids from unqualified
    12
    persons just because they are cheaper.
    13
    Eighteenth change. Even with the addition
    14
    of bidding, the Agency believes there will
    15
    still be situations where the reasonableness of
    16
    costs will need to be determined on a
    17
    site-specific basis due to extenuating
    18
    circumstances. For example, there may be
    19
    situations where three bids cannot be obtained
    20
    because there are only -- there are not three
    21
    persons who provide this service or perform the
    22
    work that is needed. Therefore, the Agency
    23
    proposes to change the unusual and
    24
    extraordinary expenses section to unusual or
    Keefe Reporting Company
    (618) 244-0190

    52
    1
    extraordinary circumstances section. If
    2
    expense is the only issue, that can be handled
    3
    under the bidding provisions.
    4
    In Exhibit 7 of Dan Goodwin's testimony
    5
    from ACEC, he provides a list of several
    6
    situations that it proposes to list in the
    7
    rules as atypical situations. The Agency has
    8
    reviewed this list and believes that all of the
    9
    situations identified by ACEC are either
    10
    already reimbursed on a time and material
    11
    basis, can be addressed through the bidding
    12
    process, or have been addressed in the proposed
    13
    rules, including this errata. The Agency does
    14
    not see a need to designate certain situations
    15
    as atypical in the rules.
    16
    Nineteenth change. In its original
    17
    proposal, the Agency proposed a
    18
    review -- proposed a rule to review the rules
    19
    at least every two years to ensure the maximum
    20
    payment amounts remain current with the
    21
    prevailing market prices. In its first errata,
    22
    the Agency proposed a change to this
    23
    requirement to an automatic increase in the
    24
    maximum payment amount each year. The Agency
    Keefe Reporting Company
    (618) 244-0190

    53
    1
    now proposes to add back in a mandatory review
    2
    of rates to ensure that they are keeping pace
    3
    with the prevailing market rates. The only
    4
    difference between the language as originally
    5
    proposed is that review must now be conducted
    6
    every three years instead of every two years.
    7
    The Agency believes that a three-year minimum
    8
    is sufficient because the maximum amount will
    9
    automatically be increased each year, and the
    10
    Agency will be able to track market
    11
    fluctuations through the bidding process.
    12
    Change 20. Jarrett Thomas, who submitted
    13
    testimony on behalf of PIPE and the Illinois
    14
    Association of Environmental Laboratories,
    15
    recommended that references to specific methods
    16
    for BTEX and PNA analyses be deleted from
    17
    Section 732, appendix D, and 734 appendix D.
    18
    In response, the Agency proposes to delete
    19
    those references.
    20
    Twenty-first change. Based on discussions
    21
    with interested parties, the Agency proposes
    22
    to increase the hourly rates for Engineer I,
    23
    Engineer II, Geologist I, Geologist II,
    24
    Geologist III and Professional Geologist. The
    Keefe Reporting Company
    (618) 244-0190

    54
    1
    Agency believes that the amended rates are
    2
    reasonable amounts for purposes of
    3
    reimbursement for reimbursing costs from the
    4
    UST fund.
    5
    And, finally, the twenty-second change.
    6
    The Agency has proposed changes to the water
    7
    well survey requirements. So that water well
    8
    is -- so that water well survey is required
    9
    only when contamination exceeds the groundwater
    10
    and exposure route for remediation objectives.
    11
    Focussing on the remediation objectives -- on
    12
    these remediation objectives will protect
    13
    potable water supply wells while reducing the
    14
    number of sites where well surveys are
    15
    required. The reduction in number of well
    16
    surveys conducted will further reduce
    17
    corrective action costs.
    18
    That concludes my testimony.
    19
    HEARING OFFICER TIPSORD: Thank you.
    20
    Excuse me. I had my head down. You weren't
    21
    sworn in, right?
    22
    MR. KING: I was.
    23
    HEARING OFFICER TIPSORD: I thought you
    24
    were.
    Keefe Reporting Company
    (618) 244-0190

    55
    1
    MR. KING: I just wanted to take a few
    2
    minutes and amplify a couple things that both
    3
    Kyle and Doug commented on.
    4
    As you can see from the nature of our
    5
    third errata sheet, we took very seriously the
    6
    commitment that we made at the last hearing,
    7
    that we were going to go back and look at
    8
    everything and figure out what we thought were
    9
    appropriate changes to make, and we have done
    10
    that. And we think that the hearing process
    11
    has allowed us to make a number of significant
    12
    improvements to our proposal. And we think
    13
    that the Board will see those improvements as
    14
    well. Because we did not get PIPE's proposal
    15
    until after we filed the third errata sheet,
    16
    our proposal is not reflective of anything in
    17
    the proposal.
    18
    Nonetheless, during the last week, we went
    19
    and reviewed that proposal. At least we
    20
    reviewed what we had, because we only had half
    21
    the proposal, since some of the numbers
    22
    are -- a lot of numbers -- and I suppose we can
    23
    see those today. I don't know if those have
    24
    been handed out yet or not.
    Keefe Reporting Company
    (618) 244-0190

    56
    1
    Okay. Based on what -- on our review of
    2
    the proposal, we did not see any additional
    3
    modification that needed to be made, except for
    4
    one small area. It's apparent to us, based on
    5
    PIPE's proposal, that they are still confused
    6
    about what the Agency has proposed in Subpart
    7
    H. And as a result of that, we plan on
    8
    submitting, with our final comments, revisions
    9
    to the introductory provision of Subpart H that
    10
    will form kind of a road map description of how
    11
    Subpart H is intended to function. And I think
    12
    that change should help clarify things for
    13
    PIPE.
    14
    At this point, that's the only change we
    15
    think that's merited, based on our reading of
    16
    the PIPE proposal.
    17
    I was noticing one of the serious concerns
    18
    that we have with the PIPE proposal is that
    19
    there are many suggestions we think are
    20
    inconsistent with the terms of Title 16, and
    21
    some are inconsistent with federal law as well.
    22
    I don't think the Board has authority to adapt
    23
    rules in this proceeding that are inconsistent.
    24
    HEARING OFFICER TIPSORD: I'm sorry,
    Keefe Reporting Company
    (618) 244-0190

    57
    1
    Mr. King. I apologize, but I lost your voice
    2
    completely.
    3
    MR. KING: I don't think the Board has
    4
    authority to adapt rules that are inconsistent
    5
    with Title 16. And I certainly don't think
    6
    it's advisable to adapt rules that are
    7
    inconsistent with federal law.
    8
    Doug has identified a number of those in
    9
    his testimony, and I wanted to go through one
    10
    additional one that Doug and I talked about.
    11
    It wasn't really something that Doug felt he
    12
    could go through because it concerned the
    13
    relationship between the site remediation
    14
    program and the LUST program.
    15
    In PIPE's proposal, they proposed that a
    16
    definition which would be added to an UST
    17
    remediation applicant, such that the UST RA
    18
    would have the same status as an owner or
    19
    operator of the UST system. They drew that
    20
    definition from Title 17 and site of
    21
    remediation program, but I don't think in
    22
    proposing that, they understand how that term
    23
    is used in that program or the implication of
    24
    its use relative to the federal rules and
    Keefe Reporting Company
    (618) 244-0190

    58
    1
    regulations that govern the tank program.
    2
    As required by federal law and
    3
    regulations, Title 16 in the Board's LUST
    4
    regulations have always specified that the
    5
    legal responsibilities for operating
    6
    underground storage tank systems and responding
    7
    to releases from those systems belong to the
    8
    owners and operators of those systems.
    9
    Throughout numerous regulatory proceedings, the
    10
    Board has been very careful to keep its rules
    11
    in line with that principle to avoid conflict
    12
    with federal provisions. PIPE's proposal
    13
    represents the first time that I've seen anyone
    14
    suggest that a consultant should step into the
    15
    shoes of owners and operators with respect to
    16
    these legal responsibilities.
    17
    In the mid 1990s when we set about writing
    18
    Title 17 in terms of the statutory provisions,
    19
    we knew we were not bound by the same legal
    20
    constraints as was existing in the LUST
    21
    program. We knew that we needed to come up
    22
    with a broader term, because of the broader
    23
    scope of liability, that it tends to cites
    24
    under the liability provisions of state and
    Keefe Reporting Company
    (618) 244-0190

    59
    1
    federal Super Fund liability provisions.
    2
    Unlike the LUST program where only the UST
    3
    owner/operator is liable, under Super Fund
    4
    provision, liability can also attach to prior
    5
    owners and operators and generators and
    6
    transporters.
    7
    Thus, when we were revising Title 17, we
    8
    came up with the terms of remediation applicant
    9
    as an approach that would allow anyone with
    10
    potential liability concerning the site to
    11
    enter the RSP and clean up that site with IEPA
    12
    oversight. That term went into the statute,
    13
    and then it was adopted in part 734 into the
    14
    Board rules, which became effective in 1997.
    15
    Although it is possible under the SRP
    16
    rules for a consultant to become an RA, a
    17
    remediation applicant, on an SRP site, the only
    18
    time I perceived that happening is when a
    19
    consulting firm intends to buy a site, clean it
    20
    up and then sell it for a profit. In those
    21
    instances, the consultant is acting more as an
    22
    owner of the site or maybe in a situation where
    23
    they're looking to become an owner and thus
    24
    develop the property. And that's kind of a
    Keefe Reporting Company
    (618) 244-0190

    60
    1
    rare occurrence.
    2
    In the vast number of instances,
    3
    consultants are hired by RAs within the SRP
    4
    program, and they're hired to perform
    5
    consulting services and are paid by RAs for
    6
    those services. If consultants working under
    7
    the LUST program want to take on the rights and
    8
    responsibilities of owners and operators, they
    9
    can do that, and they can do that by purchasing
    10
    the UST system and registering with the OSFM as
    11
    the owners of the UST system. I don't see any
    12
    reason to add that concept of the UST RA to the
    13
    LUST rules.
    14
    The other thing; I heard Mr. Fleischli's
    15
    testimony this morning, and I'm kind of
    16
    surprised at the issue relative to our proposal
    17
    specifying that a cleanup going beyond Tier 2
    18
    would not be paid for by the UST fund.
    19
    We have talked to numerous consultants
    20
    over the last four to six weeks about the idea
    21
    of specifying that cleanup should not go past
    22
    Tier 2, and they've all seen -- they've all
    23
    told us that they don't see any real problem
    24
    relative to that. And the reason why they
    Keefe Reporting Company
    (618) 244-0190

    61
    1
    don't see any problem -- I'll explain.
    2
    When Tier 1 was developed, it was based on
    3
    conditions at a site which would be the most
    4
    extreme in terms of potential risk.
    5
    Tier 2 provides that a person can go in
    6
    and look at what the conditions are at the site
    7
    and then develop remediation objectives based
    8
    on those conditions.
    9
    Virtually every -- for instance, the SP
    10
    program, virtually everybody who goes into that
    11
    program does an evaluation of the site that
    12
    allows the calculation of Tier 2 objectives.
    13
    And I'll give you one example that I think
    14
    is -- I think is fairly easy to understand.
    15
    Under Tier 1, there was a property assumption
    16
    of soil. It's called the FOC, the fraction of
    17
    organic carbon. When the Tier 1 table was
    18
    created, the assumption was that the fraction
    19
    of organic carbon would be .1 percent, which
    20
    would be the most extreme conditions we could
    21
    find under Illinois soil. What is typically
    22
    you would find in Illinois soil is that it is a
    23
    fraction of organic carbon more around the
    24
    percentage of 1 percent or 2 percent. Well,
    Keefe Reporting Company
    (618) 244-0190

    62
    1
    what that does is you immediately have a
    2
    multiplication factor, common of the cleanup
    3
    objective, which allows it to be raised when
    4
    you do that site-specific investigation.
    5
    And all -- what we're saying is that if
    6
    that's what the soil -- if the soil at a site
    7
    is not going to allow contamination to move,
    8
    based on the Tier 2 calculations, then why
    9
    should we be funding cleanups through Tier 1
    10
    level, which are not needed to assure that same
    11
    level of public health protection?
    12
    So I'll finish my comments with that.
    13
    HEARING OFFICER TIPSORD: Are there any
    14
    questions for the Agency? I assume we're ready
    15
    for questions? Any questions?
    16
    MR. WALTON: Harry Walton, Illinois
    17
    Environmental Regulatory Group, and Chairman of
    18
    the Regulation and Site Remediation Advisory
    19
    Committee. And I have some questions with
    20
    regard to remedial objectives.
    21
    QUESTIONS BY MR. WALTON:
    22
    Q I'd like to take it pathway by pathway.
    23
    On the ingestion, are you proposing
    24 any real changes to the risk posed in the ingestion
    Keefe Reporting Company
    (618) 244-0190

    63
    1 pathway when you go to Tier 2?
    2
    A (By Mr. Clay) No.
    3
    Q Thank you. For inhalation, when you
    4 calculate a site-specific cleanup objective for
    5 inhalation, would there be a change for the
    6 inhalation pathway?
    7
    A No.
    8
    Q Please evaluate that. I think there would
    9 be a bit of a change on that, on the FOC.
    10
    A Okay.
    11
    Q Now, under those scenarios when you do a
    12 Tier 2, would there be any institutional controls
    13 placed on the property that would go with the
    14 property in the future?
    15
    A What we're proposing, there would be no
    16 additional institutional controls put on the
    17 property. You would be required to record the NFR
    18 letter, but there would be no additional conditions
    19 on that NFR letter.
    20
    Q With regard to the ingestion pathway and
    21 statewide background number for PNAs, would those be
    22 used as remedial objectives at LUST sites?
    23
    A Could you repeat that please?
    24
    Q With regards to the PNA statewide
    Keefe Reporting Company
    (618) 244-0190

    64
    1 background numbers, in the Metropolitan City of
    2 Chicago, would those be used as objectives in the
    3 Tier 1 numbers?
    4
    A Yes, they would be.
    5
    Q And, again, would those require any
    6 institutional controls placed on the property?
    7
    A No, just the recording of the NFR letter.
    8
    Q In regards to the groundwater pathway,
    9 where would the receptor exposure be in the
    10 groundwater pathway? Is it at all points on the
    11 property, property boundary?
    12
    A What we're -- I guess I don't understand
    13 your question. You mean the Tier 2?
    14
    Q The Tier 2, where would the compliance
    15 point be moved to under this scenario?
    16
    A The Tier 2 would apply on site. If it is
    17 off site, it would still have to meet Tier 1.
    18
    Q So there would be no institutional control
    19 with the exclusion of groundwater pathway under your
    20 Tier 1 scenario?
    21
    A Correct.
    22
    Q Are you stating that you would use the SSL
    23 equations, the vertical migration equations, in your
    24 FOC to calculate the Tier 2?
    Keefe Reporting Company
    (618) 244-0190

    65
    1
    A Yes.
    2
    Q You also stated that the remedial
    3 objectives would be based upon use of the
    4 groundwater ordinance. In this case, where would
    5 the exposure point be measured?
    6
    A Yeah. It would be at the outside of the
    7 ordinance, the model of extent of that
    8 contamination.
    9
    Q Would that exclusion require an
    10 institutional control placed on the property?
    11
    A There would be -- other than the ordinance
    12 being mentioned, use of the ordinance being
    13 mentioned in the NFR letter, there would be no other
    14 institutional control.
    15
    Q So all receptors, on-site receptors, they
    16 would be exposed in a direct context sense, to
    17 Tier 1 ROs at point of exposure?
    18
    A Yes, you could say it that way.
    19
    Q How many LUST sites are there in Illinois
    20 that are in communities that there's a current
    21 groundwater use ordinance?
    22
    A As I stated, there had been 23,000
    23 releases. Of those, over 10,000 are located in
    24 ordinance communities. We've approved 111
    Keefe Reporting Company
    (618) 244-0190

    66
    1 ordinances in Illinois. And that's the total
    2 issues. There's 10,000, approximately 10,000 open
    3 releases that still need to be remediated, and about
    4 4,000 of those are located in ordinance communities.
    5
    Q So I guess Gary said Tier 1 solution is as
    6 protective to a Tier 2 solution, and that holds for
    7 all pathways?
    8
    A Correct.
    9
    MR. WALTON: That's it.
    10
    MR. CLAY: I might add one more thing.
    11
    Treatment of groundwater is oftentimes the most
    12
    expensive part of a cleanup. And when you look
    13
    at the numbers, if there's 4,000 sites that are
    14
    in ordinanced areas and could use an ordinance,
    15
    if those 4,000 sites, you know, chose to
    16
    remediate groundwater, even though it wasn't
    17
    necessary, and I think it's a conservative
    18
    number of a hundred thousand dollars to cleanup
    19
    that groundwater -- usually it's higher.
    20
    You're talking about $400 million, to put this
    21
    in perspective in dollars, that we feel is
    22
    cleanup that's not necessary, because the
    23
    ordinance prohibits the use of that groundwater
    24
    as potable, for installing potable wells, so.
    Keefe Reporting Company
    (618) 244-0190

    67
    1
    HEARING OFFICER TIPSORD: You have a
    2
    follow-up on that?
    3
    BOARD MEMBER JOHNSON: No.
    4
    HEARING OFFICER TIPSORD: Go ahead.
    5
    BOARD MEMBER JOHNSON: I was looking over
    6
    this, Doug, the new Section 855, which bothers
    7
    me. I was used to calling it ordinary,
    8
    extraordinary, an unusual expenses 855.
    9
    But I assume that that was going to be the
    10
    addition that was going to engender the most
    11
    interest or most questions.
    12
    QUESTIONS BY BOARD MEMBER JOHNSON:
    13
    Q The biggest question I had was in Section
    14 C, in part, in 855, your proposed language is the
    15 maximum payment amount for the work bid shall be the
    16 amount of the lowest bid, unless the lowest bid is
    17 less than the maximum payment amount set forth in
    18 Subpart H, in which case the maximum payment amount
    19 set forth in Subpart H shall be allowed.
    20
    And this goes back, I guess, to
    21 essentially our first hearing when we talked about
    22 your Subpart H maximum payments is -- to me this
    23 implies that no longer is going to be -- I mean,
    24 it's implying that regardless of what the bids are,
    Keefe Reporting Company
    (618) 244-0190

    68
    1 you get three of them, they're all under the amount
    2 that you've defined as the maximum number, payment
    3 allowed. We're going to get the maximum payment
    4 allowed. Am I reading that right?
    5
    A (By Mr. Clay) Yes.
    6
    Q Do you recall the question somebody asked
    7 in the first hearing that these are maximum amounts,
    8 and if in fact the amount comes in underneath that,
    9 that's what's going to be reimbursed, rather than
    10 the amount delineated in Subpart H?
    11
    A Because someone could, without bidding, go
    12 in and do the work for the amounts in Subpart H, we
    13 put it in C that way to allow them to go ahead and
    14 use Subpart H.
    15
    And I would have to agree with you;
    16 that would be reasonable to take the lowest bid,
    17 since we've also stated in testimony that someone
    18 who's conducting this bidding has already
    19 predetermined or prequalified these bidders as
    20 someone that would be acceptable to them.
    21
    Q And you're going to require not only if I
    22 get five bids, I'm going to want all five of them so
    23 I can't pick and choose which ones I submit to you,
    24 then this seems to imply as well that if I go out
    Keefe Reporting Company
    (618) 244-0190

    69
    1 and get any bids, three or more, I'm going to have
    2 to submit them to you, whether or not I intend
    3 to -- I guess what I'm saying is, if I'm an
    4 owner/operator, and I go out and get three bids and
    5 they all are underneath the maximum allowable
    6 amount, unless I'm required by the rules to do so,
    7 I'm not going to submit them to you guys. Does this
    8 require the submission of any bid for any work?
    9
    A We didn't want to penalize the consultant
    10 from bidding if they did all come in below the
    11 maximum payment amount. So in those cases, they
    12 wouldn't have to submit those bids. They could just
    13 use the maximum amount.
    14
    Q Okay. I think it would probably be easier
    15 to reconcile with the statutory language that rather
    16 than have you guys looking at a bid, that
    17 identifies, you know, an amount less than what the
    18 maximum allowable amount is, I think it seems to me
    19 like it's better for your reviewers to say this is a
    20 reasonable expense when they don't have to -- when
    21 or for any amount less.
    22
    A Okay.
    23
    Q I guess I had a question with respect to
    24 the now 860, which is the old 855.
    Keefe Reporting Company
    (618) 244-0190

    70
    1
    Is that intended to kick in only in
    2 instances where bids have been sought previously?
    3 Or only instances -- your example was if there
    4 aren't three people, which is the question I was
    5 going to ask.
    6
    What if you can't find three
    7 subcontractors that are going to be able to bid on
    8 this, because there aren't three of them in the
    9 State of Illinois? When does that kick in? When
    10 does that 60 kick in? Whenever it fits this
    11 definition that it looks like a three part task, to
    12 determine maximum payment amount, amounts -- let's
    13 see. They demonstrate to the Agency the costs are
    14 eligible for payment, they exceed the maximum
    15 payment and the result of unusual or extraordinary
    16 circumstances. You're not going to have the
    17 requirement that owner/operator first exhaust the
    18 bidding process?
    19
    A I think the intent was that they don't
    20 necessarily have to bid, but this is an
    21 extraordinary circumstance that they've identified
    22 up front, you know. We would expect they would
    23 probably bid that to show that it's going to be over
    24 the maximum payment amounts.
    Keefe Reporting Company
    (618) 244-0190

    71
    1
    There could be situations that
    2 they've got an approved plan and budget. They go
    3 in, they're doing the work, and then they come
    4 across some extraordinary, unusual or extraordinary
    5 circumstance. Well, at that point, you obviously
    6 can't bid it. You're implementing the corrective
    7 action plan at that point. Then they can come to
    8 the Agency and justify those higher costs.
    9
    BOARD MEMBER JOHNSON: Thank you.
    10
    HEARING OFFICER TIPSORD: Go ahead.
    11
    MR. WEINHOFF: Jeff Weinhoff, CW3M. I
    12
    just had a couple questions on the mechanics of
    13
    the bidding process.
    14
    QUESTIONS BY MR. WEINHOFF:
    15
    Q For example, during stage one, you bid
    16 drilling, and it came out two dollars a foot higher.
    17 And that was, you know, for three bids. The low was
    18 two dollars a foot higher. Would you need to rebid
    19 stage two and stage three? Or would that bid be
    20 good for that site forever, or each time you're
    21 going to propose it, would you need to rebid it?
    22
    A (By Mr. Clay) I think you need to rebid
    23 each time, because I think your bid that you're
    24 requesting or your proposal you're requesting bids
    Keefe Reporting Company
    (618) 244-0190

    72
    1 for would be different.
    2
    Q So with each submittal you need to rebid
    3 that work?
    4
    A Correct.
    5
    Q Okay. And the second question I had was
    6 like for excavation, transportation, backfill, are
    7 you requiring like three bids for excavation and
    8 three bids for transportation and three bids for
    9 disposal, or three bids for the whole job together?
    10
    A We would anticipate it would be for each
    11 stage of that. Three bids for transportation, three
    12 bids for excavation and three bids for disposal,
    13 since you're dealing with different companies for
    14 disposal, different companies for trucking,
    15 different companies for excavation.
    16
    Q I see. So you wouldn't get one contractor
    17 do it all for you? You'd get a separate amount?
    18
    A Correct.
    19
    Q Okay. And then with disposal, how would
    20 distance with the landfill be affected? Because
    21 you've got three bids for transportation, those bids
    22 are going to be affected by which landfill you're
    23 going to use, for example. So would you need nine
    24 then to go with your three landfill bids, or the
    Keefe Reporting Company
    (618) 244-0190

    73
    1 three different landfills that you do bid?
    2
    A Well, I guess the bid from three trucking
    3 companies, for example, or three different
    4 landfills.
    5
    Q So you'd get different costs for each
    6 trucking company and landfill and excavator?
    7
    A Yes. Well, I don't know why the excavator
    8 makes any difference. Trucking would be the only
    9 difference because of the distance of the landfill.
    10
    MR. WEINHOFF: That's all I have.
    11
    HEARING OFFICER TIPSORD: Mr. --
    12
    MR. TRUESDALE: A couple of questions.
    13
    HEARING OFFICER TIPSORD: You need to
    14
    note -- you need to identify yourself for the
    15
    court reporter.
    16
    MR. TRUESDALE: Joe Truesdale with CST
    17
    Environmental Services.
    18
    QUESTIONS BY MR. TRUESDALE:
    19
    Q One question, just to clarify Jeff's
    20 statement about the drilling costs.
    21
    You mentioned that the drilling costs
    22 for each activity in the stage, one stage, two
    23 stage, three site investigation would be bid
    24 separately. So essentially what you're saying then
    Keefe Reporting Company
    (618) 244-0190

    74
    1 is the costs associated with those bids would be
    2 entirely dependent on the scope of work being
    3 performed, correct?
    4
    A (By Mr. Clay) Yes.
    5
    Q The second question. In the proposal to
    6 limit remediation on sites and use the groundwater
    7 ordinance to address the ingestion of groundwater
    8 objective, and the original ASTM corrective based
    9 action document that TACO is based on, there are
    10 other pathways essentially that are addressed,
    11 inhalation of dissolved hydrocarbon in the
    12 groundwater that's virtually ignored in TACO. So
    13 under the existing frame work of TACO, since the
    14 owner/operator always has the ability to clean up to
    15 groundwater ingestion objectives, it's never been a
    16 technical issue. However, if you run through those
    17 numbers in ASTM and put in some general values, you
    18 usually come up with something that says benzene
    19 concentration somewhere less than one part per
    20 million would pose an excessive risk for inhalation.
    21 This is all hydrocarbons in groundwater.
    22
    Now, in the context of using the
    23 groundwater ordinance, the soilability limits, you
    24 can have up to 20 parts per million benzene in the
    Keefe Reporting Company
    (618) 244-0190

    75
    1 groundwater.
    2
    Has there been any consideration
    3 given to evaluating those potential inhalation risks
    4 associated with leaving those contaminants in place?
    5
    A Well, I mean the three pathway, the three
    6 exposure pathways --
    7
    HEARING OFFICER TIPSORD: Speak up.
    8
    MR. CLAY: There are three exposure
    9
    pathways to TACO. Ingestion, soil inhalation
    10
    and then ingestion of groundwater. And those I
    11
    don't know we're anticipating any new exposure
    12
    methods.
    13
    MR. KING: If I just could make a comment
    14
    on that.
    15
    Where I think Mr. Truesdale has suggested
    16
    that there may be some additional changes that
    17
    may be warranted to TACO, I don't think it's
    18
    appropriate to try to change TACO in the
    19
    context of the LUST rules. The Agency's
    20
    planning on opening a -- proposing additional
    21
    changes to TACO hopefully within the next
    22
    several months. And I think if there's an
    23
    issue about whether there needs to be an
    24
    additional pathway included within TACO, I
    Keefe Reporting Company
    (618) 244-0190

    76
    1
    think that would be an appropriate time to
    2
    discuss that issue.
    3
    Q (By Mr. Truesdale) I think what I'm
    4 stating actually is that in your testimony and
    5 errata sheet, you suggest that this proposal is
    6 adequately protective of human health and the
    7 environment. However, if you read through the ASTM
    8 corrective based action --
    9
    HEARING OFFICER TIPSORD: Mr. Truesdale,
    10
    do you have another question?
    11
    MR. TRUESDALE: Sorry. I apologize.
    12
    HEARING OFFICER TIPSORD: Ms. Manning?
    13
    MS. MANNING: I just have one question for
    14
    Mr. King.
    15
    QUESTIONS BY MS. MANNING:
    16
    Q Gary, you testified very generally and
    17 very broadly that PIPE's proposed language is
    18 inconsistent with federal law and state law. Yet
    19 the only example you gave was the suggestion that
    20 the Board define a UST RA. Certainly the suggestion
    21 was not that Title 17 become Title 16? Title 16 is
    22 Title 16.
    23
    Nonetheless, could you indicate what
    24 other provisions of PIPE's proposed language you're
    Keefe Reporting Company
    (618) 244-0190

    77
    1 speaking of that you consider inconsistent with
    2 either federal or state law?
    3
    A (By Mr. King) I thought Doug went into
    4 several of those within his testimony. At least
    5 that's what I heard him saying.
    6
    MR. CLAY: The approval by operation of
    7
    law, rather than denial, was a big issue with
    8
    the USEPA. It's also contrary to the statute.
    9
    The 45 days for review time proposed by PIPE is
    10
    inconsistent with the state statute, which
    11
    allowed 120 days. Those are two.
    12
    Free product. The wording in the federal
    13
    rules is the maximum practicable -- I believe
    14
    something to that effect, as opposed to whether
    15
    or not it's a threat to human health, which is
    16
    what PIPE is proposing. Those are the ones I
    17
    can name off the top of my head.
    18
    MS. MANNING: We're going to address all
    19
    those. Thank you.
    20
    HEARING OFFICER TIPSORD: Any other
    21
    questions? Start with Mr. --
    22
    MR. COOK: Jay Cook, United Science
    23
    Industries.
    24
    QUESTIONS BY MR. COOK:
    Keefe Reporting Company
    (618) 244-0190

    78
    1
    Q With regard to the competitive bidding
    2 process, is it anticipated that the consultant, the
    3 primary consultant, would solicit bids on behalf of
    4 the owner/operator?
    5
    A (By Mr. Clay) Yes.
    6
    Q And the time required to prepare the bid
    7 specifications to solicit those bids, is that
    8 considered to be a reimbursable corrective action
    9 cost?
    10
    A It's reimbursable as a handling charge.
    11 Under the definition it's partially for procurement.
    12
    Q Can you clarify that? The time it's
    13 actually necessary for the engineer to prepare the
    14 bid specifications and the bidding documents, is
    15 that professional services time reimbursable?
    16
    A It is reimbursable as a handling charge.
    17 As a current handling charge, we believe that's what
    18 that was intended for.
    19
    Q I'm not sure I understand that. As an
    20 example, just to have -- if I had an engineer, let's
    21 say who was working, and he had 10 hours of service
    22 time in preparing the bid specification documents,
    23 and his billing rate was a hundred dollars an hour,
    24 so you've got a thousand dollars charge, is that
    Keefe Reporting Company
    (618) 244-0190

    79
    1 what would be reimbursed, or is it a percentage of
    2 the contract that's awarded? Like, the drilling
    3 contract that's awarded, or a percentage of
    4 the -- or the excavation, transportation, disposal
    5 contract that's awarded?
    6
    A It's a percentage -- if you had a $10,000
    7 subcontractor doing drilling, it's a percentage of
    8 that as your handling charge. And the time to
    9 prepare and put together those bids and to collect
    10 those bids, evaluate those bids would be in that
    11 handling charge.
    12
    Q And so that's different than the rest of
    13 the way that the professional services are handled
    14 within the regulations or reimbursement for
    15 professional service on an hourly basis? This would
    16 be on a percentage base?
    17
    A It is different. It's just the putting
    18 together the bid proposal and evaluating those bids
    19 would be under the handling charge.
    20
    Q And so the consultant would receive more
    21 compensation the higher the bids were; is that
    22 correct?
    23
    A That's the way the handling charges work,
    24 that's correct.
    Keefe Reporting Company
    (618) 244-0190

    80
    1
    I might add, though, if there's a
    2 situation where the owner and operator is going to
    3 reimburse or pay for the subcontractor directly, in
    4 that case, the consultant would not be entitled to
    5 handling charge. There is a provision in -- well,
    6 in Subpart H and then in 734.855, that sets forth an
    7 amount for the consultant for their time for putting
    8 up those bids together.
    9
    Q Separately if the contractor is paid?
    10
    A Yes. Because we recognize there there's
    11 no handling charge for the consultant, but they
    12 would be compensated from them.
    13
    Q They would be paid for their hourly rate
    14 as long as it was reasonable for the services
    15 performed?
    16
    A No. It's not time and material. It's a
    17 specific amount.
    18
    MR. ROMINGER: Clarification. That's an
    19
    845 G. I believe Doug said 855.
    20
    HEARING OFFICER TIPSORD: Thank you.
    21
    Q (By Mr. Cook) And Dwayne just said that's
    22 $160 per event?
    23
    A Yes.
    24
    Q So that's roughly a couple of hours, hour
    Keefe Reporting Company
    (618) 244-0190

    81
    1 and a half?
    2
    A Right. We figured two hours.
    3
    Q To compare each set of specifications?
    4
    A Yes.
    5
    Q Okay. And had the Agency evaluated the
    6 costs of soliciting bids, and in the process of Jeff
    7 just described, it seemed like a fairly elaborate
    8 process to me. There are potentially multiple
    9 rounds of bid solicitation that took place. What
    10 added costs would there be to the program and
    11 estimated added cost to the program to solicit these
    12 bids across the remaining LUST sites? Do you have
    13 an estimate, the increase in cost?
    14
    A I don't have a specific estimate, but
    15 we've always paid handling charges. And, you know,
    16 I assume that they're part of the handling charge is
    17 to, you know, seek a competitive price. And so I
    18 mean, I guess we anticipate that that was being done
    19 to some degree already because that's what handling
    20 charge is for in part.
    21
    Second, I don't think we -- I mean,
    22 in a lot of cases, there's not going to be bids
    23 sought. They're going to use the maximum payment
    24 amounts as -- Member Johnson said, I mean, you don't
    Keefe Reporting Company
    (618) 244-0190

    82
    1 have to bid it. I mean, from what we've heard from
    2 the number of consultants, the amounts in the rules,
    3 they don't have a problem with it. So I don't see
    4 everything going to bidding. But if they do, it's
    5 covered by the handling charges.
    6
    MR. COOK: I don't have any other
    7
    questions.
    8
    MR. GOODWIN: Mr. Dan Goodwin with Secor
    9
    International.
    10
    QUESTIONS BY MR. GOODWIN:
    11
    Q Doug and Gary and Kyle, any of the three
    12 of you that you feel like you can respond to this
    13 question, I'd like to hear from you.
    14
    You have introduced three, I think,
    15 pretty significant concepts into this latest set of
    16 changes to the proposal. One being the concept of
    17 competitive bidding and particularly as an
    18 alternative to the dollar limits on reimbursement
    19 that would apply.
    20
    Secondly, the requirement for
    21 obtaining cost estimates, provided cost estimates,
    22 on at least two alternative technologies in addition
    23 to standard technology cost estimate in order to
    24 establish a reimbursement limit for that.
    Keefe Reporting Company
    (618) 244-0190

    83
    1
    And the third item -- my mind has
    2 gone blank.
    3
    A (By Mr. Clay) TACO.
    4
    Q TACO. The introduction of the TACO Tier 2
    5 concept was discussed earlier.
    6
    My question is, for any or all three
    7 of those concepts, have you done a analysis of the
    8 statutory authority and satisfied yourselves that
    9 the statutory authority is already there, and if so,
    10 would you be willing to provide that analysis?
    11
    A (By Mr. King) Are you asking whether we've
    12 done a legal analysis?
    13
    Q Yes.
    14
    A I don't -- we haven't seen a formal legal
    15 analysis on those things, no.
    16
    Q Okay. Do you intend to do one if it
    17 appears there's an issue?
    18
    A I'm sure we would if there was an issue.
    19 But as we've always seen the Board's authority in a
    20 rule making, you know, there are specific things
    21 that the Board -- you know, the Board can't be
    22 inconsistent with its statutory authority. And
    23 we've identified some areas where there are certain
    24 things, you know, in the PIPE proposal that we
    Keefe Reporting Company
    (618) 244-0190

    84
    1 thought are inconsistent with that authority. We
    2 did not identify any inconsistency issues as we were
    3 evaluating what we were suggesting here.
    4
    Q Wouldn't you agree that to incorporate any
    5 of those three proposals into the regulations, the
    6 Board has to make a finding that there is an
    7 underlying statutory authority for the Board to do
    8 such a thing?
    9
    A Oh, I would agree, yes, absolutely.
    10
    Q But you, the Agency, has not really done
    11 any kind of a formal evaluation to make a finding to
    12 present to the Board that that already does in fact
    13 exist?
    14
    A We have not done any kind of formal
    15 internal document. I assume that we certainly could
    16 look at that issue in terms of our comments and
    17 provide input to the Board on that legal question.
    18
    MR. GOODWIN: Thank you.
    19
    HEARING OFFICER TIPSORD: Ms. Davis?
    20
    MS. DAVIS: I am Cindy Davis, CDS.
    21
    QUESTIONS BY MS. DAVIS:
    22
    Q I have a question on the proof of payment
    23 and the handling charge.
    24
    Doug, you just described a situation
    Keefe Reporting Company
    (618) 244-0190

    85
    1 where, let's say, you need to go out, and you need
    2 to haul to a landfill, but couldn't, due to the
    3 price the Agency has established. We would go out
    4 and get three bids. What happens in the case,
    5 though, where the owner/operator wants the
    6 contractor to wait for payment, and let's say the
    7 subcontractors have waited for payment? So I won't
    8 have proof of payment to put in the reimbursement
    9 request. So in that case, what I'm understanding
    10 the rules say, that there is no handling charge if
    11 you can't provide proof of payment. So how does the
    12 consultant get paid to go for the three bids?
    13
    A (By Mr. Clay) Well, it's just not the
    14 canceled check. There could be a lien waiver, and
    15 there was another affidavit -- yeah, an affidavit or
    16 lien waiver or a canceled check. So I mean, you
    17 could provide a lien waiver.
    18
    Q Okay.
    19
    MR. SCHUMACHER: You're not --
    20
    HEARING OFFICER TIPSORD: Excuse me. You
    21
    need to identify yourself.
    22
    MR. SCHUMACHER: Brad Schumacher.
    23
    24
    QUESTIONS BY MR. SCHUMACHER:
    Keefe Reporting Company
    (618) 244-0190

    86
    1
    Q You do a cleanup for 200,000. You get
    2 done Monday. You went to submit the reimbursement
    3 on a Friday for your reimbursement. Obviously you
    4 haven't paid the trucker, you haven't paid the
    5 landfill, you haven't paid anybody yet. So you're
    6 not going to have the waiver or anything.
    7
    MS. DAVIS: That is a problem.
    8
    HEARING OFFICER TIPSORD: Excuse me,
    9
    excuse me. We're drifting into testimony.
    10
    MS. DAVIS: Okay.
    11
    HEARING OFFICER TIPSORD: Please stick to
    12
    questions. If you want to comment on this at
    13
    the end of the day, I'll be more than happy to
    14
    let you testify.
    15
    MS. DAVIS: That was my -- that was the
    16
    end of the question.
    17
    QUESTIONS BY MS. DAVIS:
    18
    Q And the next question I have is, in the
    19 case of a drilling aspect where I own my own
    20 drilling company, and let's say a particular site I
    21 can't do a drilling for the set price. So I go out
    22 and I get three bids as the Agency has allowed me.
    23 And it also allows me that if I wanted to, I could
    24 do the work for the lowest bid. How do I get paid
    Keefe Reporting Company
    (618) 244-0190

    87
    1 for my handling for my time to go get those bids for
    2 the scope of work? Because I'm a person who is
    3 using a subcontractor with the indirect financial
    4 interest. I mean, how do I get paid?
    5
    A (By Mr. Clay) In that case, I think you
    6 would be entitled to that lump sum as if the owner
    7 and operator were paying for the subcontractor. And
    8 then, you know, that's sort of a business decision.
    9 That's a decision you're making, that you want, in
    10 your case, your company to do the work as opposed to
    11 the low bidder.
    12
    MS. DAVIS: Okay.
    13
    HEARING OFFICER TIPSORD: Go ahead.
    14
    MR. SCHUMACHER: Brad Schumacher.
    15
    QUESTIONS BY MR. SCHUMACHER:
    16
    Q I didn't get an answer. If I sent in my
    17 reimbursement claim, I am not going to have any
    18 waivers, cancelled checks, affidavit, because I
    19 haven't paid my contractor yet. So are you going to
    20 deny my claim? Or how does that work? Obviously,
    21 we're going to pay our subcontractor, but what if my
    22 terms are 90 days, I submit a claim, and you're
    23 going to not process the claim because I don't have
    24 the waivers? Or backups that I'm paying the
    Keefe Reporting Company
    (618) 244-0190

    88
    1 subcontractor?
    2
    MR. CLAY: Can I respond to that this
    3
    afternoon?
    4
    HEARING OFFICER TIPSORD: Sure.
    5
    MR. CLAY: Let us discuss it.
    6
    MR. SCHUMACHER: Thanks.
    7
    HEARING OFFICER TIPSORD: Mr. Truesdale?
    8
    QUESTIONS BY MR. TRUESDALE:
    9
    Q One more question. It's related to what
    10 Mr. Goodwin talked about earlier and about the TACO.
    11
    You mentioned before, Doug, that you
    12 don't expect that there will be deed restrictions or
    13 other environmental land use controls required for
    14 sites that use the Tier 2 objectives. And
    15 Mr. Walton referred to the PNA background analysis
    16 for metropolitan areas, for instance.
    17
    What if an owner/operator did soil
    18 removal at a site after issuance of an SRN based on
    19 background PNA data, and that soil was subsequently
    20 moved to a site outside of the metropolitan area, or
    21 in a case where a Tier 2 inhalation objective was
    22 calculated based on site-specific moisture content
    23 and that soil was subsequently excavated and spreads
    24 to the soil where the physical characteristics
    Keefe Reporting Company
    (618) 244-0190

    89
    1 forced the moisture content to change and
    2 volitization occur. How would the Agency address
    3 those situations?
    4
    A (By Mr. Clay) Well, on every one of our
    5 NFR letters, there should be a condition that says
    6 to the effect any soil removed from the site needs
    7 to be handled in a proper manner. Whether it's
    8 Tier 1 or Tier 2, the Agency -- or the LUST section
    9 is not making a determination whether that soil is
    10 moved to a different location as a waste. They're
    11 saying that that soil in place is safe, is
    12 protective to human health and environment.
    13
    So what I said was there would
    14 be -- you would see no difference in the NFR letter
    15 if it was a Tier 1, based on the Tier 1 numbers. Or
    16 if you collected site-specific soil property
    17 information calculated Tier 2, you wouldn't be able
    18 to tell that in your NFR letter. There would be no
    19 additional conditions. We'd still have the
    20 condition on both, that, you know, if soil is
    21 removed, it needs to be handled in accordance with
    22 the appropriate regulation.
    23
    Q But under the current frame work, the
    24 owner/operator always had the ability to clean up to
    Keefe Reporting Company
    (618) 244-0190

    90
    1 the most stringent Tier 1 objectives. So there are
    2 no expressed costs associated with managing that
    3 waste. If it was excavated and disposed of, the
    4 cost would still fall on the owner/operators under
    5 the new scenario; is that correct?
    6
    A I don't understand the question.
    7
    Q If the owner/operator made the decision to
    8 clean up to the most stringent Tier 1 subsequently
    9 excavated soil and moved it to another property, it
    10 already met the most stringent Tier 1 objectives
    11 applicable to any property in Illinois. So there
    12 would be no expressed risk with managing that
    13 material in accordance with state regulations.
    14 However, under the new frame work, there could be
    15 costs associated with that, for the owner/operators,
    16 correct?
    17
    A You're assuming that with that statement,
    18 you're assuming that Tier 1 residential can be put
    19 in any location anywhere and has no waste
    20 designation. We don't make that decision in the
    21 LUST program.
    22
    Q Right.
    23
    A And so, you know, there may be soil that
    24 meets the Tier 1 residential that wouldn't be
    Keefe Reporting Company
    (618) 244-0190

    91
    1 appropriate for certain areas or conditions to put
    2 into. So we're not making that designation that
    3 it's clean soil, if you will. We don't have that
    4 authority in the LUST program.
    5
    MR. COOK: Jay Cook with USI.
    6
    QUESTIONS BY MR. COOK:
    7
    Q Under the federal financial responsibility
    8 requirements, the definition of financial
    9 responsibility, is there a specific definition of
    10 what an owner/operator must demonstrate in the
    11 financial, in terms of financial responsibility? We
    12 know there are monetary amounts. But that financial
    13 responsibility originally was intended to do several
    14 things. One of them, I believe, was to show that
    15 the owner/operator is capable of undertaking a
    16 corrective action; is that correct?
    17
    A That's correct.
    18
    Q Financially capable of undertaking a
    19 corrective action?
    20
    A Right.
    21
    Q And corrective action then in Illinois
    22 could include remediation to either Tier 1 or Tier 2
    23 requirements; is that correct?
    24
    A Tier 1, Tier 2, Tier 3.
    Keefe Reporting Company
    (618) 244-0190

    92
    1
    Q Are there instances where the Agency could
    2 require an owner/operator to utilize a more
    3 stringent cleanup criteria than what's being
    4 proposed in this Tier 2 type of situation?
    5
    A It would be based on what's outlined in
    6 the regulations. That Tier 1, Tier 2 or Tier 3, if
    7 they met that, then we would issue the remediation
    8 letter.
    9
    Q In instances where the Agency is proposing
    10 that reimbursement only be allowed to the use of
    11 these Tier 2 objectives, is it possible that the
    12 Agency could require what I'll call a more
    13 conservative cleanup approach? In other words,
    14 meeting more stringent cleanup objectives?
    15
    A (By Mr. King) I don't see how that's
    16 legally possible, because, I mean, TACO provides
    17 different methodologies for a person to establish
    18 remediation objectives relative to a site. And the
    19 way the Board rule is set up under 742, that's an
    20 owner/operator's decision to make.
    21
    Q So if they elect, they could utilize
    22 Tier 2 and still meet the requirements legally that
    23 are imposed by the Agency, and the Agency could not
    24 require them to perform the work?
    Keefe Reporting Company
    (618) 244-0190

    93
    1
    A Yes, that's correct.
    2
    Q Okay. With that being the case, as a
    3 practical matter, do you have an estimate of the
    4 number of owners and operators in the State of
    5 Illinois that are financially able to undertake a
    6 cleanup that would exceed these Tier 2, those -- how
    7 much, as a practical matter, how much of the
    8 owner/operators will utilize Tier 1 or something
    9 more stringent than what you're proposing is the
    10 maximum amount that would be reimbursed under this
    11 Tier 2 approach?
    12
    A I think it would be very few.
    13
    Q Very few? So as a practical matter, sort
    14 of the default cleanup objective becomes this Tier 2
    15 approach conditioning?
    16
    A I'm trying to think. I guess I'm, in
    17 responding to that, I'm just trying to figure out
    18 what -- I guess I wouldn't quite use the term
    19 "default cleanup objective."
    20
    Q It would be the method of choice by the
    21 vast majority owners and operators in your
    22 estimation?
    23
    A I think that's probably true. I mean, I
    24 think you're correct in your statement that far
    Keefe Reporting Company
    (618) 244-0190

    94
    1 fewer number of owners and operators will go to
    2 Tier 1. They would stay with Tier 2 because that's
    3 what we would be paying for. And it would be in our
    4 view, it would certainly be equally protective with
    5 Tier 1. There may be some owners -- I mean, there
    6 are owners and operators now that utilize Tier 3
    7 provisions, and that certainly would be the case
    8 still.
    9
    Q Is it a fair characterization to say then
    10 that because of the owners and operators, the
    11 majorities of them probably don't have the money to
    12 take the more stringent approach to clean up, that
    13 they take this approach, is it a fair
    14 characterization by saying by shifting that, the
    15 eligibility of those sites, so that the maximum
    16 amount of reimbursement that's available at these
    17 sites is based on Tier 2 objectives? That it really
    18 is a practical matter, for all intents and purposes,
    19 you've practically cleaned -- or changed the
    20 remediation objectives, as a practical matter? Not
    21 as a technical matter, not as a legal matter, but
    22 just as a practical matter, you've changed the
    23 remediation objectives statewide?
    24
    A No, I wouldn't say it that way at all. I
    Keefe Reporting Company
    (618) 244-0190

    95
    1 mean, the remediation objectives are still
    2 within -- established under 742. And there's Tier
    3 1, Tier 2, Tier 3. We haven't changed those
    4 remediation objectives. We've changed that, what
    5 would be reimbursed.
    6
    MR. CLAY: And to add to that, I mean, as
    7
    Gary testified earlier, in the site remediation
    8
    program when those people that are in the
    9
    program are footing the bill, they almost in
    10
    all cases go to Tier 2.
    11
    Q For what reason in your estimation?
    12
    A Because of footing the bill and being
    13 cheaper cleanup, and it's equally protective of
    14 human health and the environment.
    15
    Q Because, in your opinion, does -- Gary,
    16 you're an attorney, I believe; is that correct?
    17
    A (By Mr. King) Yes.
    18
    Q In your opinion, would an owner/operator
    19 incur more liability to a third party if they only
    20 clean up the Tier 2? Let's say that I'm a tank
    21 owner, but I don't own the site; I don't own the
    22 real estate; I own the tanks. And as a result of
    23 that, I'm responsible for cleaning this site up.
    24 Now, if I only remediate to Tier 2, that's all I
    Keefe Reporting Company
    (618) 244-0190

    96
    1 have to do as it pertains to my relationship with
    2 the Agency. But as my relationship is established
    3 with this property owner, they may not be very happy
    4 about that.
    5
    So in your opinion, do I have greater
    6 liability to this third party property owner because
    7 I haven't cleaned up to Tier 1?
    8
    A I would say the answer is no.
    9
    When we established TACO in 1997, we
    10 were very careful, and we went through a large
    11 number of debates, a large number of testimony
    12 around the whole concept that in terms of public
    13 health protection and protection of the environment,
    14 a Tier 1 was equal to a Tier 2, was equal to a Tier
    15 3.
    16
    Now, there may be -- and we see this
    17 particularly in the site remediation program. If
    18 you've got an out-of-state developer who wants to
    19 buy a piece of property, he will demand that that
    20 property be cleaned up to -- sometimes will demand
    21 that that property be cleaned up to at least Tier 1
    22 because he may not be familiar with the Illinois
    23 system.
    24
    And when those questions come up, we
    Keefe Reporting Company
    (618) 244-0190

    97
    1 have to -- you know, we go through and discuss with
    2 people what Tier 2 and Tier 3 are and that kind of
    3 thing. And usually people, once they understand
    4 what we're doing in Illinois, are willing to accept
    5 something other than Tier 1 as a methodology.
    6
    Q I see. The answer to that then is, no,
    7 that wouldn't, in your opinion, change the liability
    8 between the property owners. I would assume that it
    9 would not decrease the potential for lawsuits
    10 between the parties.
    11
    Is the fund, can the indemnification
    12 within the fund for third party indemnifications be
    13 tapped in this instance where the owner of the tanks
    14 has elected not to clean up to Tier 1, elected to
    15 cleanup to Tier 2, and the property owner is a
    16 separate party and is unhappy about that decision on
    17 the part of the tank owner/operator, can the
    18 property owner make a claim against the fund for
    19 indemnification, third party indemnification?
    20
    A Well, anybody can make a claim relative to
    21 for indemnification, and that has to go through the
    22 process, through the Attorney General's office and
    23 that.
    24
    But we could take the position that
    Keefe Reporting Company
    (618) 244-0190

    98
    1 indemnification would not be proper, because if
    2 they've done a Tier 2 cleanup, it was the same issue
    3 of potential risk to human health or environment as
    4 a Tier 1 claim.
    5
    MR. COOK: Okay. I just had a question
    6
    that I wanted clarification.
    7
    BOARD MEMBER GIRARD: Can I just follow up
    8
    on that?
    9
    QUESTIONS BY BOARD MEMBER GIRARD:
    10
    Q In terms of, you know, protection of human
    11 health and the environment, you feel that an NFR
    12 letter provides that; is that correct?
    13
    A (By Mr. King) Yes.
    14
    Q So it means you met all the obligations
    15 under the Act?
    16
    But the questions about liability
    17 still, I'm not sure, has been clearly answered. If
    18 a property owner has an NFR letter, does that
    19 property owner then have any future liability for
    20 the contamination that may still be in the ground
    21 from the LUST site?
    22
    A There's certainly a large body of cases
    23 that involve tort law where individual citizens sue
    24 companies with claims that their health has been
    Keefe Reporting Company
    (618) 244-0190

    99
    1 impacted through the contamination of the site. You
    2 could have an NFR letter on a site, the site has
    3 been cleaned up, to protect human health and the
    4 environment, and somebody could still file a claim
    5 saying that there had been a human health impact
    6 that was tortuous in nature, in that there was
    7 liability related to that.
    8
    Now, that claim would exist -- it
    9 could exist if I've cleaned up -- it wouldn't matter
    10 what you cleaned it up to. You could still have
    11 somebody making that kind of claim, whether it was
    12 Tier 1, Tier 2. Somebody could still claim that the
    13 owner and operator was liable for impact to their
    14 human health based on a tort law offense.
    15
    MR. CLAY: And keep in mind, the Tier 1
    16
    versus Tier 2 that we're talking about is
    17
    simply applying site-specific soil
    18
    characteristics to the cleanup objectives as
    19
    opposed to very conservative.
    20
    MR. KING: As opposed to the default
    21
    number which Tier 1 is based on.
    22
    MR. CLAY: Right. So it's not increasing
    23
    the -- you know, in most cases, one in a
    24
    million risk that, you know, TACO was based on.
    Keefe Reporting Company
    (618) 244-0190

    100
    1
    Q (By Board Member Girard) But you feel that
    2 legally cleaning up the Tier 2 standards provides as
    3 much protection from liability as cleaning up to
    4 Tier 1?
    5
    A (By Mr. King) Well, you're talking about
    6 potential risk to human health or the environment,
    7 yes.
    8
    BOARD MEMBER GIRARD: Thank you.
    9
    HEARING OFFICER TIPSORD: Okay?
    10
    MR. GOODEIL: Russ Goodeil, Applied
    11
    Environmental.
    12
    QUESTIONS BY MR. GOODEIL:
    13
    Q Doug, I've got a question, I guess, on the
    14 simplest terms.
    15
    You had indicated that there are a
    16 hundred and eleven communities that have groundwater
    17 use ordinance.
    18
    A (By Mr. Clay) Yes.
    19
    Q And the Agency is basically encouraging,
    20 and even through this proposed legislation, forcing
    21 owners/operators or consultants to go out and get
    22 more groundwater. Then I guess my question --
    23
    A That's not true. That's not true.
    24
    Q Then, like I say, I'm not a hydrogeologist
    Keefe Reporting Company
    (618) 244-0190

    101
    1 or engineer or anything. But I guess, you know, as
    2 more of a citizen, my concern comes in if we're
    3 implementing these groundwater use ordinances and
    4 not cleaning up the groundwater, granted it is
    5 expensive, where do we as citizens and Environmental
    6 Protection Agency draw the line as to how many
    7 communities or how much groundwater contamination is
    8 acceptable? And that's, I guess, you know, in the
    9 simplest terms.
    10
    A Well, the community makes that
    11 determination whether or not they want to adapt that
    12 ordinance. And what we're posing is the utilization
    13 of that ordinance, only if one has been approved and
    14 adopted and is acceptable to that site.
    15
    I mean, you may have a site that's on
    16 the edge of the ordinance. Even though the
    17 community has an ordinance, you wouldn't be required
    18 to use that, because the model and the extent of the
    19 contamination goes beyond that.
    20
    So the idea is not that anyone has to
    21 go in and adopt an ordinance or go to a municipality
    22 and request the adoption of the ordinance. If one
    23 is already there and is approved and can be used,
    24 that's the one that has to be utilized.
    Keefe Reporting Company
    (618) 244-0190

    102
    1
    Q As a follow-up to that, what level of
    2 groundwater contamination as citizens of Illinois is
    3 acceptable? I mean, where do we draw the line? I
    4 mean, I know expenses are a major concern. But how
    5 much contamination in Illinois groundwater is
    6 acceptable?
    7
    A (By Mr. King) Well, I mean, that to me, it
    8 seems like that's an appropriate debate to consider
    9 when we're talking about what is within the TACO
    10 regulations. And I think that is an issue that we
    11 certainly debated at the time those regulations were
    12 adopted.
    13
    You know, to give you an example of
    14 kind of the thought process that we've been going
    15 through with this. There is an ordinance within the
    16 City of Chicago that's in effect that prohibits the
    17 installation of potable water wells within the City
    18 of Chicago. There have been hundreds of sites that
    19 have relied on that groundwater ordinance and have
    20 not remediated groundwater, you know, to meet
    21 potable supplied uses.
    22
    What sense does it make to clean up
    23 the hole in the donut? I mean, one of the reasons
    24 why TACO was created was to provide a mechanism so
    Keefe Reporting Company
    (618) 244-0190

    103
    1 that you don't have to clean up the hole in the
    2 donut. Why do it if it's -- why spend the resources
    3 to clean up that hole in the donut if it doesn't
    4 make sense to do that?
    5
    Q I understand that, but the Agency is now
    6 encouraging the rest of the donut basically, using
    7 your terms -- I mean implementing more groundwater
    8 use ordinances within communities throughout
    9 Illinois.
    10
    And it's my understanding -- I may be
    11 misunderstanding. But through passage of the
    12 additional groundwater use ordinances, we're making
    13 that hole in the donut much bigger, is my
    14 understanding.
    15
    HEARING OFFICER TIPSORD: Mr. Goodeil, I
    16
    was going to say, you need to keep it in the
    17
    form of questions.
    18
    MR. KING: Yeah. I just want to make it
    19
    clear. We do not -- and we have made -- we
    20
    have made it very clear in numerous instances
    21
    that the decision to adopt a groundwater use
    22
    ordinance belongs to that municipality.
    23
    They're making the decision relative to the
    24
    groundwater use within their community and how
    Keefe Reporting Company
    (618) 244-0190

    104
    1
    much they're going to force sites within that
    2
    community to clean up relative to groundwater.
    3
    If a community does not want to have that
    4
    ordinance, and that is certainly our -- that is
    5
    certainly their option. Many communities have
    6
    seen that there was a benefit to having
    7
    projects move forward, be cleaned up, you know,
    8
    when they have that groundwater ordinance in
    9
    place.
    10
    HEARING OFFICER TIPSORD: I don't think
    11
    we're going to get done with the Agency. I
    12
    would hope we'd get done before lunch, but it's
    13
    now 12:15. We have been at it for about 2
    14
    hours and 15 minutes. So I think we need to go
    15
    ahead and take a lunch break. We'll break one
    16
    hour. We'll come back promptly in one hour and
    17
    continue with the Agency at that time. Thanks.
    18
    (Lunch break.)
    19
    HEARING OFFICER TIPSORD: Let's go ahead
    20
    and go back on the record.
    21
    Mr. Clay has indicated that they have a
    22
    response to, I think, Mr. Schumacher's
    23
    question. Go ahead, Mr. Clay.
    24
    MR. CLAY: Yeah. As we stated, there's
    Keefe Reporting Company
    (618) 244-0190

    105
    1
    canceled checks, a waiver or affidavit would be
    2
    acceptable to payment, but I mean, it's part of
    3
    the handling charge. In reading the definition
    4
    of handling charge, it's for interest. And so
    5
    it's presumed or expected that the prime would
    6
    pay their subcontractors, and reimbursement and
    7
    then get reimbursed from the Agency.
    8
    So I mean, that's, you know, like I said,
    9
    part of the -- in the definition of handling
    10
    charges interest.
    11
    MR. SCHUMACHER: Can I?
    12
    HEARING OFFICER TIPSORD: Sure. Do you
    13
    have a follow-up? Sure.
    14
    QUESTIONS BY MR. SCHUMACHER:
    15
    Q Even, say, we paid our subcontractors
    16 within 30 days. When I do the cleanup, I want to
    17 immediately submit the remediation and all the
    18 reimbursement. I don't want to wait 30 days to get
    19 a waiver of lien, you know, if I'm paying on that.
    20 Is there any way that I can go ahead and submit the
    21 claim, and is there any way that I -- say the
    22 comptroller is going to give us a check within, you
    23 know, we get the letter in a month and a half or two
    24 months, and then I have that time frame that before
    Keefe Reporting Company
    (618) 244-0190

    106
    1 I get paid, before the comptroller actually issues a
    2 check. Could I submit the waiver of liens?
    3 Because, say, you know, if it takes a hundred days
    4 to get paid, and I pay my subcontractor in 30 days
    5 or 60 days, and I can get the waiver of liens, I
    6 have that time frame to get that waiver of liens to
    7 the EPA or to somebody before the check is actually
    8 cut. That will at least show that, hey, I did pay
    9 all my subcontractor. Here's a waiver of lien.
    10 Because what I don't want to -- 30 days, I don't
    11 want to wait 30 more days to get in the line for
    12 reimbursement just for a waiver of lien.
    13
    Is there any way that we can submit
    14 them prior to getting a check? Like, would you
    15 normally do for a normal contract -- you submit your
    16 waiver of lien before the company pays you?
    17
    A Right. And I mean, basically you need to
    18 wait until you get a waiver of lien before you
    19 submit the bills. And I understand what you're
    20 saying.
    21
    But you've got to remember from the
    22 Agency's standpoint, we're dealing with thousands of
    23 these things. So you're talking another review now
    24 or at least a portion of a review to now you
    Keefe Reporting Company
    (618) 244-0190

    107
    1 submitted your waiver of liens, which you already
    2 reviewed the package and said, you know, you haven't
    3 paid your subcontractors, at least you haven't shown
    4 us that you paid your subcontractors.
    5
    And I mean, to be honest, one of the
    6 reasons this provision is in there is because we
    7 received complaints from subcontractors that said
    8 I'm not getting paid. And we said, well, let me
    9 look that up. And we looked it up and said, well,
    10 we paid the owner/operators three months ago. They
    11 are not paying the subcontractor.
    12
    Q That's not really the Agency's
    13 responsibility? It should be the contractors, it
    14 should be the consultant, it should be a contractor
    15 thing. You know, the subcontractor is not getting
    16 paid, the general, and you know, take legal action
    17 against that person. It's not --
    18
    A No, I disagree. I mean, we are to
    19 reimburse corrective action costs. If you haven't
    20 paid your sub, then you haven't incurred that cost.
    21 I mean, that's the way I look at it.
    22
    HEARING OFFICER TIPSORD: Okay.
    23
    24 QUESTIONS BY MR. COOK:
    Keefe Reporting Company
    (618) 244-0190

    108
    1
    Q You said you haven't incurred that cost.
    2 If I was audited, our books were audited, on an
    3 accrual basis, my auditors would say based on
    4 generally accepted accounting principles, that I
    5 hadn't incurred that cost. So when you make that
    6 statement or you just -- I just want a
    7 clarification. What's that based on? Is it based
    8 on GAP?
    9
    A Based on what?
    10
    Q GAP.
    11
    A I'm not familiar with that term.
    12
    Q Generally accepted accounting principles.
    13
    A Okay. It is based on the fact that you
    14 don't have anything that showed proof of payment
    15 that you're proposing, which is a canceled check, a
    16 waiver or an affidavit from your sub.
    17
    MR. COOK: All right.
    18
    HEARING OFFICER TIPSORD: Any other
    19
    questions? Ms. Manning?
    20
    MS. MANNING: I have a question for
    21
    Mr. King.
    22
    QUESTIONS BY MS. MANNING:
    23
    Q Gary, you indicated in your testimony that
    24 evidence of a continued confusion over Subpart H,
    Keefe Reporting Company
    (618) 244-0190

    109
    1 which you promised to set straight after these
    2 hearings. Could you just enlighten us now in terms
    3 of what area of confusion you think there still
    4 remains with your proposed Subpart H, and how it's
    5 going to work employed by the Agency?
    6
    A (By Mr. Clay) Yeah. I mean, one of the
    7 real confusions was that we identified -- and I
    8 think this was in talking with PIPE members and in
    9 talking with Dan Goodwin -- was there was some
    10 confusion on how long summons would work and how we
    11 would determine a maximum amount for that task
    12 actually works.
    13
    And if it's a lump sum of $2,000, for
    14 example, for consulting services, and the consultant
    15 submits an invoice that says $2,000 for a
    16 corrective -- well, let's use the real world
    17 example. Okay. 51 20 for a corrective action plan,
    18 which allows in Subpart H, the consultant submits an
    19 invoice that says 5120 preparation for corrective
    20 action plan. That's all we're looking for as far as
    21 the consultant services and showing that that cost
    22 was incurred. We would pay 5120. There would be no
    23 other documentation required. I mean, we want to
    24 know the dates when the work was done, and that's
    Keefe Reporting Company
    (618) 244-0190

    110
    1 probably it on that invoice. So there wouldn't be
    2 time sheets or anything like that required.
    3
    If the consultant would submit an
    4 invoice for $4,000, for preparation of corrective
    5 action plan, we would not reimburse them 5120. So
    6 the 5120 is a maximum. But if they ask for 5120 for
    7 that task, then we would reimburse that. We're not
    8 going to reimburse you for more than you ask for.
    9
    And I think that's what we want to
    10 clarify is how those lump sums and unit rates
    11 would -- what we would expect and how that would be
    12 paid.
    13
    Q So that's true of all the lump sum and
    14 unit rates from your perspective, that you don't go
    15 behind those once an invoice is submitted, saying
    16 that I've done that work?
    17
    A For subcontractors, you know, we have to
    18 have backup invoices for the subs.
    19
    For example, if we've got a drilling
    20 subcontractor, you know, we'd want to have $19 a
    21 foot, which is how many feet that were drilled, the
    22 dates. But that's what we would expect from the
    23 subcontractor. It would be from the consultant. We
    24 have to have that invoice from the sub. But, yeah,
    Keefe Reporting Company
    (618) 244-0190

    111
    1 for the lump sums and the unit rate, that's what we
    2 would expect.
    3
    MS. MANNING: Okay, thank you.
    4
    HEARING OFFICER TIPSORD: Anything else?
    5
    Okay. I have a few questions.
    6 BY HEARING OFFICER TIPSORD:
    7
    Q First of all, Mr. Clay, in your testimony
    8 on page 4 from this hearing, one of the comments
    9 that's made here is that the Agency believes there
    10 will be a significant savings in cleanup costs with
    11 the establishment of, quote, "reasonable costs,"
    12 unquote and regulations. And we've heard a lot of
    13 testimony about what's reasonable and all of that.
    14
    I guess my to-the-point question is,
    15 do you believe that's because you're reducing what's
    16 currently considered reasonable?
    17
    A (By Mr. Clay) I don't think it's reducing
    18 what's considered reasonable. I think it's a matter
    19 of what everybody considers reasonable as part of
    20 the rules.
    21
    I mean, for example, some of the
    22 examples I gave as far as what's being billed as
    23 reasonable and certified as reasonable, we felt were
    24 far from reasonable. And so I don't know that we're
    Keefe Reporting Company
    (618) 244-0190

    112
    1 reducing what's reasonable. I think it's just a
    2 matter of making sure that everybody knows up front
    3 what is reasonable.
    4
    And then as a result of that, I think
    5 there will be savings in report preparation, you
    6 know, re work. We said in past hearings that most
    7 of the denials are the result of budget issues as
    8 opposed to technical issues. So hopefully we'll
    9 avoid those having to be resubmitted.
    10
    Q That's actually my next question then. A
    11 list of unreasonable costs of the Agency deemed to
    12 be unreasonable, I am assuming that none of those
    13 costs were appealed to the Board? Or were those
    14 costs appealed to the Board?
    15
    A The examples?
    16
    Q Yes.
    17
    A I don't know. I think those were all
    18 within the last year, and some of them may have
    19 been -- we didn't look at whether or not they were
    20 appealed or not.
    21
    Q Could you check on that? I'd be
    22 interested to see if they were appealed and whether
    23 or not were affirmed. Or, you know, I think that's
    24 a significant issue. If you were not affirmed,
    Keefe Reporting Company
    (618) 244-0190

    113
    1 obviously the Board didn't agree with your summation
    2 that those were reasonable?
    3
    BOARD MEMBER JOHNSON: Those were all
    4
    denied, your list of unreasonable --
    5
    MR. CLAY: I think they were all denied,
    6
    yes.
    7
    The example that I gave where it was $32 a
    8
    foot for injection of the oxygenated compound,
    9
    they just resubmitted that at $16 a foot, and
    10
    we approved that. So that was one that was
    11
    resubmitted as opposed to, you know, gone to
    12
    something going to appeal, but we'll get back
    13
    on that.
    14
    Q (By Hearing Officer Tipsord) Okay. Then
    15 on -- I think it was page 7 -- no, 14. In
    16 discussion about PIPE's comments regarding sort of a
    17 draft denial or a draft decision by the Agency, you
    18 noted that -- and they analogized with the pertinent
    19 section, you say that the analogy to the permit
    20 review is not an appropriate unit. You talked to
    21 the permit section, and that a permit issue RCRA
    22 part B permits require draft to a final decision.
    23
    Again, I'm making -- I'm sure you'll
    24 correct me if I'm wrong. You talked to the land --
    Keefe Reporting Company
    (618) 244-0190

    114
    1
    A That's correct.
    2
    Q Are you aware of whether or not water and
    3 air permits --
    4
    A I believe they do. For example, their
    5 NPDS permits, they do draft permits.
    6
    HEARING OFFICER TIPSORD: Thank you. And
    7
    then in the rules, first of all, in this errata
    8
    sheet, given the size of the errata sheet, I'm
    9
    going to ask the same request of PIPE later on.
    10
    Could you provide that to us on disk?
    11
    MR. ROMINGER: Sure.
    12
    HEARING OFFICER TIPSORD: And particularly
    13
    on page 5 -- and this is also an issue that I
    14
    noticed that PIPE raised in their discussion.
    15
    But in the new language on page 5, the Agency
    16
    states, the Agency "may" allow. As you
    17
    probably are aware, JCAR is not fond of the use
    18
    of the word "may." So could we have some
    19
    further clarification? And I'm not even sure
    20
    that "may" is correct based on the testimony.
    21
    I think you're using it, as we may do this if
    22
    nothing else works, but you will do it in the
    23
    first sentence, doesn't happen.
    24
    BOARD MEMBER JOHNSON: 202?
    Keefe Reporting Company
    (618) 244-0190

    115
    1
    HEARING OFFICER TIPSORD: Yeah, page 5.
    2
    Could you just check on that? And we may need
    3
    some further clarification.
    4
    MR. CLAY: I think that's fine. We'll
    5
    allow alternative clarification.
    6
    MR. ROMINGER: Yeah. It intends them to
    7
    allow to use those provisions.
    8
    HEARING OFFICER TIPSORD: Yeah. Then on
    9
    page 38, and you talk about this again in your
    10
    testimony, about reviewing payment amounts and
    11
    that you'll periodically review and maybe
    12
    commit to changes. Would the Agency be willing
    13
    to commit to when they'll bring those -- you
    14
    know, if you decide changes are necessary for
    15
    Subpart H, how much time it will be before you
    16
    bring those to the Board?
    17
    I mean, like, if you do it every three
    18
    years, are you going to wait another three
    19
    years before you bring it to the Board? Would
    20
    you be willing to make a commitment to bring
    21
    those to the Board within a certain time frame
    22
    after that?
    23
    MR. CLAY: Can we look at that? And part
    24
    of it will be dependent upon how extensive they
    Keefe Reporting Company
    (618) 244-0190

    116
    1
    are. I mean, if it's one number. We wouldn't
    2
    want it to input from the community. So we'd
    3
    have to have time for that. But I mean, if
    4
    it's a couple numbers, it would obviously be
    5
    much easier to do very quickly as opposed to if
    6
    all the numbers are changing. But we'll
    7
    respond to that.
    8
    MR. ROMINGER: Yeah.
    9
    Q (By Hearing Officer Tipsord) Then sort of
    10 a general question -- and this is again going to the
    11 economics of the rule, we heard -- you gave us a lot
    12 of numbers today about the number of consultants,
    13 laboratories, etcetera, that are out there that are
    14 probably not members of PIPE.
    15
    My question sort of is, do you
    16 anticipate that these rules, as adopted, as you have
    17 proposed them in this errata sheet, will result in
    18 any potential businesses going out of business? Or
    19 I mean, do you have a feel for that?
    20
    MR. CLAY: We don't anticipate that.
    21
    HEARING OFFICER TIPSORD: Thank you. Are
    22
    there any other questions for Mr. Clay or the
    23
    Agency? Thank you very much.
    24
    We'll move on to PIPE then. Let's go off
    Keefe Reporting Company
    (618) 244-0190

    117
    1
    the record for just a second.
    2
    (Whereupon there was a short
    3
    discussion off the record.)
    4
    MS. MANNING: This is PIPE's response to
    5
    the testimony of Doug Clay that was prefiled,
    6
    and I'll be reading that today.
    7
    HEARING OFFICER TIPSORD: We're back on
    8
    the record.
    9
    MS. MANNING: Madam Hearing Officer,
    10
    should we mark both of these exhibits? Have
    11
    you done that already as exhibit --
    12
    HEARING OFFICER TIPSORD: Yeah. We'll
    13
    mark the filing from August 3rd, PIPE's
    14
    proposed alternative language as Exhibit 90 if
    15
    there's no objection.
    16
    MS. MANNING: And I would state that I
    17
    regret that I don't have copies of this
    18
    document today that we filed. So Exhibit 90?
    19
    HEARING OFFICER TIPSORD: Yes.
    20
    (Whereby, the Hearing Officer
    21
    marked Exhibit 90.)
    22
    MS. MANNING: And then I would offer then
    23
    as Exhibit 91 a document entitled PIPE
    24
    Testimony in Response to IEPA Testimony of
    Keefe Reporting Company
    (618) 244-0190

    118
    1
    August 9, 2004, and Third Errata Sheet PIPE
    2
    Testimony in Support of Alternate Language.
    3
    HEARING OFFICER TIPSORD: Any objection?
    4
    Seeing none, we'll mark that as Exhibit 91.
    5
    (Whereby, the Hearing Officer
    6
    marked Exhibit 91.)
    7
    (Witness was sworn.)
    8
    MS. MANNING: Madam Hearing Officer,
    9
    before I begin, too, I would like to suggest
    10
    that the legislative community of PIPE as well,
    11
    they may testify from time to time after I
    12
    respond to the Agency's comments. So perhaps
    13
    they ought to be sworn in as well.
    14
    HEARING OFFICER TIPSORD: Okay. Let's
    15
    swear you in.
    16
    MR. TRUESDALE: Joe Truesdale, CSD
    17
    Environmental.
    18
    MR. WEINHOFF: Jeff Weinhoff, CW3M.
    19
    MR. DOTY: Dwayne Doty, United Science
    20
    Industries.
    21
    (All were sworn.)
    22
    MS. MANNING: Thank you.
    23
    HEARING OFFICER TIPSORD: Go ahead.
    24
    MS. MANNING: First as a general matter,
    Keefe Reporting Company
    (618) 244-0190

    119
    1
    PIPE again very much appreciates and respects
    2
    this opportunity to address the Pollution
    3
    Control Board on this rule making with great
    4
    importance regarding the underground storage
    5
    tank rules.
    6
    Second, PIPE appreciates the changes to
    7
    the rule proposal that the Agency has submitted
    8
    in its third errata, and further thanks the
    9
    Agency for the many meetings we have had over
    10
    the course of this proceeding.
    11
    In large part, PIPE supports the offered
    12
    changes that are in the third errata sheet and
    13
    agrees that they are responsive to some of the
    14
    concerns raised by PIPE and other interested
    15
    groups that have met with the Agency over the
    16
    course of the last several months. Further,
    17
    the changes make the Agency's proposal more
    18
    palatable. Specifically, PIPE, although we had
    19
    questions about the proposed draft provisions
    20
    regarding bidding, generally the concept as
    21
    drafted by the Agency is something that PIPE
    22
    can rally around, and to a certain degree,
    23
    support. Also we support definitely the
    24
    concept of the UST advisory committee, and I'll
    Keefe Reporting Company
    (618) 244-0190

    120
    1
    talk about that in a little later fashion.
    2
    However, there are still some very
    3
    important issues that need yet to be addressed
    4
    by this Board. Those issues involve process
    5
    and procedure as well as cost designated for
    6
    reimbursement.
    7
    Regarding process, we do not share the
    8
    Agency's position that their proposal will
    9
    result in any efficiencies. That's "in any
    10
    efficiencies," not "inefficiencies."
    11
    Regarding costs, PIPE continues to believe
    12
    that the Agency's costs as set forth in Subpart
    13
    H are neither well defined nor well justified.
    14
    They are not well defined because they do not
    15
    define the work necessary for certain lump
    16
    sums. They are not justified because they are
    17
    not -- they are based on historical data as
    18
    determined appropriate by the Agency, and not
    19
    on any real or market based data criteria or
    20
    statistics.
    21
    Today 's PIPE testimony is broken into two
    22
    phases. First a response to the Agency's
    23
    prefiled testimony and third errata sheet.
    24
    And, second, our testimony in support of PIPE's
    Keefe Reporting Company
    (618) 244-0190

    121
    1
    alternate approach on the areas of substitute
    2
    disagreement that remain.
    3
    The following clarifications are required
    4
    and result directly from the prefiled testimony
    5
    filed by Doug Clay on behalf of the Agency.
    6
    First -- and this is a small matter,
    7
    meeting agendas. On page 3, Mr. Clay states
    8
    that PIPE prepared the agenda for the meetings,
    9
    and although the agenda reflected what we
    10
    intend to discuss, they do not necessarily
    11
    reflect what was actually discussed in our
    12
    meetings. A quick review of those agendas will
    13
    suggest that all of the issues set forth in
    14
    them are issues that PIPE has been concerned
    15
    about from the outset of these proceedings, as
    16
    the Board will recognize from the testimony of
    17
    past hearings. It is true the PIPE prepared
    18
    these agendas. It's also true that they
    19
    reflect PIPE's concerns. Some of those
    20
    concerns, admittedly, were discussed in more
    21
    detail than others.
    22
    For example, where the Agency made clear
    23
    its position at the outset in opposition to
    24
    certain items, such as procedural alternatives,
    Keefe Reporting Company
    (618) 244-0190

    122
    1
    database for collection of market data and cost
    2
    issues, there was very little discussion.
    3
    It was not PIPE's intention submitting
    4
    these agendas to show areas of disagreement, to
    5
    show areas of agreement -- excuse me. Just
    6
    areas of concern and discussion. Those areas
    7
    of concern and discussion are consistent with
    8
    our testimony throughout this Board proceeding.
    9
    Impetus for the rule making. In response
    10
    to Mr. Clay's assertion, which is found on page
    11
    3 of his prefiled testimony, item 2, he states
    12
    that, quote, "This rule making was initiated in
    13
    2002 in response to statutory changes passed
    14
    that year."
    15
    And, presumably, I guess, not because the
    16
    Agency saw the fund began to fail, PIPE asserts
    17
    the following: First, this rule making was not
    18
    filed with the Board for public hearing until
    19
    January 13, 2004, a full year and a half after
    20
    PA 92-0554 became law on June 24, 2002. While
    21
    the Agency did in fact at some point during
    22
    this period of time have meetings with the Ad
    23
    Hoc committee, which consists largely of those
    24
    individuals who appeared and offer testimony in
    Keefe Reporting Company
    (618) 244-0190

    123
    1
    this proceeding, namely Dan Goodwin and Cindy
    2
    Davis, the heart of the concerns raised by the
    3
    Ad Hoc committee at that time were not
    4
    addressed by the Agency before it filed this
    5
    rule and in large part remain unaddressed. And
    6
    for that, you can see the testimony in both Dan
    7
    Goodwin and Cindy Davis in this proceeding.
    8
    The entire testimony at hearing, as well
    9
    as Mr. Clay's very next point, item 3 on page
    10
    4, contradicts the idea that this rule is not
    11
    about controlling costs.
    12
    Mr. Clay is correct in asserting that the
    13
    transcript incorrectly captured Cindy Davis's
    14
    testimony when it reflected that she stated
    15
    that the Agency, during our meetings, told us
    16
    for the first time that they needed to save
    17
    $125 million from the fund. Cindy didn't say
    18
    125 million. She did say 25 million. And we
    19
    were told 25 million by the Agency during one
    20
    of our meetings. 25 million is the figure that
    21
    correctly references Ms. Davis's testimony.
    22
    Mr. Clay states that the $25 million
    23
    reduction figure is justified because, quote,
    24
    "Approximately 25 million more is being paid
    Keefe Reporting Company
    (618) 244-0190

    124
    1
    out of the fund each year than is coming in."
    2
    PIPE would like to point out that, first and
    3
    foremost, it supports the idea of ensuring that
    4
    the UST fund is used wisely -- excuse me -- for
    5
    its intended purpose. That intended purpose is
    6
    reimbursement for the remediation of
    7
    underground storage tank sites. However, with
    8
    the exception of FY 03, at least in the data
    9
    presented to us by the Agency, the cost of
    10
    reimbursement has not historically exceeded the
    11
    revenues the fund generates.
    12
    If the state's goal is cost control, which
    13
    the Agency at this stage is hard pressed to
    14
    deny, the Board and the Agency should look at
    15
    the costs of the state's implementation of the
    16
    program, rather than direct all of the focus of
    17
    this rule making to the unspoken and unproven
    18
    assertion that current costs of reimbursement
    19
    are unreasonable. Over the last three fiscal
    20
    years, the Agency's share of operational costs
    21
    from the fund has risen $200,000 to $400,000
    22
    per year, such that the 04 cost of
    23
    administering the Agency's LUST fund was almost
    24
    $4 million, which doesn't include the money
    Keefe Reporting Company
    (618) 244-0190

    125
    1
    that the Agency utilized from the USEPA for the
    2
    administration of the program. As the Board
    3
    well knows, $4 million exceeds the entire
    4
    annual appropriation for the Board's own
    5
    operations.
    6
    Various other states, like Wisconsin,
    7
    administer their entire UST program with
    8
    federal USEPA dollars alone and do not even tap
    9
    into the state's own UST fund for the
    10
    administration of the program.
    11
    And on that note, I would suggest that the
    12
    Agency put a lot of the states other laws in
    13
    and talk directly just about the costs of those
    14
    other laws. But I would direct the Board's
    15
    attention to look carefully at those laws,
    16
    because a lot of things that PIPE is talking
    17
    about in this proceeding are in fact covered in
    18
    those laws.
    19
    Things like escape clauses, the 800 -- the
    20
    855 rule now, 860, 732.855, 732.860, those are
    21
    included in most of the state's provisions,
    22
    escape clauses like that, as well as most of
    23
    those other states have some sort of scope of
    24
    work provisions, so that when there is a lump
    Keefe Reporting Company
    (618) 244-0190

    126
    1
    sum attached to a specific job, the job is more
    2
    clearly delineated than in this proposal, and
    3
    I'll get to that later.
    4
    The Agency has not suggested what its
    5
    proposal will actually say or how much it will
    6
    cost. Mr. Clay's testimony admits that the
    7
    Agency has not performed the formal economic
    8
    analysis to determine, in specific dollars, the
    9
    savings that will be generated by its proposal.
    10
    The Agency's expectation of savings is
    11
    bolstered only by its presumption that it is
    12
    establishing, quote, "reasonable costs." Yet
    13
    those costs have not been derived from any
    14
    scientifically sound method or from any
    15
    reliable market place data. The Agency's
    16
    presumptions need to be closely examined by the
    17
    Board.
    18
    Further, the Agency's focus in this rule
    19
    making was not in the least focused on the
    20
    great number of sites that have yet to be
    21
    remediated in Illinois. Indeed, it was PIPE
    22
    who put forth data concerning the great number
    23
    of sites that remain inactive. There was no
    24
    great concern expressed as to why 5,000 sites
    Keefe Reporting Company
    (618) 244-0190

    127
    1
    still await remediation. Indeed, if the UST
    2
    remediation business were as lucrative as the
    3
    Agency would like to have the Board believe,
    4
    one might wonder why this great number of sites
    5
    remains inactive. Based upon these statistics,
    6
    one might wonder why the EPA is not actively
    7
    encouraging businesses like those in PIPE who
    8
    are engaged in remediation to double their
    9
    efforts, instead of discouraging them from
    10
    doing so by squeezing them out of their
    11
    remediation business by setting the costs based
    12
    on the Agency's selective and dated historical
    13
    data.
    14
    Time to review claims. On page 5, item 5,
    15
    the Agency declares the testimony of interim
    16
    PIPE president, Cindy Davis, inaccurate. This
    17
    Agency testimony has caused PIPE to reevaluate
    18
    our testimony on time frames. And,
    19
    accordingly, we have researched all of the data
    20
    available on the Agency's Web site regarding
    21
    this, and indeed, Mr. Clay is correct. That
    22
    the Agency's time frame for issuing each of its
    23
    various decisions averages much less than a
    24
    hundred and twenty days.
    Keefe Reporting Company
    (618) 244-0190

    128
    1
    Further, the Agency has averaged much less
    2
    time for decision making FY 04 than it did in
    3
    FY 03. The Agency is indeed making substantial
    4
    improvements in these time frames. And clearly
    5
    the data suggests, however, that a hundred and
    6
    twenty day wait for a decision is now out of
    7
    the norm.
    8
    However, and importantly, Cindy Davis was
    9
    also correct, at least in terms of her
    10
    experience with her company. The data
    11
    regarding her company, CSD Environmental, bears
    12
    out her testimony. The average time it takes
    13
    for the Agency to issue a decision on a project
    14
    involving her company is 119.86 days, which
    15
    Ms. Davis now recognizes is well outside the
    16
    norm. Indeed, the next closest average,
    17
    considering only those companies whose
    18
    remediation decisions constitute more than
    19
    1 percent of the overall Agency decisions, is
    20
    94.26 days. Indeed, out of 3,353 decisions
    21
    reviewed, the average Agency time to respond
    22
    has been 67.84 days. Also, the data easily
    23
    demonstrates that the time frame began to
    24
    shorten considerably after the Board's decision
    Keefe Reporting Company
    (618) 244-0190

    129
    1
    in Ayers.
    2
    Ms. Davis is correct on another point as
    3
    well. And from the start of the UST project to
    4
    final reimbursement, regardless of the time
    5
    frame it takes to issue individual decisions of
    6
    the Agency, it takes a very long time to get
    7
    that. The statistics above -- excuse me,
    8
    include each and every decision the Agency
    9
    makes in the UST program. The Board must bear
    10
    in mind that there are so many of these
    11
    decisional steps that the actual time frame
    12
    from start to finish; that is, from budget to
    13
    final reimbursement, must consider a number of
    14
    them added together. For that time frame,
    15
    there are no statistics.
    16
    The Agency further states that since the
    17
    Act provides it with 120 days to respond to
    18
    submittals, any change to that time frame would
    19
    need to be a statutory change, and reduction in
    20
    this time frame would impact the Agency's
    21
    administration of the LUST program.
    22
    And indeed, this morning Gary King
    23
    indicated that our proposal is inconsistent
    24
    with state law, and we'll get into that later,
    Keefe Reporting Company
    (618) 244-0190

    130
    1
    because I disagree with him in terms of any
    2
    PIPE's proposals being challenged under state
    3
    law. That the statute allows for a 120-day
    4
    response period does not require the Agency to
    5
    take a 120-day response period for each and
    6
    every decision.
    7
    Further, since the Agency does indeed
    8
    issue most of its decisions in a time frame
    9
    that's actually closer to 60 days, the Agency's
    10
    continued reluctance to at least consider some
    11
    of its decisional -- to at least consider the
    12
    reduction of some of these time frames is
    13
    perplexing, particularly when it asserts that
    14
    this rule is going to allow for more efficient
    15
    administration and processing.
    16
    On page 6, item 5, regarding extension of
    17
    the 120-day time frame if more information is
    18
    sought, Mr. Clay asserts, quote, "In some
    19
    cases, additional information that is needed
    20
    can be submitted within the 120-day time frame,
    21
    and the submittal can be approved."
    22
    First, the Board needs to ask the
    23
    questions Hearing Officer Tipsord was asking
    24
    earlier in terms of tying the language down in
    Keefe Reporting Company
    (618) 244-0190

    131
    1
    this rule making. The Board needs to ask what
    2
    cases and under what circumstances, ie who gets
    3
    to ask -- who gets asked to provide additional
    4
    information and who doesn't.
    5
    It has not generally been the experience
    6
    of the members of PIPE that the Agency calls
    7
    and asks for more information. The opposite in
    8
    fact has been the practice. The Agency does
    9
    not generally solicit information, and
    10
    generally it provides no information regarding
    11
    the reasons for rejection or modification
    12
    beyond the standard and vague phraseology
    13
    "exceeds the minimum requirements of the Act."
    14
    Given the Agency's assertion, one must
    15
    question why would they continue to have such a
    16
    problem with tying these principles down, in
    17
    the manner provided in PIPE's alternative
    18
    language. Similarly, the Board should ask the
    19
    Agency questions like the amount of time it
    20
    takes the Agency to approve a plan or report is
    21
    largely dependent upon the quality of the
    22
    submittal, and that has not been in all of
    23
    PIPE's members' perspective as well.
    24
    The next item that Doug talked about is
    Keefe Reporting Company
    (618) 244-0190

    132
    1
    PIPE itself being a vocal minority. And it
    2
    challenges -- he challenged in his testimony
    3
    again that PIPE would not identify its members
    4
    and could not provide a breakdown of how many
    5
    members represented each of the different types
    6
    of businesses involved in the remediation of
    7
    LUST sites.
    8
    He then gave various statistics -- the
    9
    Agency did -- in terms of putting everything
    10
    into perspective, and offered without
    11
    suggesting names, that there were numerous
    12
    silent consultants out there who were perfectly
    13
    happy with Subpart H. Hopefully, PIPE expects
    14
    that the Board is not going to be swayed by any
    15
    assertions by the silent people out there who
    16
    are not speaking to the Board in this
    17
    proceeding. If other companies or associations
    18
    have something to say in this rule making, they
    19
    can and should do it.
    20
    Rather, given the context of Ayers and
    21
    other litigation concerning the rate sheet, the
    22
    Agency's continued focus on who the members of
    23
    PIPE are breeds suspicion, if you would, within
    24
    the members of PIPE. And as everyone knows
    Keefe Reporting Company
    (618) 244-0190

    133
    1
    here, PIPE was born out of this rule making.
    2
    While PIPE very respectfully recognizes the
    3
    Board's admonition at hearing -- Member
    4
    Girard's -- that failure to disclose its
    5
    membership may weaken its credibility, and
    6
    we've discussed your concern.
    7
    It's evident from this proceeding that
    8
    this whole side of the room are members of PIPE
    9
    for the most part. We can identify everybody.
    10
    And there's a board staffer. And Dan is not.
    11
    But PIPE is well represented. It's a new
    12
    association that has worked quite positively
    13
    with the Agency.
    14
    I don't mean my comments here today to be
    15
    disingenuous. I do want the Board to know how
    16
    serious the members of PIPE are, however.
    17
    The following rather prominent and engaged
    18
    Illinois associations have happily worked side
    19
    by side with PIPE. In addition to the Agency,
    20
    the ACEC, the ISPE and the IPMA. Indeed,
    21
    PIPE's birth was envisioned and inspired by
    22
    IPMA.
    23
    And to the extent of the question of whose
    24
    interests PIPE represents continues to be
    Keefe Reporting Company
    (618) 244-0190

    134
    1
    relevant to the Board, I'm going to offer you
    2
    the following:
    3
    There are 10,000 UST sites in Illinois
    4
    that have yet to be remediated. And PIPE is an
    5
    association of various established and viable
    6
    companies. Oftentimes we're direct competitors
    7
    in this business. They're in a position to and
    8
    are very competent to, as you can tell from
    9
    their testimony and their questions, to
    10
    remediate those 5,000 sites that remain to be
    11
    remediated in the State of Illinois. PIPE has
    12
    members, companies who are more tangentially
    13
    involved in the UST remediation, such as
    14
    laboratories, landfills and drillers.
    15
    I think in Doug's testimony, he said there
    16
    were 48 landfills. We don't have 48 landfills
    17
    as our members, but as you all know, one
    18
    landfill company, you know, might have several
    19
    landfills. So numbers aren't necessarily
    20
    driving the concerns of this rule making.
    21
    While the Agency alerts that there are a
    22
    number of companies who perform LUST
    23
    remediation in Illinois -- and they are
    24
    correct -- the Agency very much realizes that
    Keefe Reporting Company
    (618) 244-0190

    135
    1
    the companies who have been active in PIPE at
    2
    these hearings have the greatest market share
    3
    of that business, especially when you're
    4
    considering how it relates to the gas station
    5
    owner and operator with the retail gas station
    6
    owner and operators, and those that are not
    7
    owned by the large oil companies. Given that
    8
    these smaller owners and operators are the
    9
    ones, especially in downstate Illinois, who
    10
    risk the most harm from this rule making, it
    11
    should be no surprise that the consults and
    12
    businesses who are in a position to
    13
    successfully remediate these properties are the
    14
    ones that are the most active in this hearing.
    15
    PIPE suggests, again, that the Agency
    16
    ought to be encouraging businesses like those
    17
    in PIPE who can remediate these remaining
    18
    properties. The rule making ought to consider
    19
    the importance to Illinois of the viability of
    20
    these companies.
    21
    Thankfully, Doug's testimony finally
    22
    speaks of market factors, as PIPE has
    23
    encouraged all along. However, he does not do
    24
    so as support for the numbers that have been
    Keefe Reporting Company
    (618) 244-0190

    136
    1
    presented in rule making, the rates proposed,
    2
    because they're not based on real market data,
    3
    but instead in support of the competitive
    4
    bidding proposal, which as stated earlier, PIPE
    5
    supports as it's written.
    6
    Scope of work. The Agency's description
    7
    of scope of work speaks volumes about the
    8
    differences of opinion that remain between the
    9
    Agency and the participants in this making.
    10
    Quote, "The scope of work is the work required
    11
    to perform the task being reimbursed; preparing
    12
    and submitting a plan, preparing or submitting
    13
    a report." State job descriptions are
    14
    generally more comprehensive than the Agency's
    15
    description of what they consider to be the
    16
    scope of work on a UST project.
    17
    Payment for environmental services
    18
    requires a flexible reimbursement procedure
    19
    that varies according to the degree of
    20
    difficulty in the project. The Agency has
    21
    proposed to divide the payment of services for
    22
    the consultants into two types of
    23
    payments -- time and material, and lump sum or
    24
    fixed fee. PIPE agrees that dividing payments
    Keefe Reporting Company
    (618) 244-0190

    137
    1
    into these two types is appropriate, depending
    2
    on the specifics of the tasks and the magnitude
    3
    of the unknowns. Time and material pricing
    4
    works best when the technical and financial
    5
    risks and unknowns are large.
    6
    As many authorities recognize -- and I'm
    7
    not going to read all of that, but the bottom
    8
    line is, is it's a quote from the Environmental
    9
    Business Committee White Paper Performance
    10
    Based Contracting. And it basically -- the key
    11
    phrase here is that unfortunately many key
    12
    government decision makers seem to share belief
    13
    that a fixed price guarantees delivery of a
    14
    product -- or a project for a fixed price.
    15
    This is not a valid notion, because change
    16
    orders and large contingency fees are then
    17
    needed to protect against unanticipated site
    18
    conditions or technology performance. By
    19
    utilizing time, material contract when the
    20
    risks or unknowns are great, and then applying
    21
    lump sum or fixed fee price contracts to
    22
    discrete, well defined tasks with small
    23
    unknowns, efficiency gains and cost savings can
    24
    be realized.
    Keefe Reporting Company
    (618) 244-0190

    138
    1
    The Agency does not believe that a
    2
    detailed, defined scope of work for every
    3
    aspect of the leaking underground storage tank
    4
    is necessary. PIPE is not requesting a defined
    5
    scope of work be prepared for every aspect of
    6
    the leaking underground storage tank site.
    7
    However, PIPE requests a defined scope of work
    8
    be prepared for those services that will be
    9
    paid for on a lump sum or a fixed fee basis.
    10
    In the next part, we explain the concept behind
    11
    a proposed sub appendix G, which we'll pass
    12
    around in a while.
    13
    We've drafted Appendix G. And it says,
    14
    "which provides a scope of work for the
    15
    services for which PIPE has identified as a
    16
    commodity type where the tasks are well defined
    17
    with relatively small risks and unknowns." The
    18
    intent of the scope of work is to identify all
    19
    of those tasks that are needed to prepare these
    20
    reports or services and to establish a standard
    21
    of review. It is our hope that the scope of
    22
    work will eliminate arguments of what items and
    23
    services are to be provided for the lump sum or
    24
    fixed fee. Without a clear defined scope of
    Keefe Reporting Company
    (618) 244-0190

    139
    1
    work, the Agency and the consulting engineer
    2
    may have differing opinions of what work is
    3
    required to be performed, ultimately increasing
    4
    the need for appeals. In the event the Agency
    5
    reviewer decides the site warrants additional
    6
    information beyond the scope, the consulting
    7
    engineer should be paid on a time and material
    8
    basis to provide the site-specific information.
    9
    Mr. Clay has voiced concerns to PIPE that
    10
    if the rules were to list the services to be
    11
    provided, and it was not an inclusive list, the
    12
    consulting engineer would be requesting
    13
    additional pay. However, it is unfair to the
    14
    consulting engineer when the profitability of
    15
    their firm is to provide these services is at
    16
    risk.
    17
    The best option would be to work together
    18
    and develop an all-inclusive list to be
    19
    included in the Board's regulations, which
    20
    allows all the players to know the rules of the
    21
    game. PIPE also agrees that a method needs to
    22
    be established to allow additional services to
    23
    be included on the scope of work if it's
    24
    determined the service was left off in error.
    Keefe Reporting Company
    (618) 244-0190

    140
    1
    Swell Factor and Conversion Factors. I'm
    2
    going to allow for testimony in terms of the
    3
    technical to you guys. I'm going to let you
    4
    handle that.
    5
    TACO tools and entry back into the fund
    6
    after an NFR letter. Regarding this issue,
    7
    PIPE responds that forcing a TACO based cleanup
    8
    affects the freedom of choices available to the
    9
    owners and operators who hire PIPE members, and
    10
    accordingly, we defer to IPMA and the position
    11
    of owners and operators of this issue.
    12
    However, PIPE does have some serious
    13
    concerns with the Agency's objection to allow
    14
    owners and operators back into the fund when an
    15
    unforeseen problem has been discovered after an
    16
    NFR letter is issued following a TACO based
    17
    cleanup.
    18
    The Agency used PIPE's own data, which
    19
    demonstrates that some owners and operators
    20
    already used TACO, to suggest that since there
    21
    was already a comfort level, there should
    22
    therefore be a mandate. Yet the Agency has
    23
    known from our discussions that owners and
    24
    operators will not accept a TACO mandate until
    Keefe Reporting Company
    (618) 244-0190

    141
    1
    they are guaranteed to get back into the fund,
    2
    if need be, after an NFR letter is issued.
    3
    Thus, the idea of allowing these items to
    4
    be reimbursed following an NFR is not to make
    5
    owners and operators more comfortable with TACO
    6
    regulations, but to increase their willingness
    7
    to utilize the tools that TACO provides. The
    8
    Agency's position on this issue, that being not
    9
    being able to get into the NFR again if there's
    10
    a problem of award, is shortsighted. If the
    11
    Agency wants to realize the cost savings that
    12
    TACO will provide, it ought to seriously
    13
    consider a vehicle for allowing an NFR to be
    14
    reopened under certain special circumstances,
    15
    as already is the case with MTBE contamination.
    16
    The UST fund is, after all, a fund that is
    17
    designed to fully insure against contamination
    18
    from leaking underground storage tanks.
    19
    On a final note regarding this issue, the
    20
    Agency suggests that allowing for a reopening
    21
    of an NFR letter, even under special
    22
    circumstances, would make it even harder to get
    23
    a handle on the fund's outstanding liability.
    24
    And on this note, we would suggest that we
    Keefe Reporting Company
    (618) 244-0190

    142
    1
    appreciate whatever desire the Agency has to
    2
    get a handle on the fund's outstanding
    3
    liability. The TACO issue shouldn't hold
    4
    anybody up, on the TACO issue as well.
    5
    And the next issue that I'm going to talk
    6
    about is the professional technical
    7
    certification and Title 16.
    8
    In Item 12, the Agency's proposal, the
    9
    Agency presents testimony for the first time
    10
    that suggests putting the LPE or LPG
    11
    certification in the Act. The legislature only
    12
    intended for oversight of site investigation
    13
    and corrective action by that professional.
    14
    The testimony misses the mark and shouldn't
    15
    really sway the Board. PIPE has never
    16
    suggested that the Agency should rely solely on
    17
    an LPE or LPG certification. We've never
    18
    suggested that. As the Board knows, when the
    19
    legislature required an LPE, later an LPG,
    20
    certification, the theory was that the licensed
    21
    professional would certify to the propriety,
    22
    from a technical perspective, of the decisions
    23
    that were made at the site concerning cleanup.
    24
    In large part, this is to justify that the work
    Keefe Reporting Company
    (618) 244-0190

    143
    1
    that was done was necessary for the site
    2
    remediation. That is, in fact, the issue here,
    3
    by the way.
    4
    The question is, how many soil borings
    5
    were necessary. The provision also was
    6
    necessary because the Agency itself does not
    7
    oversee UST remediation from a technical
    8
    perspective, as it does in other programs, but,
    9
    rather, its oversight is limited to an on-paper
    10
    fiscal review.
    11
    The point PIPE makes is an absolutely
    12
    valid one, which should be folded into these
    13
    rules by the Board. That point is that where
    14
    there is room, and need, for technical judgment
    15
    regarding how a UST site is cleaned up, the
    16
    Agency ought to defer to the judgment of the
    17
    professional who has signed the certification,
    18
    as opposed to Agency reviewer who oftentimes
    19
    lacks technical training and is only trained
    20
    really in the Agency's standards of fiscal
    21
    review. The UST program needs to quit mixing
    22
    apples and oranges, apples being technical
    23
    questions, and oranges being fiscal questions.
    24
    Further, the Agency's citation to 57.7(f),
    Keefe Reporting Company
    (618) 244-0190

    144
    1
    as being the alleged sole provision regarding
    2
    LPE and LPG certification, brings up a very
    3
    interesting statutory question, which I
    4
    understand the Board already knows anyway in
    5
    terms of the various conflicting statutes which
    6
    make up Section 57.7 and are contained in Title
    7
    16.
    8
    As you know, in 2002, Title 16 was the
    9
    subject of conflicting amendments in four
    10
    different bills, each of which became public
    11
    law. I am not going to read them all, but the
    12
    Board should know that they're very
    13
    conflicting. And the problem is that the
    14
    latter two Acts, which were the LPE and LPG
    15
    certification and their revision act actually
    16
    were passed before the site classification
    17
    bill, but did not become law until after such
    18
    bill. Thus, the amendments that were
    19
    contemplated and made law in the newer law in
    20
    reality amended the old new law.
    21
    Even in reviewing the Illinois Compiled
    22
    Statutes of 2002, they present four different
    23
    versions of Section 57.7. They also point the
    24
    reader to Section to 5 ILCS 70/6, which
    Keefe Reporting Company
    (618) 244-0190

    145
    1
    indicates how conflicting statutes are to be
    2
    interpreted.
    3
    Basically, the provision requires that,
    4
    where possible, the laws, quote, "shall be
    5
    construed together in such a manner as to give
    6
    full effect to each act, except in the case of
    7
    irreconcilable conflict." The provision
    8
    further states that an irreconcilable conflict
    9
    between two or more acts which amend the same
    10
    section of an act exists only if the amendatory
    11
    acts make inconsistent changes in the section
    12
    as it therefore existed.
    13
    Certainly, regarding the professional
    14
    certification clauses, there is no obvious
    15
    intention by virtue of the passage of what is
    16
    now 57.7(f) to limit the provisions that the
    17
    legislature passed regarding LPEs and LPGs in
    18
    the context of 92-735. The Agency's original
    19
    filing in this matter merely cites 92-554 and
    20
    92-735 as the rule's impetus, but does not
    21
    necessary either shed further light on the
    22
    statutory quagmire.
    23
    The Board simply -- the only reason I'm
    24
    saying this is, the Board really needs to be
    Keefe Reporting Company
    (618) 244-0190

    146
    1
    careful in dealing with these provisions in
    2
    terms of how it interprets the Act when they're
    3
    conflicting.
    4
    On a final note on this particular issue,
    5
    the Agency continues to obfuscate the point
    6
    PIPE attempts to make regarding professional
    7
    certification. Instead, it talks about its
    8
    greater authority to ensure reimbursement costs
    9
    are reasonable and promises to provide the
    10
    Board with examples of how it has received
    11
    professional certifications that have
    12
    constituted inaccurate or improper
    13
    certifications.
    14
    Doug went through a list of them this
    15
    morning. As PIPE has told the Agency a number
    16
    of different times, we hope that they denied
    17
    all of those claims. That's their job. We
    18
    would hope they do it. In fact, PIPE pointed
    19
    out to the Agency that it has the authority
    20
    under the statute already to go after any
    21
    fraudulent contractors. This rule making is
    22
    not about fraudulent contractors.
    23
    Database and electronic improvements for
    24
    the LUST program. The Agency's response to the
    Keefe Reporting Company
    (618) 244-0190

    147
    1
    participants' suggestion of a database for the
    2
    collection of market data is, while not
    3
    unexpected, is perplexing. Certainly, with all
    4
    the resources of the fund that are available to
    5
    the Agency, it is in a position to consider the
    6
    benefits that electronic efficiencies will
    7
    offer them -- electronic filing, electronic
    8
    data collection. Instead, the Agency continues
    9
    to deem the very suggestion of electronic
    10
    efficiencies as a, quote -- and this is the
    11
    quote from the testimony -- "a mandated
    12
    burdensome and time-consuming data collection
    13
    effort which sends the LUST program in the
    14
    wrong direction."
    15
    We couldn't disagree more. Time and
    16
    again, government and businesses have
    17
    benefitted from electronic efficiencies and
    18
    data collection. It is fairly well-established
    19
    business fact that, generally, electronic
    20
    efficiencies reduce work; they do not create
    21
    more of it.
    22
    Indeed, the Agency's position on this
    23
    issue is in direct conflict with its position
    24
    that its rule proposal is intended to create
    Keefe Reporting Company
    (618) 244-0190

    148
    1
    efficiencies. If this rule proposal is going
    2
    to work as well as the Agency expects,
    3
    basically if the costs are within Subpart H are
    4
    good to go, there is absolutely no reason why
    5
    not to design an electronic filing form and
    6
    database which processes claims in record time.
    7
    UST Advisory Committee and proposed
    8
    process changes. The Agency's comments
    9
    regarding PIPE's proposal, items 14, 15 and
    10
    17 -- actually, I'm here to answer any
    11
    questions about them when we get into the
    12
    testimony about our proposal.
    13
    We appreciate and support the Agency's
    14
    proposal of the UST Advisory Committee, which
    15
    is in item 14. And certainly that committee
    16
    will identify problems. But unfortunately,
    17
    simply a UST advisory committee is not going to
    18
    solve any problems, and they're certainly not
    19
    going to solve problems immediately. The time
    20
    for some of these solutions and some of these
    21
    issues to be addressed and raised and finally
    22
    disposed of is now, while the Agency is before
    23
    the Pollution Control Board.
    24
    Average costs of remediation per site. In
    Keefe Reporting Company
    (618) 244-0190

    149
    1
    response to item 17, which delineates the
    2
    average cost of remediating sites from 1997 to
    3
    2001, PIPE fails to understand the Agency's
    4
    following point: And this is the point they
    5
    make. The Agency did not include incidents
    6
    closed in later years because it assumes that
    7
    many claims related to those sites have yet to
    8
    be submitted. Actually, as PIPE has indicated
    9
    in testimony exhibits, many of those sites,
    10
    even the 1997 to 2001 data, are actually sites
    11
    that were opened in the years delineated in the
    12
    Agency's chart, but haven't been closed yet
    13
    either.
    14
    PIPE asserts that the more logical reason
    15
    for the omission of the 2002, 2003 and 2004
    16
    data is that it is not supportive of the
    17
    Agency's position. Certainly, over the course
    18
    of the years, one would expect that average
    19
    costs would rise. If they have not, it's
    20
    likely due to the fact that in some years,
    21
    there may have been more complicated cleanups
    22
    than in other years.
    23
    As various members of PIPE have testified
    24
    in this proceeding, there are currently some
    Keefe Reporting Company
    (618) 244-0190

    150
    1
    very complicated cleanups underway. The Board
    2
    should not be swayed by the Agency's continued
    3
    use of old data to support real time figures.
    4
    The rate sheet. In item 18, the Agency
    5
    asserts that, quote, "There appears to be some
    6
    confusion regarding the Agency's use of the
    7
    rate sheet." We're no longer confused. The
    8
    Agency utilized rate sheets, for various
    9
    purposes, at various times, based upon rates
    10
    deemed appropriate by select Agency employees
    11
    looking at select files of select costs. In
    12
    large part, the numbers brought to the Board in
    13
    this rule making are based upon those select
    14
    costs.
    15
    Proof of payment for subcontractors. In
    16
    item 19, the Agency is requesting the proof of
    17
    payment to subcontractors be included in the
    18
    application for payment. Mr. Clay states the
    19
    proof of payment to the subcontractor is
    20
    necessary to show that the subcontractor was
    21
    paid, and therefore the owner or operator is
    22
    entitled to reimbursement of handling charges.
    23
    The definition of handling charges is defined
    24
    in the proposed amendments to 35 Illinois
    Keefe Reporting Company
    (618) 244-0190

    151
    1
    Administrative Code, Part 734, Section 735.115.
    2
    And that definition is administrative,
    3
    insurance and interest costs and a reasonable
    4
    profit for procurement, oversight and payment
    5
    of subcontractors -- subcontracts and field
    6
    purchases.
    7
    According to the definition, handling
    8
    charges are due to the owner and operator
    9
    regardless of whether he paid the subcontractor
    10
    at the time of services or if the subcontractor
    11
    agreed to wait until the owner and operator
    12
    received payment from the LUST fund.
    13
    Obviously, from question and answers
    14
    earlier today, it's not the Agency's intention
    15
    to indicate whether the contractor paid the
    16
    subcontractor. And to wait for that payment,
    17
    they expect that there has to be proof of
    18
    payment before they will pay the contractor for
    19
    any of the subcontractor costs. Even if the
    20
    subcontractor agreed to wait for payment, the
    21
    prime contractor bore the cost of insurance,
    22
    administration, and is entitled to a reasonable
    23
    profit for the procurement and oversight of
    24
    subcontracts. It is unfair to the prime
    Keefe Reporting Company
    (618) 244-0190

    152
    1
    contractor to deny a handling charge if the
    2
    subcontractor agreed to wait for payment.
    3
    For essentially the same reasons, PIPE
    4
    proposes that Section 734.630, double zero, be
    5
    removed. Even if the prime contractor has a
    6
    financial interest in the subcontractor, the
    7
    prime still bears a cost of insurance,
    8
    administration, etcetera. There's nothing
    9
    untoward in this relationship. It's a typical
    10
    business relationship.
    11
    Drilling beyond stage three. In item 20,
    12
    the Agency squarely presents the dilemma a
    13
    consultant faces when he has to perform work
    14
    not necessarily contemplated in the four
    15
    corners of the rules.
    16
    Mr. Clay explains that, if someone has to
    17
    drill beyond stage three, he could do so
    18
    without approval, because he now will know,
    19
    with certainty, what he will be paid for the
    20
    drilling.
    21
    What we've all come to realize that
    22
    there's this disconnect in this proceeding.
    23
    However, is that the concern is not with what
    24
    the cost of drilling will be, but whether the
    Keefe Reporting Company
    (618) 244-0190

    153
    1
    Agency is going to approve the drilling at all.
    2
    The Agency has shown no propensity to defer to
    3
    the judgment of a licensed professional as to
    4
    whether any work will be necessary or whether
    5
    that particular work was necessary, and the
    6
    Agency has shown every propensity to deny costs
    7
    if the work performed, that contractor
    8
    performed, was what the Agency deems, without a
    9
    technical review, excessive. The mantra being,
    10
    "exceeds the minimum requirements of the Act."
    11
    If the Agency intends to streamline, they
    12
    should allow an expedited method of getting
    13
    approval in this situation, or other "out of
    14
    the box" atypical situations. They should also
    15
    exhibit a willingness to define a particular
    16
    scope of work.
    17
    IDOT excavation, transportation, disposal
    18
    costs. In item 22, the Agency claims it has
    19
    been in contact with IDOT. And, in fact,
    20
    putting the letter into evidence today -- and I
    21
    have had an opportunity to read it. And it
    22
    doesn't deny that PIPE's testimony that the
    23
    average cost that IDOT pays contractors
    24
    for -- the particular cost is 99.75. The
    Keefe Reporting Company
    (618) 244-0190

    154
    1
    Agency proposes 57. But they claim a
    2
    distinction because of the way IDOT reviews
    3
    bids and awards contracts. And I continue and
    4
    I think PIPE continues to fail to understand
    5
    the distinction.
    6
    The fact of the matter is, when reviewing
    7
    the IDOT contracts, that is the average cost of
    8
    that particular piece of work.
    9
    At this time, Madam Hearing Officer, I'm
    10
    concluding my remarks, at least that are
    11
    directly in response to the Agency's remarks
    12
    and the errata sheet.
    13
    In large part, as I indicated, we're
    14
    supportive of all of the Agency's comments in
    15
    the errata sheet and the movement they've made
    16
    in the errata sheet, but we believe that
    17
    there's a lot of substantive issues that
    18
    remain. And I'm willing to go on and talk
    19
    about what it is that PIPE is proposing, unless
    20
    anybody wants to ask any questions at this
    21
    point.
    22
    HEARING OFFICER TIPSORD: Let's go ahead
    23
    and proceed with your testimony, and we'll take
    24
    questions.
    Keefe Reporting Company
    (618) 244-0190

    155
    1
    MS. MANNING: Okay. If I might just add,
    2
    that our proposals really are, from our
    3
    perspective, while some of the issues are in
    4
    direct conflict with the Agency's issues in
    5
    terms of scope of work, in terms of potential
    6
    cost and in terms of procedures, by and large,
    7
    we've been able to work out a lot of the other
    8
    issues.
    9
    One of the issues we would suggest the
    10
    Board look at -- and we didn't -- and I know
    11
    other people have testified. I think David
    12
    Reeser (sp) maybe at the first hearing that the
    13
    Board had in this matter, is to look at the
    14
    idea of merging Part 732 and Part 734. Having
    15
    both parts is going to be very complicated for
    16
    the regulating community, in that every time
    17
    somebody is operating under one or the other,
    18
    every time, you know, it's changed, you'll have
    19
    to change both parts. We just raised this as
    20
    an idea because we believe that it's
    21
    complicated to have both 732 and 734, but we
    22
    offer no suggestions to the Board in terms of
    23
    whether to do it.
    24
    Subpart A. In terms of the general
    Keefe Reporting Company
    (618) 244-0190

    156
    1
    provisions, the Agency's applicability
    2
    clause -- and we've talked to them about the
    3
    applicability clause. And I think we're pretty
    4
    much on the same page with that, except that I
    5
    think that the language we proposed -- and I
    6
    would welcome any words that the Board finds
    7
    appropriate in terms of the applicability on
    8
    this.
    9
    The key, I think, is that there can't be
    10
    retroactive application of the rules. Whatever
    11
    amendments the Board makes and whatever -- once
    12
    they're promulgated and they go through the
    13
    joint committee, that's when they're effective.
    14
    So any work performed, any budgets approved
    15
    prior to the effective date of these rules,
    16
    these rules wouldn't apply to. I don't think
    17
    that the Agency's provisions are written that
    18
    tightly, and I think they should be.
    19
    We put in both for 732 and 734 -- and,
    20
    again, we would welcome any wordsmithing on the
    21
    part of the Board in terms of tightening the
    22
    applicability.
    23
    Definitions. Gary King spoke about this,
    24
    this morning. And I find it interesting that
    Keefe Reporting Company
    (618) 244-0190

    157
    1
    PIPE's only perspective in putting the
    2
    definition of UST-RA is to simplify things.
    3
    There was no intention to develop any sort of
    4
    liability that's under Title 17 into Title 16.
    5
    It's especially interesting, in that the
    6
    Agency's proposing TACO. TACO comes out of
    7
    Title 17. And if there's legal issue in terms
    8
    of the applicability of the site remediation
    9
    program to an underground storage tank cleanup,
    10
    one would think that would be a legal issue,
    11
    not simply a suggestion that a definition be
    12
    considered that makes this process work better.
    13
    We didn't even think of the UST-RA issue
    14
    until, quite honestly, there was an Agency
    15
    surreplying the Ayers case, where there was an
    16
    argument raised that there was something
    17
    untoward, if you will, because one of the
    18
    members of PIPE was the decision maker in terms
    19
    of appealing something on behalf of an owner.
    20
    And the point I think we're trying to make
    21
    is there's nothing untoward in that at all.
    22
    Owners and operators have contracts with
    23
    consultants continually in this program, and
    24
    that ought to be recognized by the Board, and
    Keefe Reporting Company
    (618) 244-0190

    158
    1
    that there's no problem with that.
    2
    And the definition that's contained in
    3
    Title 17, speaks perfectly to various issues.
    4
    It basically just says, "a Underground Storage
    5
    Tank remediation applicant means any person
    6
    seeking to perform or performing investigation
    7
    or remedial activities under Title 16 of the
    8
    Act, including the owner/operator of the site
    9
    or persons authorized by law or consent to act
    10
    on behalf or in lieu of the owner/operator of
    11
    the site."
    12
    This simply recognizes the contract, if
    13
    you will. That is a matter of general business
    14
    course between consultants and owners and
    15
    operators of the underground storage tank fund.
    16
    That's it.
    17
    And there are other states, if you look at
    18
    them. I think Indiana is one of them where
    19
    they actually have a form that an owner or an
    20
    operator can file, indicating that a consultant
    21
    can deal on his behalf with the Agency. The
    22
    idea is just to make this easier.
    23
    And, again, even the language here doesn't
    24
    suggest that we're assuming liability on the
    Keefe Reporting Company
    (618) 244-0190

    159
    1
    part of the consultant. It says responsibility
    2
    for interfacing with the Agency on questions
    3
    concerning the propriety of the remediation
    4
    almost always rests with the consultant the
    5
    owner has hired to remediate the property.
    6
    The next item I think that I just wanted
    7
    to talk about is the data collection, plans and
    8
    budgets and reports. We had suggested language
    9
    in the Section 734.135. And, again, the Agency
    10
    has been opposed to the whole concept of a
    11
    database. The benefits of the database, I
    12
    think, we talked about earlier.
    13
    The language just says the Agency shall
    14
    create an electronic database that will allow
    15
    for electronic plans, budgets and reports;
    16
    collect and maintain data relevant to costs and
    17
    remediation of sites, including costs that are
    18
    usual and customary in the cleanup of such
    19
    sites, as well as data related to the number
    20
    and severity of sites yet to be remediated; and
    21
    provide for expeditious review and payment of
    22
    claims that meet the requirements of the Act.
    23
    Early action. We proposed changes in the
    24
    early action, free product removal section.
    Keefe Reporting Company
    (618) 244-0190

    160
    1
    Again, this was for purposes of making these
    2
    rules easier to deal with. It wasn't intended,
    3
    and I don't believe that it causes any major
    4
    legal issues. In fact, I don't consider that
    5
    it has any legal issues in terms of 734.215.
    6
    On Page 15 of our proposal, we talk about
    7
    the Board notes as well. And the suggestion is
    8
    to look at the Board notes because they may be
    9
    obsolete. Our idea is to tie this all up so
    10
    that we all know whatever language the Board is
    11
    using, whether it's maximum rates or lump sums
    12
    or reimbursable costs. As we've suggested, it
    13
    needs to be tied up.
    14
    And there's -- really the Board notes are
    15
    simply confusing to the regulating community.
    16
    So the Board might want to consider whether it
    17
    just wants to do away with those Board notes
    18
    and make the rules, say what they need to say.
    19
    Subpart E, review of plans, budgets or
    20
    reports. Gary testified to this -- well, he
    21
    didn't testify to it, but he did say that this
    22
    would be, I guess, Doug, if that there was a
    23
    problem with the procedure and if it conflicted
    24
    with state law, but it's my impression that
    Keefe Reporting Company
    (618) 244-0190

    161
    1
    they do not.
    2
    First of all, the time frames in here are
    3
    not doing anything that's inconsistent with the
    4
    Act. It's just setting forward a specific
    5
    process. 734.505(a) is exactly the language of
    6
    the Agency. 734.505(b) talks about the
    7
    authority to approve, reject or require
    8
    modification.
    9
    What it really does -- actually, in the
    10
    middle of that is the Agency fails to make such
    11
    decision within 120 days, the applicant can
    12
    consider the Agency to have denied the
    13
    submittal and can proceed to invoke the
    14
    processes set forth in this.
    15
    That is the law. That is the law. PIPE
    16
    would like it differently. It would be great
    17
    that if it was actually a grant as opposed to a
    18
    denial in most cases, but it's a denial. So
    19
    that is the law.
    20
    The part the Agency may find objectionable
    21
    also isn't -- there's nothing wrong with the
    22
    law, and that is to turn the burden of proof.
    23
    The Agency will have the burden as to why the
    24
    applicant's submittal violated the Act or these
    Keefe Reporting Company
    (618) 244-0190

    162
    1
    regulations or was not otherwise approvable.
    2
    If the applicant prevails before the Board, the
    3
    Board may authorize the payment of the
    4
    applicant's costs from the UST fund. That's
    5
    the law as well.
    6
    C is the Agency shall process claims as
    7
    expeditiously as possible. Where the submittal
    8
    and attendant costs are consistent with this
    9
    part, the Agency shall approve such a submittal
    10
    within 45 days of its receipt. Just because
    11
    the law says they get 120 days doesn't mean you
    12
    can't, in your regulations, allow for a shorter
    13
    time frame, especially if the Agency is used to
    14
    processing it in that amount of time frame, a
    15
    shorter time frame anyway, number one.
    16
    And, number two, if the theory of these
    17
    rules is that everything is going to be easy,
    18
    and it's an easy review, and the costs are
    19
    contained, when everyone follows Subpart H, the
    20
    Agency shouldn't have any trouble just
    21
    approving the plan then within that period of
    22
    time.
    23
    Subpart D then says if the Agency intends
    24
    to reject the submitted plan, budget or report,
    Keefe Reporting Company
    (618) 244-0190

    163
    1
    or requires modification thereto, or requests
    2
    more information, it shall within 45 days of
    3
    the receipt of such submittal, provide written
    4
    notification of such intention. Such written
    5
    notification -- and those four provisions are
    6
    taken right out of the statute. Granted those
    7
    provisions are taken out of the statute after
    8
    the 120-day time frame in terms of rejection,
    9
    and in the middle part of it in terms of a
    10
    modification, but there's nothing wrong with
    11
    doing it this way from an administrative law
    12
    perspective. It does not violate the
    13
    Environmental Protection Act. It does not
    14
    violate the Administrative Procedures Act. It
    15
    certainly is a streamline procedural approach
    16
    to getting decisions made easier, quicker and
    17
    more efficiently.
    18
    It says it if chooses to modify the
    19
    submittal in response to the Agency's written
    20
    notification, the applicant shall provide such
    21
    notification of modification to the Agency
    22
    within 35 days of receipt of the Agency's
    23
    letter of intention. The applicant's notice of
    24
    modification shall not extend the applicable
    Keefe Reporting Company
    (618) 244-0190

    164
    1
    120-day review period.
    2
    In fact, I think Doug, in his testimony,
    3
    talked about how, you know, when they get
    4
    information, it doesn't extend the 120-day
    5
    period. So they shouldn't have any problem
    6
    with that either, because you shouldn't ever
    7
    extend the 120-day period in underground
    8
    storage tank.
    9
    F is then if, at the end of the period,
    10
    the Agency deems that the submittal should be
    11
    rejected, it shall provide written notification
    12
    for the reason of such rejection, which shall
    13
    include one more of those reasons delineated in
    14
    734.505(d).
    15
    And I'd like to point those out, if for no
    16
    other reason, are statutory. You know, that's
    17
    why they're italicized, except they're not
    18
    currently the Agency's proposal. And generally
    19
    when they get a rejection letter, there's not
    20
    this specification. When UST remediation
    21
    applicants, or whatever you want to call them,
    22
    the consultants apply and get a denial letter
    23
    from the Agency, oftentimes that denial letter
    24
    simply says exceeds the minimum requirements of
    Keefe Reporting Company
    (618) 244-0190

    165
    1
    the Act, and doesn't allow for any more
    2
    specificity on that.
    3
    And it talks about if the applicant has
    4
    modified its plan, based on the Agency's
    5
    request; that's not good enough, and there's
    6
    still a problem. The Agency ought to explain
    7
    to them why that's a problem as well.
    8
    G says an owner and operator may waive the
    9
    right to a final decision within 120 days.
    10
    That's basically already in the Agency
    11
    proposal. That language isn't any different
    12
    than the Agency's letter.
    13
    H, I think is the same as the current
    14
    Agency language as well. The Agency shall mail
    15
    notice of its intended action, pursuant to
    16
    Section 734.505(d).
    17
    I. Any final action by the Agency to
    18
    reject or require modifications or rejection by
    19
    failure to act, of a plan, budget, or report,
    20
    in accordance with Section 735.505(f), again,
    21
    which cite the statutory language, shall be
    22
    subject to appeal to the Board within 35 days
    23
    after the Agency's final action in the manner
    24
    provided for in review of permit decisions in
    Keefe Reporting Company
    (618) 244-0190

    166
    1
    section.
    2
    Nothing new either.
    3
    Where an applicant has filed an appeal
    4
    with the Board, the Agency shall at the
    5
    applicant's request, agree to a 90-day
    6
    extension provided in Section 40 of the Act.
    7
    Generally, they do that anyway. I mean,
    8
    there is a distinction there in terms of saying
    9
    that the Agency shall agree to a 90-day
    10
    extension. Perhaps there is an issue there,
    11
    but if so, it's not a big one, and it's not
    12
    something that is a deal breaker in terms of
    13
    PIPE anyway. It's not really the focus of this
    14
    procedure.
    15
    My testimony here is that the focus of
    16
    this procedure is absolutely within the
    17
    confines of both the Environmental Protection
    18
    Act and the Administrative Procedure Law.
    19
    During this period at the applicant's
    20
    request, the Agency will meet with the
    21
    applicant in an effort to resolve any dispute
    22
    about costs or narrow any issue that may be
    23
    appealed to the Board.
    24
    2. Where the applicant prevails before
    Keefe Reporting Company
    (618) 244-0190

    167
    1
    the Board, the Board will authorize payment of
    2
    the applicant's reasonable attorney's fees from
    3
    the fund, in accordance with Section 57.7 of
    4
    the Act, unless the Board finds that the appeal
    5
    was not taken in good faith.
    6
    Admittedly, that particular provision
    7
    further details the discretion already allowed
    8
    the Board in the Act. So if the Board
    9
    obviously prefers the discretion as it is
    10
    written in the Act, that's not a deal breaker
    11
    in terms of PIPE either.
    12
    3. As an alternative to a Board appeal,
    13
    the parties may mutually agree, in writing, to
    14
    the services of a mediator or arbitrator who
    15
    shall be paid a reasonable fee from the UST
    16
    fund. And then it talks about specific
    17
    requirements that the UST Advisory Committee
    18
    will establish, a list of acceptable neutrals
    19
    who need not be lawyers and who shall not be
    20
    state employees, but demonstrate an
    21
    understanding of issues related to the
    22
    contracts. The UST advisory committee will set
    23
    a limitation as on the rate to be paid any such
    24
    neutral.
    Keefe Reporting Company
    (618) 244-0190

    168
    1
    PIPE's intention here is not to avoid a
    2
    Board appeal. And PIPE drafted this, in large
    3
    part, not knowing what the balance of powers
    4
    are and still not knowing what the balance of
    5
    powers are in terms of pursuing appeals to the
    6
    Board. It's very costly, as you know now, as I
    7
    certainly know, to proceed through the Board
    8
    through an appeal process. Statutes require
    9
    that you have to have a lawyer to argue before
    10
    the Board. This particular process would give
    11
    the parties an "out" if they chose. Obviously,
    12
    if would be a contract between the EPA and a
    13
    particular consultant, instead of going the
    14
    route of the Board, which would have an appeal
    15
    to the courts. They decide just to resolve it
    16
    more informally. It's an alternative dispute
    17
    resolution procedure that allows for that to
    18
    happen.
    19
    The Board might, I think, already has a
    20
    rule that allows the Agency and members of the
    21
    regulating committee to have an alternative
    22
    dispute resolution procedure, which takes a
    23
    decision outside of the confines of the Board.
    24
    I think it's in the MSHA program, but I am not
    Keefe Reporting Company
    (618) 244-0190

    169
    1
    sure. I will provide the Board with that
    2
    particular provision, but I'm sure that there's
    3
    at least one area on board regulation where the
    4
    Agency's proposed itself an alternative dispute
    5
    resolution mechanism.
    6
    The reason PIPE is proposing this is that
    7
    the balance and the equation of power in the
    8
    underground storage tank program is no
    9
    different than it is in other programs that the
    10
    Agency administers. In large part, that's
    11
    because of the numbers of cases that the Agency
    12
    deals with. It's also because that the money
    13
    in dispute is not as large as it is elsewhere
    14
    when you're talking about permits and those
    15
    kinds of things.
    16
    The other issue I think the Board needs to
    17
    look at is, this really isn't a permit appeal.
    18
    While the law has drawn the underground storage
    19
    tank process into Section 40 of the Act, it
    20
    really isn't a permit appeal. So there are
    21
    various kinds of things which I've suggested in
    22
    my filing to the Board in terms of differences
    23
    and similarities between this and the permit
    24
    process.
    Keefe Reporting Company
    (618) 244-0190

    170
    1
    Certainly I would suggest, though, the
    2
    Wells case that we talked about in here that
    3
    found that the failure of a company to receive
    4
    information before a denial may very well
    5
    violate due process. It's something the Board
    6
    at least should look at in terms of evaluating
    7
    the propriety of a process like this. PIPE is
    8
    very serious about the idea of process and in
    9
    making sure that things work more
    10
    expeditiously.
    11
    More so than any other program or many
    12
    programs, PIPE members feel they're in a black
    13
    box when we're dealing with the Agency, and
    14
    it's a black box that's really hard to get out
    15
    of. And it's really costing them a lot of
    16
    money in terms of doing their business, and
    17
    many of them are even considering getting out
    18
    of the business as a result of that particular
    19
    black box. That is not good for the State of
    20
    Illinois. It's not good for the remediation of
    21
    these 5,000 sites that are inactive and sitting
    22
    out there. So this is a real serious proposal
    23
    on the part of PIPE that we would like the
    24
    Board to listen to in terms of making this
    Keefe Reporting Company
    (618) 244-0190

    171
    1
    process more workable and in terms of balancing
    2
    the equations of the parties out a little
    3
    easier, and a little more as the Act intends,
    4
    that the regulated community and the EPA have
    5
    equal authority when they get before the Board.
    6
    Obviously, this was written as well before
    7
    the Board's case in Ayers recently that you
    8
    issued on Thursday. We just found out about
    9
    that case, tHat the attorneys' fees issue. And
    10
    I'm sure the --
    11
    MR. KING: Excuse me.
    12
    MS. MANNING: Okay.
    13
    MR. KING: I don't think we should be
    14
    talking about cases that are pending before the
    15
    Board.
    16
    MS. MANNING: I thought that case was
    17
    closed. I'm sorry.
    18
    BOARD MEMBER JOHNSON: It's well within
    19
    the appeal period.
    20
    MS. MANNING: Okay, thank you.
    21
    That's all I had on procedure, procedure.
    22
    The payment from the fund. We indicated
    23
    in our Subpart H filing, as the Board has known
    24
    for some time, that we have two real issues.
    Keefe Reporting Company
    (618) 244-0190

    172
    1
    The first issue is the lack of a definitive
    2
    scope of work for any of the things for which
    3
    lump sum is due and owing.
    4
    We have worked very hard, and we've given
    5
    various drafts to the Agency a long time ago,
    6
    and we're still working on all of us agreeing
    7
    what it is that's the scope of work for a
    8
    particular process where a particular lump sum
    9
    that's applicable in this particular
    10
    proceeding.
    11
    And I believe we do have a draft of
    12
    Appendix G, of proposed Appendix G that we're
    13
    going to circulate, and then I'll put into
    14
    evidence.
    15
    In terms of rates and dollars and PIPE
    16
    offering any numbers to replace our Xs that
    17
    have been presented to the Board in the filing,
    18
    at this point, we have decided -- let me just
    19
    explain what we've done thus far and where
    20
    we're working on the numbers.
    21
    PIPE has agreed, through me basically, to
    22
    exchange numbers and has attempted to come up
    23
    with specific numbers that fit the categories.
    24
    However, we have discovered, just like we
    Keefe Reporting Company
    (618) 244-0190

    173
    1
    thought perhaps we would, until we get a
    2
    delineated scope of work so that everybody
    3
    understands what's called for in every lump sum
    4
    payment or maximum amount, or whatever the
    5
    Board intends to call it in its rule, until
    6
    that happens, until everybody agrees what it is
    7
    that's required for that particular piece, it's
    8
    very difficult, if not impossible, for us to
    9
    come up with an alternative set of numbers for
    10
    that particular piece. We're still working on
    11
    it, as we do intend, at some point to present
    12
    those numbers to the Board.
    13
    And the way we're going to do that is
    14
    basically through me. Everybody will, once
    15
    their work, scope of work is delineated, based
    16
    on the Agency's sections, we're going to take
    17
    each of those sections, say this is what the
    18
    work is for this particular dollar amount, we
    19
    all agree that's what we'll do for it. That's
    20
    what's included in it. Let's get that language
    21
    in the rule, let's put a specific dollar amount
    22
    on it, and we'll present that to -- each member
    23
    of PIPE will send me their own indications of
    24
    what that number will be, should be, and then
    Keefe Reporting Company
    (618) 244-0190

    174
    1
    I'll send those to the Board. But that is a
    2
    process that will have to take place after
    3
    we've all come to an agreement on what the
    4
    scope of work is. And I think that is a
    5
    process that everyone in this rule making ought
    6
    to consider that needs to be done before we
    7
    actually come up with numbers that work.
    8
    The other alternative that PIPE considered
    9
    and would like the Board perhaps to consider,
    10
    and we've asked the Agency to consider, and
    11
    they've not, is the idea of using a
    12
    professional market based consultant, like RS
    13
    Means to come in and look at this particular
    14
    situation, this particular market, this
    15
    particular state and indicate what those
    16
    numbers ought to be.
    17
    My understanding is the State of Wisconsin
    18
    is going through rule making at this point in
    19
    time, and they're going effective with their
    20
    new rule in September. And my understanding is
    21
    they're basing some of theirs on drawing from
    22
    RS Means. We've actually talked to the people
    23
    from RS Means. PIPE's not in a position
    24
    obviously to hire them and to say come and look
    Keefe Reporting Company
    (618) 244-0190

    175
    1
    at market data. PIPE is convinced and
    2
    committed to develop accurate market based fees
    3
    and structures. We're not just looking here to
    4
    up the costs and have a high cost of
    5
    remediation. As I said, there's
    6
    5,000 -- there's a lot of work yet to do in
    7
    Illinois. What we're very concerned about,
    8
    however, to make those costs relevant to
    9
    reliable and market based, and there needs to
    10
    be a appreciation for the businesses that are
    11
    already established that are capable of doing
    12
    this work and in prices that reflect their
    13
    costs of doing business. So at this point in
    14
    time, that's where we are. Go ahead.
    15
    BOARD MEMBER JOHNSON: Have you come to a
    16
    consensus? Have your group members come to a
    17
    consensus on how you intend to do that?
    18
    MS. MANNING: Yes. And we had the scope
    19
    of work that we'll pass out today. I think Joe
    20
    has it. Do you just have one copy, Joe?
    21
    MR. TRUESDALE: I have three versions.
    22
    HEARING OFFICER TIPSORD: You know what?
    23
    I'm going to need to have more than one copy.
    24
    MS. MANNING: How about we put it in
    Keefe Reporting Company
    (618) 244-0190

    176
    1
    public comment after the Board hearing?
    2
    MR. TRUESDALE: I have two different
    3
    versions that I'm aware of yet.
    4
    MS. MANNING: That's what we're doing. I
    5
    mean, we've have a scope of work that all of
    6
    the consultants that at least are members of
    7
    PIPE have agreed to. And what they're going to
    8
    do is give me numbers.
    9
    HEARING OFFICER TIPSORD: From a practical
    10
    standpoint, we've already had five sets of
    11
    hearings here. It would seem to me that this
    12
    would be a fairly substantial piece of
    13
    information you're wanting to put in. When
    14
    does PIPE anticipate having this scope of work
    15
    done so that you can move on to the next point?
    16
    MS. MANNING: Probably two weeks, a week.
    17
    MR. TRUESDALE: If I might just add
    18
    something. A lot of it -- a lot of problems
    19
    have come from just trying to figure out what
    20
    will be required in the regulations and the
    21
    changes that have come about through this
    22
    hearing process, what was required for site
    23
    investigation in the initial proposal versus
    24
    what site investigation requirements are.
    Keefe Reporting Company
    (618) 244-0190

    177
    1
    Fourth, first, second and third errata sheets.
    2
    The scope continues to change for us. So it's
    3
    hard to put our finger on what we have to do as
    4
    a result of that.
    5
    MS. MANNING: Well, you saw some of that
    6
    in the testimony this morning about the
    7
    questions about the bids. I mean, there's a
    8
    moving target here, which makes it more
    9
    difficult, because every time any part of the
    10
    questions our people had this morning, well, if
    11
    you have more than one bid, you know, do you
    12
    have more than one bid for each thing? And if
    13
    the bid -- you know, if you do a second
    14
    drilling, do you have to go and get the bids
    15
    again the second time? And so all of those
    16
    things need to be considered in terms of what
    17
    the scope of work is.
    18
    BOARD MEMBER JOHNSON: Well, we
    19
    appreciate -- it's like trying to put a thumb
    20
    tack on jello. You know, we have a time line,
    21
    and I think that that's what Marie was getting
    22
    to is that we can't wait forever.
    23
    MS. MANNING: I understand that. And we,
    24
    honestly, the last time we met with the Agency
    Keefe Reporting Company
    (618) 244-0190

    178
    1
    and Dan Goodwin, there was -- and I think he's
    2
    going to testify today, we asked for more time
    3
    because we thought we had another couple of
    4
    weeks to work with the Agency. So I would
    5
    think it might behoove the Board to have
    6
    another set of hearings or just one in the next
    7
    week or two. But Dan is going to testify today
    8
    as well.
    9
    HEARING OFFICER TIPSORD: Before we move
    10
    on to that, did you have additional testimony,
    11
    or are you ready for questions?
    12
    MS. MANNING: Did you guys want to say
    13
    anything? Can we have just a few minutes?
    14
    HEARING OFFICER TIPSORD: Yeah. Let's
    15
    take a few-minute break, yeah.
    16
    (Brief break.)
    17
    HEARING OFFICER TIPSORD: Let's go back on
    18
    the record.
    19
    MS. MANNING: In response to the Board's
    20
    question, Madam Hearing Officer, I am prepared
    21
    to put two pieces into evidence, which might
    22
    indicate that at least on some costs were
    23
    closer to the Agency than it appears. And
    24
    those are the construction costs, those costs
    Keefe Reporting Company
    (618) 244-0190

    179
    1
    that are very well defined, and they're not the
    2
    professional services costs. They don't
    3
    necessarily require the same scope of work.
    4
    I have a document. Which exhibit are we
    5
    at now? And I'll go ahead and mark it.
    6
    HEARING OFFICER TIPSORD: Exhibit 92 for
    7
    construction costs. And I'll explain it.
    8
    (Whereby, the Hearing Officer
    9
    marked Exhibit Number 92.)
    10
    MS. MANNING: These are costs that
    11
    directly are taken out of the Agency's
    12
    proposal, Subpart H. One we did is put the
    13
    word out to various members of PIPE. Six
    14
    companies responded. Some companies didn't put
    15
    numbers as to anything and others put numbers
    16
    down. And this fills in at least the Xs from
    17
    PIPE's perspective on those unit costs. As you
    18
    can see, we're really not far from the Agency
    19
    on some of these costs, like ET & D.
    20
    BOARD MEMBER JOHNSON: What, Claire?
    21
    MS. MANNING: E T & D, excavation,
    22
    transportation, disposal. The famous $58, in
    23
    other words. We're not seeking the $97 that
    24
    IDOT pays their contractors for ET & D. You
    Keefe Reporting Company
    (618) 244-0190

    180
    1
    know, that big issue about IDOT.
    2
    MR. ROMINGER: Is that a third column
    3
    down?
    4
    BOARD MEMBER JOHNSON: I was just trying
    5
    to find that.
    6
    MS. MANNING: Yes, it's the third, Member
    7
    Johnson. It's the third group, ET & D yards
    8
    per three.
    9
    BOARD MEMBER JOHNSON: 67.46.
    10
    MS. MANNING: That's the 90th percentile,
    11
    you're right. The minimum was 57. The maximum
    12
    was 69.509, average was 6140. These were based
    13
    on, as I indicated, each of the company's
    14
    submitting to me, somebody designing this form
    15
    based on the Agency's Subpart H, as we've
    16
    suggested it be amended in terms of adjusting
    17
    certain categories.
    18
    An example of that is the type of tanks.
    19
    I think the Agency only had two or three
    20
    different types of categories of tanks, and we
    21
    thought there needed to be more categories of
    22
    tanks. As can you tell when you get a tank
    23
    that's very large, the issues get more
    24
    complicated. And several of the companies
    Keefe Reporting Company
    (618) 244-0190

    181
    1
    didn't want to put a price on that at all.
    2
    So there are some, you know, of these
    3
    various different things where what you can see
    4
    from this is where we were uncomfortable
    5
    putting prices on and where the companies were
    6
    comfortable putting prices on. And in some
    7
    areas that's not all that far apart from the
    8
    Agency in terms of these discrete construction
    9
    costs.
    10
    Many of these costs as well, the Board can
    11
    look at RS Means and find similar kinds of
    12
    costs. And that's my next --
    13
    BOARD MEMBER GIRARD: Before you leave
    14
    this exhibit, could I just ask a question now?
    15
    MS. MANNING: Sure.
    16
    BOARD MEMBER GIRARD: How again did you
    17
    solicit this information from the company? Did
    18
    you just call them up and say how much money
    19
    you would like to get for this service?
    20
    MS. MANNING: They're not services.
    21
    Basically we said look at Subpart H, and
    22
    emailed a blank Excel spread sheet, said price
    23
    this as you would if you're bidding for an IDOT
    24
    job, and send it to me. And that's exactly
    Keefe Reporting Company
    (618) 244-0190

    182
    1
    what happened. And then I took those figures
    2
    and created this document.
    3
    We were not able to do any of the other
    4
    costs that need a more clearly defined scope of
    5
    work, professional services cost, the cost of
    6
    doing EACP, those kinds of things.
    7
    BOARD MEMBER GIRARD: Now, company four,
    8
    you didn't get any information from company
    9
    four; is that correct?
    10
    MS. MANNING: That's correct.
    11
    BOARD MEMBER GIRARD: So this is simply an
    12
    email survey. And were these companies
    13
    familiar with the Subpart H proposal?
    14
    MS. MANNING: Yes.
    15
    HEARING OFFICER TIPSORD: Were they all
    16
    members of PIPE, did you say?
    17
    MS. MANNING: Yes. Some of them not
    18
    active members of PIPE. Some of the members of
    19
    PIPE, I should point out as well, were not
    20
    willing to yet attach any costs to it. So you
    21
    can't assume that they're simply the members
    22
    that testified. They're -- go ahead.
    23
    MR. TRUESDALE: I might mention that some
    24
    of the PIPE members are -- our firm, for
    Keefe Reporting Company
    (618) 244-0190

    183
    1
    instance, used RS Means data entirely to derive
    2
    costs that we presented as reasonable prices in
    3
    our statement for costs.
    4
    MS. MANNING: Which is an example I'm
    5
    going to label Exhibit Number 93.
    6
    HEARING OFFICER TIPSORD: I think we have
    7
    another question on this chart.
    8
    MR. GOBELMAN: Steve Gobelman, Illinois
    9
    Department of Transportation.
    10
    I haven't seen this form, but you say it's
    11
    like any other IDOT construction costs.
    12
    MS. MANNING: No, I didn't mean to suggest
    13
    that.
    14
    MR. GOBELMAN: Is that volume based on
    15
    what's going to the landfill per cubic yard
    16
    cost? Is that based on the volume that's going
    17
    to the landfill?
    18
    MS. MANNING: Yards per three.
    19
    MR. GOBELMAN: Is that based upon the
    20
    volume?
    21
    MS. MANNING: Yes, I think it is, isn't
    22
    it?
    23
    MR. GOBELMAN: Are you aware of how IDOT
    24
    does their work?
    Keefe Reporting Company
    (618) 244-0190

    184
    1
    MS. MANNING: I'm not making a comparison
    2
    to IDOT.
    3
    MR. GOBELMAN: Yes, you did.
    4
    MS. MANNING: Maybe. Let me just
    5
    clarify --
    6
    HEARING OFFICER TIPSORD: Wait a minute.
    7
    One at a time, one at a time.
    8
    MS. MANNING: I can.
    9
    MR. GOBELMAN: Specifically everything
    10
    related to the cost of what you perceive to be
    11
    the average cost that IDOT pays for
    12
    transportation, disposal of contaminant soil?
    13
    MS. MANNING: From our perspective, and in
    14
    what we're suggesting here, it's irrelevant to
    15
    us at this point in time what the average cost
    16
    of ET & D is that IDOT does in its contracting
    17
    service.
    18
    MR. GOBELMAN: Are you aware of how IDOT's
    19
    transportation disposal of volume is calculated
    20
    on?
    21
    MS. MANNING: Not at this point in time,
    22
    no.
    23
    MR. GOBELMAN: So, therefore, you're
    24
    making a comparison on something you don't
    Keefe Reporting Company
    (618) 244-0190

    185
    1
    understand or know about?
    2
    HEARING OFFICER TIPSORD: Wait a minute.
    3
    MR. COOK: All of these members of PIPE
    4
    that responded to that are all doing work and
    5
    are well aware of how the Agency does those
    6
    calculations, and they would use their current
    7
    levels of experience and understanding in how
    8
    the Agency works. So it is completely
    9
    irrelevant.
    10
    HEARING OFFICER TIPSORD: Mr. Cook, you
    11
    have not been sworn in. And you are clearly
    12
    offering testimony. So please be sworn in.
    13
    (Whereupon the witness was sworn.)
    14
    HEARING OFFICER TIPSORD: You can
    15
    continue.
    16
    MR. COOK: Well, my point is, that the
    17
    firms that prepare those numbers would have
    18
    prepared those numbers consistent with the
    19
    means that they would use to prepare a budget
    20
    that they would submit to the Agency today.
    21
    MS. MANNING: Correct.
    22
    MR. COOK: So they're well aware of the
    23
    Agency's methods of determination of soil
    24
    volumes and that sort of thing. So this
    Keefe Reporting Company
    (618) 244-0190

    186
    1
    comparison to IDOT, which was used casually, I
    2
    believe, was completely irrelevant.
    3
    MS. MANNING: Thank you.
    4
    MR. TRUESDALE: I might just mention maybe
    5
    to clarify.
    6
    The way it was presented is, it was sent
    7
    out as this would be a request for proposal for
    8
    any environmental work, be it an SRP project,
    9
    whatever, an arbitrator request, a proposal for
    10
    a request for this particular work item, that's
    11
    how it was bid irrespective whether it was in
    12
    the LUST program, SRP. It was marketable rates
    13
    for doing this service.
    14
    MS. MANNING: And, again, it's presented
    15
    to show that on some of these costs, there's
    16
    not that great a distinction.
    17
    And based on your question about moving
    18
    this forward, I wanted the Agency to know, and
    19
    I wanted the Board to know that it's not like
    20
    we're out here hanging, not working. We're
    21
    working at very hard getting to where we think
    22
    this rule needs to go, and I presented that to
    23
    show you that.
    24
    HEARING OFFICER TIPSORD: We had no doubt
    Keefe Reporting Company
    (618) 244-0190

    187
    1
    that you were working hard.
    2
    BOARD MEMBER GIRARD: I have one more
    3
    question.
    4
    How can you come up with a bid for -- I
    5
    mean, like I understand excavation. You know,
    6
    per yard square and disposing a per yard
    7
    square. But transportation costs depend on the
    8
    distance that's being transported. So how are
    9
    you able to come up with a figure without
    10
    knowing that, you know, it's X number of miles
    11
    to your disposal site, from your cleanup site?
    12
    HEARING OFFICER TIPSORD: I am sorry?
    13
    MR. RANGUSSO: Bob Rangusso with Marlin
    14
    Environmental.
    15
    I think you're getting to the point
    16
    exactly. How do you set one price when there's
    17
    such high variability in the cost of transport
    18
    and disposal variables throughout the state,
    19
    regional, local, traffic, seasonal conditions,
    20
    all of those things. What we were responding
    21
    to is the Agency has set one number that
    22
    categorically covers the maximum for any
    23
    scenario that might happen throughout the
    24
    state. So, therefore, we're trying to match
    Keefe Reporting Company
    (618) 244-0190

    188
    1
    apples with apples on their behalf. I mean, I
    2
    would certainly agree that it is not something
    3
    that should be -- it should be on a
    4
    site-by-site basis.
    5
    MS. MANNING: That's why I would add to
    6
    that, that's why some PIPE members refused to
    7
    actually even fill the numbers out because they
    8
    were not able to do that.
    9
    Our point was the Board is going to want
    10
    to see something as an alternative to the
    11
    Agency. The Agency has been asking us for
    12
    alternative numbers for several months now.
    13
    You have hit the nail on the head. It is very
    14
    difficult to put numbers out there when you
    15
    don't exactly know what the numbers apply to.
    16
    We were trying as best as possible to be
    17
    responsive to the Agency Subpart H.
    18
    BOARD MEMBER GIRARD: But would this make
    19
    it appear that Subpart H now has become the
    20
    floor for these costs, because the lowest cost
    21
    of these five companies that came back with an
    22
    estimate is the maximum cost that the Subpart H
    23
    proposals is to pay for that? $57?
    24
    MS. MANNING: Again, we looked at Subpart
    Keefe Reporting Company
    (618) 244-0190

    189
    1
    H, where we could define a particular cost
    2
    based on what we believe to be the Agency's
    3
    expectation.
    4
    MR. TRUESDALE: I might explain.
    5
    Some of the responses may have been that
    6
    appears that Agency proposed Subpart H costs
    7
    are adequate or something to that effect. So
    8
    as a result, the numbers that went in would
    9
    have been reflective of what Subpart H
    10
    suggested.
    11
    HEARING OFFICER TIPSORD: Go ahead.
    12
    MR. WALTON: Harry Walton.
    13
    At the previous hearing, there was a lot
    14
    of dialogue focussed at the IEPA statistics for
    15
    their population from which they drew their
    16
    costs. In comparison, what is the population
    17
    from which PIPE drew its sampling, in context
    18
    to the total population out there, do you feel
    19
    that your numbers are statistically valid? Are
    20
    the same issues that you raised to the Illinois
    21
    EPA's numbers, are they still issued here also?
    22
    MS. MANNING: I'll answer to that, Harry.
    23
    I don't disagree with you. The fact of the
    24
    matter is, it took us a long time to try to
    Keefe Reporting Company
    (618) 244-0190

    190
    1
    decide whether we were going to throw these out
    2
    or not. We're not suggesting these are the
    3
    numbers. In fact, that is exactly the issue in
    4
    this proceeding. The Agency comes out with
    5
    select numbers based upon not a statistical
    6
    database. Our numbers are based on -- I can
    7
    tell you our numbers are based on contractors
    8
    that do a lot of UST work today. Now, today,
    9
    probably out of -- there's an exhibit already
    10
    in the record out of most of those UST
    11
    remediation consultants that have in the double
    12
    digits, if you will, sites out there, and are
    13
    members who may have been asked to fill this
    14
    out.
    15
    MR. WALTON: But population size is very
    16
    small?
    17
    MS. MANNING: What do you mean population
    18
    size?
    19
    MR. WALTON: Responses that characterize
    20
    your entire statistics.
    21
    MS. MANNING: I would point out, Harry, as
    22
    well, when I reviewed the documentation of all
    23
    the underground remediation businesses, the
    24
    businesses in Illinois that do underground
    Keefe Reporting Company
    (618) 244-0190

    191
    1
    storage tank remediation, the great bulk of
    2
    them, the great bulk of them had less than
    3
    1 percent market share, if you will, out of
    4
    the -- for lack of a better word, less than
    5
    1 percent of the Agency's decision making
    6
    applied to those.
    7
    HEARING OFFICER TIPSORD: Excuse me,
    8
    Ms. Manning, but you're making it very
    9
    difficult for us to hear. Go ahead,
    10
    Ms. Manning.
    11
    MS. MANNING: Less than 1 percent of the
    12
    Agency's decisions applied to that great bulk
    13
    of contractors.
    14
    MR. WALTON: I understand.
    15
    MS. MANNING: So, basically, this is a
    16
    good representative group of those underground
    17
    storage tank remediation businesses that do a
    18
    lot of underground storage tank remediation.
    19
    HEARING OFFICER TIPSORD: Mr. Truesdale?
    20
    MR. TRUESDALE: In addition to that, I'd
    21
    like to point out, once again, that many of the
    22
    costs were derived solely from RS Means, which
    23
    is a database that's essentially infinitely
    24
    prepared by a third party data resource
    Keefe Reporting Company
    (618) 244-0190

    192
    1
    clearing house. UST abandonment costs, for
    2
    instance, at least I know at least one of the
    3
    inputs of the six companies were derived solely
    4
    based on RS Means data and is within the range
    5
    of applicability for the rest. So the
    6
    individual estimates that were submitted do
    7
    have a kind of inherent check and balance
    8
    system against RS Means.
    9
    I know that Holliston Wallgreen (sp),
    10
    two-inch well installation, which I believe
    11
    Claire is going to present as another exhibit,
    12
    was derived solely from RS Means' data, using
    13
    their production rate estimates and their
    14
    material, labor and equipment costs.
    15
    MS. MANNING: Basically, Member Girard,
    16
    I'm not -- this can't be done. It's just that
    17
    it needs to be done correctly. And at least
    18
    from my perspective, this is more market based
    19
    because it's actually done by people out from
    20
    the market than it is based on historical data
    21
    that was discovered and potentially dated. I
    22
    mean, I guess so that's the point I'd like to
    23
    make on this particular document.
    24
    MR. ROMINGER: I have just a quick
    Keefe Reporting Company
    (618) 244-0190

    193
    1
    question on that.
    2
    When I was looking through this under the
    3
    soil, removal and disposal, the transportation
    4
    for clean soil column, and then all of the
    5
    columns under truck disposal, I was just
    6
    wondering if there was some information that's
    7
    missing, because when you look down the
    8
    information that's applied to the cost reach
    9
    company, when you get down to the
    10
    90th percentile, the very last row, those
    11
    numbers are all higher than the numbers
    12
    actually provided by the companies.
    13
    MS. MANNING: I don't know why that is.
    14
    That's the only one like that, isn't it?
    15
    MR. ROMINGER: Well, everything under drum
    16
    disposal, under transportation, clean soil,
    17
    those are the only ones I looked at. I didn't
    18
    look at the other ones. There was some blank
    19
    lines. So I didn't know if there was some
    20
    company's information that was missing out of
    21
    that.
    22
    MS. MANNING: Go ahead.
    23
    MR. WEINHOFF: I was just going to say,
    24
    it's just due to not having enough response.
    Keefe Reporting Company
    (618) 244-0190

    194
    1
    The 90th percentile is simply a formula that
    2
    takes a number times the standard deviation
    3
    plus the average. And it's just due to lack of
    4
    enough response, and I'm still -- I mean, we
    5
    are trying to get more responses, and we're
    6
    getting as many as we can.
    7
    MR. TRUESDALE: It's representative of the
    8
    input that has significant variability.
    9
    MS. MANNING: It's not intended to be
    10
    imperial.
    11
    MR. WEINHOFF: It was a formula set in
    12
    those, and the numbers were put in, and the
    13
    formula wasn't changed and wasn't.
    14
    MR. ROMINGER: So you get a
    15
    90th percentile that exceeds all the data
    16
    inputs?
    17
    MR. WEINHOFF: If there's not enough
    18
    inputs, that's how it came out. I guess it
    19
    looks like there's probably two inputs on
    20
    those; is that correct? And so the standard,
    21
    that's just not enough to probably calculate
    22
    standard deviation.
    23
    MR. TRUESDALE: It's standard deviation
    24
    assumes the normal distribution. So it's
    Keefe Reporting Company
    (618) 244-0190

    195
    1
    probably not normal distribution.
    2
    HEARING OFFICER TIPSORD: Yeah. Mr. Cook?
    3
    MR. COOK: I think it would serve to help
    4
    sort of to resolve this situation. From USI's
    5
    perspective, we looked at this exercise as the
    6
    Agency has proposed this figure $57 per yard,
    7
    and does this figure look palatable based upon
    8
    our 15 years' of experience and the several
    9
    hundred sites that we're involved in. We put
    10
    our number down. We believe we're close. We
    11
    believe we're close enough and USI does -- we
    12
    believe we're close enough in this instance
    13
    that we don't see significant opposition to
    14
    what -- on USI's perspective for what the
    15
    Agency has proposed.
    16
    MS. MANNING: On these costs. We should
    17
    also point out that these costs do not consider
    18
    any costs of the competitive bidding process
    19
    that the Agency has just proposed. In other
    20
    words, the cost of bidding isn't built into any
    21
    of these costs.
    22
    HEARING OFFICER TIPSORD: If there's no
    23
    objection, I don't think we've formally
    24
    admitted this. We'll admit this as Exhibit 92.
    Keefe Reporting Company
    (618) 244-0190

    196
    1
    (Whereby, Exhibit Number 92 was
    2
    admitted into evidence.)
    3
    MS. MANNING: Exhibit 93 is basically
    4
    taken from RS Means 2004. It deals just with
    5
    monitor well, material costs for two-inch,
    6
    four-inch, six-inch and eight-inch wells. I'm
    7
    going to put this into -- I think you already
    8
    have it.
    9
    HEARING OFFICER TIPSORD: Yes. It's
    10
    Exhibit 93.
    11
    MS. MANNING: Thank you. This is
    12
    basically information that the Board can obtain
    13
    or the Agency could have obtained from RS
    14
    Means, which is, as we said, early in this
    15
    proceeding, a service that writes a book that
    16
    has contractor costs, as well as they have a
    17
    special one in terms of environmental costs,
    18
    and that's where this information is derived
    19
    from.
    20
    HEARING OFFICER TIPSORD: Seeing no
    21
    objection, we'll admit that as Exhibit 93.
    22
    (Whereby, Exhibit Number 93 was
    23
    marked and admitted into
    24
    evidence.)
    Keefe Reporting Company
    (618) 244-0190

    197
    1
    MR. TRUESDALE: I might adjust a bit about
    2
    that particular exhibit. The costs, once
    3
    again, were derived wholly from RS Means. And,
    4
    essentially, the same thing can be done for a
    5
    number of the other general costs components
    6
    proposed in Subpart H, using third party
    7
    environmental cost data that's representative
    8
    of a large sample set collected over a long
    9
    period of time and accepted widely throughout
    10
    not only the environmental construction agency,
    11
    but a vast majority of construction industries
    12
    nationwide.
    13
    MS. MANNING: Again, though, he's talking
    14
    unit costs, discrete costs, not costs that are
    15
    dependent on a delineated scope of work.
    16
    MR. TRUESDALE: Exactly. It's
    17
    predominantly associated with fixed services or
    18
    commodity services, not professional consulting
    19
    services.
    20
    But a similar exercise to be completed for
    21
    UST removal using RS Means' data, the example
    22
    provided in that exhibit is strictly for
    23
    monitor well construction and monitor well
    24
    abandonment.
    Keefe Reporting Company
    (618) 244-0190

    198
    1
    MS. MANNING: And PIPE has always
    2
    indicated the Agency would be fine with that
    3
    approach in terms of using RS Means, in terms
    4
    of these various unit costs that are discrete.
    5
    So that in that regard, this is not new.
    6
    MR. TRUESDALE: And another point I might
    7
    bring out, we did the ratios also just to
    8
    compare to what Doug presented in his
    9
    testimony. And it's fairly similar to what
    10
    they proposed a ratio of 1 and 1/2, I think,
    11
    for 20-foot or 25-foot well, 2 inch compared to
    12
    4 inch, the ratio for 2. However, the unit
    13
    costs were different than what is currently
    14
    proposed by the Agency, but the scenarios
    15
    appeared to check out.
    16
    HEARING OFFICER TIPSORD: Given this
    17
    testimony that you're very close to what the
    18
    Agency has proposed in Subpart H, I'm going to
    19
    ask you the same question that I asked earlier
    20
    about the businesses, the members of PIPE. If
    21
    the Board adopts Subpart H as currently
    22
    proposed by the Agency, would you anticipate
    23
    that this would put any of your companies
    24
    either out of business or at least out of the
    Keefe Reporting Company
    (618) 244-0190

    199
    1
    underground storage tank business?
    2
    MS. MANNING: As currently proposed with
    3
    the rates that are proposed without any
    4
    delineation of scope of work?
    5
    HEARING OFFICER TIPSORD: Yes.
    6
    MS. MANNING: Yes.
    7
    HEARING OFFICER TIPSORD: We'll start with
    8
    Mr. Cook, since he's already sworn in.
    9
    MR. COOK: In answer to your question, I
    10
    was -- I would segregate that question into two
    11
    parts.
    12
    With regard to the professional services,
    13
    that's where I have the major area of concern.
    14
    And I think absolutely you would see
    15
    consultants go out of business, or just simply
    16
    choose not to do LUST work any more. That's
    17
    based upon many years of experience in dealing
    18
    with all the unknowns that consultants have to
    19
    deal with, and the fact that these Subpart H
    20
    regulations, as proposed, don't provide, define
    21
    the scope of work to implement a maximum
    22
    payment amount in the absence of a defined
    23
    scope of work is -- it just doesn't make good
    24
    business sense. It doesn't make good financial
    Keefe Reporting Company
    (618) 244-0190

    200
    1
    sense for anyone.
    2
    And it would be analogous to hiring an
    3
    architect to design a home and tell him that
    4
    you're going to have him design this home, but
    5
    we're going to have him design it, and you're
    6
    going to pay him $2,000. What he doesn't
    7
    realize is that it's a 15,000 square foot home.
    8
    If he can design the home and it was a 2,000
    9
    square foot home for that fee, fine. He's
    10
    going to lose a significant amount of money on
    11
    a larger home.
    12
    So absolutely I think there are companies
    13
    that will go out of business.
    14
    I think as it pertains to drilling and
    15
    excavation, transportation and disposal and
    16
    remedial action performed in the field, I think
    17
    the Agency has a long history of collecting
    18
    well-defined data.
    19
    As I recall in Mr. Oakley's testimony -- I
    20
    believe it was in Bloomington -- he testified
    21
    that the Agency had long collected statistics
    22
    based upon excavation, transportation and
    23
    disposal of the cubic yard of soil. And I
    24
    would concur with his testimony on that. I
    Keefe Reporting Company
    (618) 244-0190

    201
    1
    would say the same thing holds true for
    2
    drilling. So I think that the Agency's data
    3
    based in those areas is much more significant.
    4
    I don't see that same thing happening with the
    5
    professional services. I don't think they have
    6
    a database that can define well a scope from
    7
    site A to site B.
    8
    HEARING OFFICER TIPSORD: Ms. Davis, did
    9
    you have anything else?
    10
    MR. TRUESDALE: I would just like to add
    11
    to Mr. Cook's testimony also.
    12
    The same is true with the construction
    13
    costs that we presented. It's all for fixed
    14
    scope of work. The items there's dissension
    15
    among PIPE members are in the areas where
    16
    there's less fixed scope of work, are less
    17
    defined tasks lists associated with it.
    18
    And the same holds true for the Agency.
    19
    We've seen the same thing also. We've seen
    20
    similar costs, fixed scope of work. That
    21
    hasn't changed substantially over years and
    22
    years for drilling and excavation, disposal,
    23
    but professional services change as a result of
    24
    variations in the regulatory frame work, the
    Keefe Reporting Company
    (618) 244-0190

    202
    1
    implementation of TACO, the multiple options
    2
    available to the owner/operators to address the
    3
    contamination at the site. New technologies
    4
    are developed every year that changes costs and
    5
    changes the amount of work associated with
    6
    cleanup of contaminated sites. Yet excavating
    7
    cubic yard of soil and drilling one foot of
    8
    boring stays relatively consistent from year to
    9
    year, and the scope of work doesn't change
    10
    appreciably.
    11
    HEARING OFFICER TIPSORD: Mr. Cook?
    12
    MR. COOK: One other thing that I would
    13
    like to add is a very serious concern that I
    14
    have, is that if specific maximum payment
    15
    amounts are passed as they relate to
    16
    professional services, then what drives
    17
    innovation? Because it's innovation within the
    18
    marketplace that ultimately drives costs down.
    19
    And in the absence of that innovation, the
    20
    ability for that professional to innovate and
    21
    to think, to go outside the box, we don't have
    22
    a permanent mechanism in Illinois to drive
    23
    costs down. It's that innovation that drives
    24
    the free market system. And I certainly hope
    Keefe Reporting Company
    (618) 244-0190

    203
    1
    the Board will keep that in mind as it makes
    2
    its decision.
    3
    HEARING OFFICER TIPSORD: Are there any
    4
    other -- Mr. King?
    5
    MR. KING: I want to ask the question of
    6
    Mr. Cook; are you saying that if Subpart H is
    7
    adapted the way it is proposed here with the
    8
    rates and the bidding options involved, that
    9
    USI is going to stop doing LUST work in this
    10
    state?
    11
    MR. COOK: I didn't say that USI would. I
    12
    say that I believe that there are firms that
    13
    will be put out of business.
    14
    MR. KING: But USI will continue to do
    15
    work?
    16
    MR. COOK: I'm not going to comment on
    17
    that one way or another at this point.
    18
    MR. KING: Is there a reason why you can't
    19
    comment on that?
    20
    MR. COOK: Is there a reason why?
    21
    MR. KING: Yes.
    22
    MR. COOK: Because there are competitors
    23
    in this room, I'm not going to comment. I'm
    24
    going to refrain from commenting while
    Keefe Reporting Company
    (618) 244-0190

    204
    1
    competitors are present.
    2
    MR. KING: When you say other competitors
    3
    are going out of business, what would that
    4
    analogy be based on?
    5
    MR. COOK: Comments within the industry.
    6
    MR. KING: Comments from other competitors
    7
    that have told you they're going to go out of
    8
    business?
    9
    MR. COOK: Yes.
    10
    HEARING OFFICER TIPSORD: Mr. Truesdale?
    11
    MR. TRUESDALE: I think the market, in
    12
    general, whether or not a particular firm
    13
    decides to continue to work, do work in the
    14
    LUST market is going to be depending on what
    15
    the numbers come out. If they're lucrative and
    16
    provide a reasonable profit for completion,
    17
    then people are going to perform the work. If
    18
    companies continue to lose money from
    19
    completing LUST projects as a result of changes
    20
    and limitations in payment, then they're going
    21
    to naturally drop out of the industry and
    22
    choose not to do that work or be forced to
    23
    close the doors and not be able to do that work
    24
    essentially.
    Keefe Reporting Company
    (618) 244-0190

    205
    1
    HEARING OFFICER TIPSORD: Thank you.
    2
    MR. TRUESDALE: It's a business decision
    3
    and will be made once the final numbers are
    4
    determined.
    5
    BOARD MEMBER JOHNSON: I looked through
    6
    this Appendix E. I guess it is the personnel
    7
    titles and rates. And there doesn't appear to
    8
    be a significant difference, not a huge
    9
    difference between any of the categories and
    10
    the maximum hourly rate attributed to that
    11
    particular job description and category.
    12
    So what you're saying your concern is, is
    13
    because of the scope of work is not defined,
    14
    you don't know how many hours of whatever
    15
    dollar per hour increment it is? Okay.
    16
    MS. MANNING: That's correct.
    17
    HEARING OFFICER TIPSORD: Mr. King?
    18
    MR. KING: Mr. Truesdale, you used the
    19
    term you have to -- you look at whether the
    20
    payback was lucrative. Was that the word you
    21
    used?
    22
    MR. TRUESDALE: Possibly. There has to be
    23
    a profit associated with completion of work.
    24
    If we just cover costs and don't have
    Keefe Reporting Company
    (618) 244-0190

    206
    1
    reasonable profit to keep our overhead and
    2
    salaries and so forth --
    3
    MR. KING: What kind of percentage of
    4
    profit would you consider to be necessary for
    5
    your firm to continue doing LUST work?
    6
    MR. TRUESDALE: I personally don't have
    7
    any idea. Industry standards for personnel
    8
    tend to range from multiplier of three to four.
    9
    So three to four times what our operating costs
    10
    would be.
    11
    MS. MANNING: If I might add to that,
    12
    RS Means includes the industry standards in
    13
    terms of profit overlay. The Board could look
    14
    at RS Means for that information.
    15
    MR. TRUESDALE: I mean, it's not strictly
    16
    profit. You have overhead cost, profit,
    17
    general conditional projects, so forth and so
    18
    on, that go on top of our operating capital.
    19
    So in order for a particular job to be
    20
    lucrative, we have to cover operating capital,
    21
    plus make enough money in addition to that to
    22
    cover overhead, general conditions, profit.
    23
    Insurance costs continue to go up, our profit
    24
    margin changes continuously.
    Keefe Reporting Company
    (618) 244-0190

    207
    1
    MR. KING: So in other words, the
    2
    reimbursement would have to end up being
    3
    lucrative in order for you, the firm, to
    4
    continue?
    5
    MR. TRUESDALE: Correct.
    6
    HEARING OFFICER TIPSORD: Mr. Cook?
    7
    MR. COOK: I'd like to clarify, too, that
    8
    I think that what's proposed in Subpart H as it
    9
    relates to professional services will be more
    10
    difficult for the smaller firms to deal with
    11
    and address.
    12
    I've heard in meetings with the Agency
    13
    that it should be an obligation of the larger
    14
    firms to cut costs, contain costs, and that it
    15
    all comes out in the wash. Smaller firms don't
    16
    have an opportunity. They're members of PIPE
    17
    that have just a few jobs, and they don't have
    18
    an opportunity to allow -- to come out into the
    19
    wash. They have the 5, 10, 15 jobs that they
    20
    have, and that's their opportunity to make a
    21
    living. I don't believe it's appropriate or
    22
    fair for those types of firms to go out of
    23
    business.
    24
    I was once there. And I stand in the
    Keefe Reporting Company
    (618) 244-0190

    208
    1
    position today where we're the largest firm in
    2
    this type of work in the State of Illinois, and
    3
    we could gladly gobble those firms up as they
    4
    go out of business, but I've been in that
    5
    individual sole proprietor's type role before,
    6
    and it's not fun. It's very difficult.
    7
    And so I think this particular set of
    8
    regulations, as it pertains to professional
    9
    services, would be extremely difficult for
    10
    those one- and two-man shops.
    11
    HEARING OFFICER TIPSORD: Did you have
    12
    anything else, Ms. Manning?
    13
    MS. MANNING: Just as a follow-up to that.
    14
    One of the things that I've been most
    15
    impressed with working with PIPE is they are a
    16
    group of very viable businesses that do compete
    17
    with one another and hardly knew each other
    18
    before they formed this association.
    19
    MR. KING: I had other questions.
    20
    HEARING OFFICER TIPSORD: That's fine. Go
    21
    ahead. I just wanted to be sure that we were
    22
    done with the presentation before we --
    23
    MR. KING: Oh, okay.
    24
    Keefe Reporting Company
    (618) 244-0190

    209
    1
    QUESTIONS BY MR. KING:
    2
    Q There's a couple references made to the
    3 Wisconsin DNR. Excuse me. To the LUST program
    4 within Wisconsin.
    5
    A (By Ms. Manning) Just a couple, yes.
    6
    Q Did you talk to somebody with --
    7
    A I did.
    8
    Q Who did you talk to?
    9
    A Mr. Dangler (sp).
    10
    Q Mr. Danger?
    11
    A I think that was his name. I can't
    12 remember. I can get you that information.
    13
    Q Who does he work for?
    14
    A Is it called pecfa (phonetic). It's the
    15 Wisconsin Underground Storage Tank Program with DNR,
    16 with the Wisconsin DNR.
    17
    Q Are you aware that in Wisconsin the LUST
    18 program is administered by two separate agencies?
    19
    A It wouldn't surprise me, as it is in
    20 Illinois as well.
    21
    Q The LUST program, the LUST program --
    22
    MR. MULLEN: The Department of Commerce
    23
    handles the issues that defer from the --
    24
    HEARING OFFICER TIPSORD: Hold on. Wait a
    Keefe Reporting Company
    (618) 244-0190

    210
    1
    minute. State your name, and we'll have you
    2
    sworn in.
    3
    MR. MULLEN: Scott Mullen (sp).
    4
    HEARING OFFICER TIPSORD: And who do you
    5
    represent?
    6
    MR. MULLEN: Regensis (sp).
    7
    HEARING OFFICER TIPSORD: Thank you.
    8
    MR. MULLEN: Yeah, we're within the group.
    9
    We all have specialists in certain areas, but,
    10
    yeah, I don't know if Claire is speaking of the
    11
    DNR or the department of commerce, but how the
    12
    divisions go, yeah.
    13
    MS. MANNING: And I'm not sure which one I
    14
    was speaking to either, actually. Just the one
    15
    that is doing the rule making that's going to
    16
    be effective September 1st. And the
    17
    gentleman's name was Mr. Dangler.
    18
    Q (By Mr. King) So you're aware that about
    19 half of the program is administered by Wisconsin
    20 DNR, and then about the other half of the program is
    21 administered by the equivalent of the Illinois
    22 Department of Commerce and Economic Opportunity?
    23
    And when were you suggesting that
    24 that is -- maybe I missed the point. Are you saying
    Keefe Reporting Company
    (618) 244-0190

    211
    1 that that is a model we'd want to start to follow?
    2
    A No, I didn't suggest that at all,
    3 Mr. King. I simply suggested that I think in terms
    4 of the -- I think the only thing I raised about that
    5 is the agency that I was talking to was totally
    6 funded by the USEPA fund, and not by the state
    7 dollars that came through the UST state fund. I
    8 believe that's about all I said about the Wisconsin
    9 issue.
    10
    I wasn't -- in fact, I think they
    11 have a competitive bidding in Wisconsin. All of the
    12 models and all of the states are very different.
    13 And I'm not necessarily suggesting that Illinois
    14 look to any different any one of the states.
    15
    I do think that you all put the
    16 different states into evidence. And I did suggest
    17 as well to the Board that they look not only at the
    18 dollar figures in the other state statutes, but also
    19 in the escape clauses, whatever you want to call
    20 them, the scope of work clauses, whatever you want
    21 to call them, because they have those kind of
    22 clauses as well.
    23
    Q I noticed in your proposal, you didn't
    24 refer to this in your testimony, but in your
    Keefe Reporting Company
    (618) 244-0190

    212
    1 proposal, there was a provision that said that the
    2 Agency personnel reviewing a plan would have to be
    3 an LPE or an LPG.
    4
    A Where is that? Just point me to the
    5 language.
    6
    Q It's page 21. This is under 734. It says
    7 something -- a technical review shall be conducted
    8 by IEPA personnel who is a licensed professional
    9 engineer or geologist.
    10
    HEARING OFFICER TIPSORD: Top page of 21.
    11
    MS. MANNING: I see it.
    12
    MR. KING: Yes.
    13
    MS. MANNING: What I think, what I was
    14
    testifying in terms of apples and oranges. If
    15
    there is a technical review performed by the
    16
    Agency, it needs to be performed by someone who
    17
    has technical licensure. And if it's a
    18
    financial review, the Agency ought to be freer
    19
    than making technical judgments.
    20
    Q (By Mr. King) So it's PIPE's position that
    21 every IEPA reviewer needs to be -- reviewing a
    22 technical plan needs to be either an LPE or LPG?
    23
    A I think that when the Agency makes a
    24 determination and denies reimbursement on a
    Keefe Reporting Company
    (618) 244-0190

    213
    1 technical ground, they ought to have a technical
    2 review and a technical person make that
    3 determination.
    4
    Q You probably have no reason to know this,
    5 but I'm sworn. So accept this for what it's worth.
    6
    But approximately 10 to 15 percent of
    7 the Agency reviewers are LPEs or LPGs. As I
    8 interpret this, that would mean that approximately
    9 85 to 90 percent of the current staff project
    10 reviewers would be ineligible to review technical
    11 plans. And based on that, do you have a view as to
    12 what that would do to the speed of the review
    13 process relative to the Agency's program?
    14
    A It's certainly not PIPE's intention to
    15 slow up the review process.
    16
    HEARING OFFICER TIPSORD: Go ahead,
    17
    Mr. Truesdale.
    18
    MR. TRUESDALE: I would add that we
    19
    contemplated that. If you look back to
    20
    professional engineer/professional geologists
    21
    Act, the requirements are a little looser than
    22
    that. The review should be conducted under the
    23
    direction and oversight of a licensed
    24
    professional engineer, licensed professional
    Keefe Reporting Company
    (618) 244-0190

    214
    1
    geologist who ultimately has responsibility for
    2
    that decision. But the review itself does not
    3
    have to be conducted by that person, just under
    4
    the direction of. It's the same way your
    5
    regulations are written, because they're
    6
    modeled after the Professional Engineer and
    7
    Professional Geologist Act.
    8
    MR. KING: But that's not what this says
    9
    here.
    10
    MR. TRUESDALE: The intention of that.
    11
    MS. MANNING: Mr. King, I honestly think
    12
    this is your language.
    13
    MR. KING: Well, it's not.
    14
    MS. MANNING: 734-5150(a)and (b).
    15
    MR. KING: It's not.
    16
    MS. MANNING: Okay.
    17
    MR. TRUESDALE: It may need to
    18
    be -- that's what the intent was. It may need
    19
    some changing of wording or whatever, but the
    20
    intention was to be consistent with the
    21
    Professional Engineer and Professional
    22
    Geologist Act.
    23
    MR. KING: I want to go back. I'm kind of
    24
    going backwards through this provision on 20
    Keefe Reporting Company
    (618) 244-0190

    215
    1
    where you discussed this mediator or arbitrator
    2
    provision.
    3
    MS. MANNING: Pardon?
    4
    BOARD MEMBER JOHNSON: You're putting all
    5
    of us out of work. The reviewers, the Board.
    6
    Q (By Mr. King) By the terms of this, it
    7 states the parties may mutually agree. So if one of
    8 the parties -- for instance, if the Agency did not
    9 agree to having a mediator or arbitrator, then that
    10 would not be applicable.
    11
    A (By Ms. Manning) That's correct. That's
    12 what alternate means, alternative.
    13
    Q Now, I can tell you right now that the
    14 Agency is not going to agree in any instance to this
    15 kind of thing.
    16
    A You've told me that before, Mr. King.
    17
    Q So, I mean, in that sense, the Board could
    18 put this in the rule or not put it in the rule.
    19 It's not going to make any difference because it's a
    20 dead letter as it would go in.
    21
    A So long as the Agency makes that position,
    22 takes that position, that's the Agency's position.
    23
    Q One of the things we seem to have a
    24 difference of opinion on is the ability of the Board
    Keefe Reporting Company
    (618) 244-0190

    216
    1 to shorten a statutory review period, which is 120
    2 days at this point. As I understand what you're
    3 saying is, that the Board has authority to mandate
    4 that the Agency complete its reviews in something
    5 shorter than 120 days.
    6
    A Under certain conditions, yes.
    7
    Q Okay. Now, if you're suggesting that the
    8 Board has the authority to shorten a statutory time
    9 frame, do you think the Board also has the authority
    10 to shorten the statutory time frame when it comes
    11 to a petitioner filing a petition for review? In
    12 other words, could the Board say you have only got
    13 15 days to file an appeal as opposed to 35?
    14
    A No, because that's jurisdictional.
    15
    Q Well, why isn't the 120-day time frame
    16 jurisdictional then? I mean, in this case, the
    17 legislature has made a decision that the Agency has
    18 the right to take up to 120 days to perform a
    19 review. On what authority would the Board have to
    20 mandate that the Agency has to review things in less
    21 than what the legislature has said it can review
    22 things?
    23
    A Actually, the legislative prescription is
    24 that the Agency shall do it within that period of
    Keefe Reporting Company
    (618) 244-0190

    217
    1 time. In other words, there used to be a
    2 consequence for the Agency not acting on it. Now
    3 there's not even a consequence, really, for the
    4 Agency not acting within the 120-day period of time.
    5 The fact of the matter is, there still probably
    6 isn't a consequence with the Agency not acting
    7 within the 120-day period of time, but that does not
    8 preclude the Board or the Agency from having a
    9 shorter time frame than that which is generously
    10 allowed by the legislature.
    11
    Q You made some comments about -- there was
    12 four different legislative versions of 57.7 F. I
    13 think it was F. Or was it H?
    14
    A No, not of F, of that section.
    15
    Q Of that section.
    16
    A Of that section.
    17
    Q Now, the Agency attempted to meld all
    18 those different bills when we drafted our rule
    19 that's before the Board here.
    20
    Are you suggesting that what the
    21 Agency drafted is somehow inconsistent with those
    22 statutes or did not meld those statutes properly?
    23
    A I was reacting to Mr. Clay's testimony
    24 regarding the LPE and LPG certification, where I
    Keefe Reporting Company
    (618) 244-0190

    218
    1 believe he just focussed on Section F, which is in
    2 only one of those statutes. So basically I was
    3 suggesting that, in fact, the LPE/LPG certification,
    4 which that particular Act amended, various different
    5 sections of the Act needed to be considered as well.
    6 I was actually acting in reaction to your testimony
    7 regarding LPE and LPG certification where you said
    8 that it's simply an oversight, and that's all the
    9 legislature intended. And in that same vein then, I
    10 just talked basically about the complicated nature
    11 of Title 16.
    12
    Q But you're not suggesting that what we
    13 propose is an inconsistent melding of those?
    14
    A I'm suggesting the Board needs to look at
    15 whether it is or whether it isn't. I think the
    16 Board is going to have to before they send it to the
    17 joint committee on administrative rules anyway. I
    18 think it's a complicated legal question.
    19
    MR. KING: That's all the questions.
    20
    HEARING OFFICER TIPSORD: Are there any
    21
    other questions for PIPE?
    22
    MS. MANNING: Thank you.
    23
    HEARING OFFICER TIPSORD: Thank you.
    24
    Mr. Goodwin, do you want to go ahead?
    Keefe Reporting Company
    (618) 244-0190

    219
    1
    MR. GOODWIN: Thank you for the
    2
    opportunity to testify further in this
    3
    proceeding.
    4
    This proceeding has proven to be one of
    5
    the most confounding sets of issues that I've
    6
    wrestled with in my professional experience.
    7
    I am here today representing the American
    8
    Council of Engineer Companies of Illinois. I
    9
    may offer some comments that don't represent
    10
    review. In which case, I will endeavor to make
    11
    it clear that I am speaking from a personal
    12
    view point or that of my employer, Secor
    13
    International Incorporated. I will also remind
    14
    everybody that ACECI is constrained from making
    15
    specific recommendations regarding pricing by
    16
    antitrust law considerations. And so if there
    17
    are questions that go into that area, I will
    18
    only be able to speak on behalf of my own
    19
    company and not for the organization.
    20
    The latest changes in the Agency's
    21
    proposal are generally moving in the right
    22
    directions, but I must say there are
    23
    significant problems that remain. Going back
    24
    on my previous testimony, the changes that the
    Keefe Reporting Company
    (618) 244-0190

    220
    1
    Agency has made in their proposal regarding the
    2
    specifics of the stage one site investigation
    3
    and what must or must not be done, those
    4
    changes, I think, largely alleviate the
    5
    concerns regarding overall prescriptive. And
    6
    my sense is that we can live with the Agency's
    7
    current proposal in that regard.
    8
    But in regard to Sub letter H, we are
    9
    still plagued by the lack of clear delineation
    10
    of scope of work associated with several of the
    11
    lump sum payment provisions. As has been
    12
    testified upon at length here today, that scope
    13
    of work delineation is very critical to making
    14
    lump sum payments work. It is imperative that
    15
    this issue be resolved before any new lump sum
    16
    payment provisions are made final. It needs to
    17
    be recognized that the movement to lump sum
    18
    payments entails a shifting of an element of
    19
    risk from the UST fund to the owner/operator,
    20
    or in those cases where the consultant is
    21
    operating under an agreement with the
    22
    owner/operator to take the loss on any charges
    23
    not reimbursed, and that risk is shifted to
    24
    consultant. If that risk is significant, it
    Keefe Reporting Company
    (618) 244-0190

    221
    1
    can be minimized by making very clear what is
    2
    or isn't covered in the scope of a given phase
    3
    of work for which a lump sum payment has been
    4
    established. Unfortunately, that clear
    5
    delineation is not yet there. And my
    6
    understanding from discussions that I've
    7
    participated in with the Agency is that the
    8
    Agency does not agree that it needs to be made
    9
    more specific. Whether we're at a true impasse
    10
    on that question or not, I don't know, but
    11
    there appears to be a major gap yet there
    12
    between the Agency and the number of the
    13
    interested parties.
    14
    Another area of concern is the area -- the
    15
    Agency's introduction of the concept of
    16
    competitive bidding as an alternative way of
    17
    dealing with a atypical situation. I happen to
    18
    think that this is a constructive and probably
    19
    ultimately a sound idea, but it is a new policy
    20
    proposal. I think it is one that needs much
    21
    more consideration and discussion among the
    22
    affected parties than we've had the opportunity
    23
    to have at this point, and I don't think it's
    24
    ready for adoption yet.
    Keefe Reporting Company
    (618) 244-0190

    222
    1
    I would just make note of the fact that
    2
    the Agency has continued in its submission of a
    3
    principal job classification in its proposal
    4
    along with the corresponding hourly rates.
    5
    This was an issue that was raised in my earlier
    6
    testimony. The Agency has indicated to me that
    7
    they do not wish or intend to add that. And I
    8
    don't want to have it become the tail that wags
    9
    the dog, but it is still something that ICE
    10
    would like to see added.
    11
    Another area that is problematic is the
    12
    review and updating of the reimbursement
    13
    limits. The Agency's flat rejection of
    14
    creating a database for this purpose is
    15
    disappointing to me, and I think it's
    16
    shortsighted.
    17
    I'm not optimistic that the proposed
    18
    advisory committee will be a very successful
    19
    mechanism for accomplishing the updating when
    20
    it is needed.
    21
    I'll just point out the Agency's proposal
    22
    makes no provision for staff support for such a
    23
    group. It would only meet quarterly, four
    24
    times a year. They have no apparent financial
    Keefe Reporting Company
    (618) 244-0190

    223
    1
    resources with which to pay anybody to do
    2
    analyses of data or compilations of data. And
    3
    therefore it would be limited to whatever can
    4
    be accomplished on a volunteer basis by the
    5
    members of the advisory committee and the
    6
    constituent groups that they represent.
    7
    Frankly, I don't think that's the way to do it.
    8
    And I would not expect that to work out very
    9
    well as the means for updating the rates.
    10
    Apart from that, having the advisory
    11
    committee as a general forum for discussion of
    12
    issues of all types, considering the
    13
    underground storage tank program, I think, is a
    14
    fine idea. I don't know that the Agency
    15
    necessarily needs a Board mandate to do that.
    16
    I think they can do it on their own, if they
    17
    chose to, but certainly I have no objection.
    18
    ACECI has no objection to the establishment of
    19
    such a group, and I would expect when we
    20
    participate as one of the organizations to be
    21
    represented.
    22
    Moving on to the PIPE proposal. I've
    23
    reviewed the alternative plan, and I think it
    24
    provides a good vehicle for resolving some of
    Keefe Reporting Company
    (618) 244-0190

    224
    1
    the issues, particularly in Subpart H issues,
    2
    but obvious difficulty in defining scope of
    3
    work for the lump sum items and for attaching
    4
    the specific dollar amounts that are present in
    5
    the proposal that I place markers at this time.
    6
    Moving away from speaking for ACECI now
    7
    and speaking just for myself and from my
    8
    company, I would like to make the following
    9
    points:
    10
    First of all, there had been three
    11
    significant new policy proposals incorporated
    12
    in the Agency's latest errata sheet. The one
    13
    that I already had mentioned, the competitive
    14
    bidding is one. The proposed limit on
    15
    reimbursement to amounts to correspond to
    16
    Tier 2 cleanup objectives is another one.
    17
    Again, I think this is a concept that has
    18
    considerable merit. And I'm not sure that if
    19
    the tank owners and operators come to
    20
    understand it fully, that they will really find
    21
    themselves opposed, notwithstanding
    22
    Mr. Fleischli's comments this morning, but I
    23
    don't think we have had sufficient time to talk
    24
    about it, and think about it and the language.
    Keefe Reporting Company
    (618) 244-0190

    225
    1
    And as I indicated earlier this morning
    2
    with my question to the Agency, I'm not at all
    3
    clear on whether there is adequate statutory
    4
    basis for such a change to the regulations.
    5
    The changes can be a two-edged sword for
    6
    owner/operator. It can save money from
    7
    individual cleanups, and it can save money for
    8
    the fund. But in some cases, it can remove the
    9
    option that the owner/operator has of cleaning
    10
    up to Tier 1 levels, which may be a very
    11
    desirable thing if they're trying to sell the
    12
    property, rather than to redevelop it as a
    13
    service station. I think that needs discussion
    14
    and development and consideration before it's
    15
    ready to adopt.
    16
    The third policy initiative here that I
    17
    think needs further discussion is the one to
    18
    require cost estimates for alternative
    19
    technologies, and then limited reimbursement to
    20
    just the least cost technology, whether it be
    21
    dig and haul or one of the alternatives that
    22
    are costed out. The current Agency proposal
    23
    does not consider differences in time of
    24
    completion of the given technology. Dig and
    Keefe Reporting Company
    (618) 244-0190

    226
    1
    haul, you can get in there and get it done and
    2
    have it over with in a relatively short period
    3
    of time. Most of the alternative technologies
    4
    will take longer, and some of them may take
    5
    years to take to completion.
    6
    Not only does the Agency's proposal offer
    7
    no guidance upon how you factor in cost of
    8
    money in the analysis, it also does not
    9
    consider how you take into account the benefit
    10
    to the owner/operator, the property owner or to
    11
    the environment of getting the cleanup done
    12
    sooner, rather than later.
    13
    The Agency's proposal does not take into
    14
    consideration the greater risk of full or
    15
    likely partial failure of alternative
    16
    technologies or the risk that the cost
    17
    estimates used proves to be significant lower
    18
    than the actual costs, because not enough data
    19
    was collected prior to developing the cost
    20
    estimate to completely determine what would be
    21
    required in the alternative technology.
    22
    None of this is to say that I think this
    23
    is necessarily a bad idea. I'm simply saying
    24
    it has to be given enough time for
    Keefe Reporting Company
    (618) 244-0190

    227
    1
    consideration, and development of all of the
    2
    details that need to be in the regulation to
    3
    make sure that it works properly.
    4
    So having said all those things, my
    5
    conclusions at this stage are that we have
    6
    three new policies that need further
    7
    discussion, and we need more time to do that.
    8
    The parties are represented here in this
    9
    room. They may be far apart in a number of
    10
    different issues in this proceeding. And in my
    11
    opinion, the Board would be making a serious
    12
    error to try to promulgate a complete final
    13
    rule based on the information that is in front
    14
    of the Board right now. And the degree of
    15
    consensus has been reached in the many
    16
    different issues involved in this proceeding.
    17
    And my suggestion is that the Board should
    18
    take one of two actions. You should either
    19
    suspend this proceeding more or less
    20
    indefinitely with the request of the parties,
    21
    the Agency, and all the people in this room to
    22
    get back to work, hammer out our differences,
    23
    narrow them. If we can't, at least if we can't
    24
    reach a complete agreement, and we could then
    Keefe Reporting Company
    (618) 244-0190

    228
    1
    come back to the Board with a proposal or
    2
    proposals that don't contain so many widely
    3
    divergent views of how things should be done.
    4
    Or the other alternative would be to split
    5
    the docket, move forward with the final rule
    6
    making on those things, that where there is
    7
    reasonable -- a reasonable degree of consensus.
    8
    And I think there are many, many aspects of
    9
    this proceeding where that point has been
    10
    reached, and continue on in a separate docket
    11
    with additional hearings on the issues that
    12
    where consensus has still not been reached.
    13
    That concludes my statement.
    14
    HEARING OFFICER TIPSORD: Thank you. Any
    15
    questions for Mr. Goodwin?
    16
    MR. KING: I don't have any questions, but
    17
    just to kind of respond when we get there.
    18
    HEARING OFFICER TIPSORD: Questions?
    19
    Thank you very much. And, actually, I
    20
    can't remember if -- it's been so long
    21
    ago -- whether Mr. Fleischli specifically
    22
    talked about having another hearing or not. He
    23
    spoke to me about that on the phone when he
    24
    talked to me last Thursday.
    Keefe Reporting Company
    (618) 244-0190

    229
    1
    Ms. Manning has indicated that PIPE would
    2
    like to have another hearing to go over scope
    3
    of work, etcetera. And now we have
    4
    Mr. Goodwin. So we have not heard from the
    5
    Agency on their position. And so I offer this
    6
    opportunity for you to do so.
    7
    MR. KING: At this point, I hesitate to
    8
    see what is going to transpire at an additional
    9
    hearing, given where we're at. I mean, we
    10
    think we have made changes that were
    11
    appropriate.
    12
    We've heard that there's some agreement on
    13
    some of the Subpart H things, there's some
    14
    disagreement on other parts. Generally, people
    15
    were in agreement with the bidding provisions,
    16
    but Mr. Goodwin has indicated disagreement with
    17
    that. So we've got people complaining about
    18
    the unit rates. We've got people complaining
    19
    about the bidding process. And yet we're in a
    20
    position where for many years, we had run this
    21
    program based on internal guidelines. And the
    22
    Board, as a clear exercise of its authority, in
    23
    the Ehrends (sp) case said that was not
    24
    appropriate for us to do any more, and so we
    Keefe Reporting Company
    (618) 244-0190

    230
    1
    haven't. So we don't have internal guidelines
    2
    that we're running a reimbursement program on.
    3
    We don't have any rules in effect. And to me,
    4
    that's not good public administration.
    5
    I think if the Board sees that there's
    6
    some weaknesses in the record -- you know, for
    7
    instance, I was hearing complaints about the
    8
    excavation, transport and disposal numbers.
    9
    Well, if the Board looks at the record and
    10
    says, well, we don't think those numbers are
    11
    justified, maybe the solution is just you bid
    12
    all of that out, bid it all out, and that would
    13
    be a result.
    14
    At this point, I don't know what we're
    15
    going to do at another hearing. What I would
    16
    suggest is that the Board take the record
    17
    that's at hand and proceed to first notice.
    18
    And then at that point, certainly that
    19
    is -- it's happened many times where the Board
    20
    has had -- at hearings, developed the record,
    21
    had first notice, and then had hearings with
    22
    regard to its first notice proposal. I think
    23
    that would certainly be much more useful than
    24
    for us to come back in a week to two weeks,
    Keefe Reporting Company
    (618) 244-0190

    231
    1
    because that wouldn't be sufficient time for
    2
    notice. But to come back in 30 days, in 60
    3
    days and not be any closer than we are now, I
    4
    don't see that that would be really useful.
    5
    And then the Agency continues to
    6
    administer a program without any rules, which I
    7
    don't think is the appropriate solution either.
    8
    So my recommendation would be that the
    9
    Board take the record that has been presented,
    10
    which is voluminous, and proceed to first
    11
    notice, and then schedule hearings based on
    12
    that, based on that first notice proposal.
    13
    HEARING OFFICER TIPSORD: Thank you.
    14
    BOARD MEMBER GIRARD: Well, I have a
    15
    question on those comments. It does seem like
    16
    there's been a lot of progress during the
    17
    course of these hearings, in the meetings you
    18
    had with PIPE and with the other firms and
    19
    individuals in terms of coming closer on
    20
    Subpart H. Even the bidding process sounds as
    21
    if it's palatable to most of the players.
    22
    It seems like the area that still has the
    23
    most outstanding issues and probably the
    24
    largest issues is, you know, the Subsection 845
    Keefe Reporting Company
    (618) 244-0190

    232
    1
    with professional consulting services, those
    2
    lump sum payments for a specific task.
    3
    Are you saying that the Agency has reached
    4
    a point where they don't feel that there's any
    5
    need to have any more discussion between the
    6
    affected parties, that the figures that you've
    7
    got are the best at this point in time?
    8
    MR. KING: Well, we've had these numbers
    9
    in the public record since January. And today
    10
    was the first time I've seen numbers in
    11
    response put back into the record here, and I'm
    12
    not sure if he even covers all these items.
    13
    You know, so if we're going to see more
    14
    numbers in an expeditious way, that they're
    15
    going to have some support for them, we would
    16
    certainly be willing to look at those. I guess
    17
    I don't know what we're going to see. I mean,
    18
    we've been waiting a long time, and we haven't
    19
    seen much in the way of responses. So I don't
    20
    know what the intentions are from PIPE or how
    21
    quickly we're going to receive any kind of
    22
    response.
    23
    HEARING OFFICER TIPSORD: Mr. Mullen?
    24
    MR. MULLEN: Scott Mullen again. I just
    Keefe Reporting Company
    (618) 244-0190

    233
    1
    wanted to ask the question to the Board; does
    2
    the Board understand why you haven't received
    3
    numbers from PIPE on these large engineering
    4
    lump sum items? It's truly only because there
    5
    is no defined scope of work. That's okay,
    6
    because that's what we would like to see done.
    7
    BOARD MEMBER JOHNSON: Well, that's in
    8
    fact the question I had. It seems as though
    9
    we've got lots of testimony and a huge record
    10
    on both sides of most issues, and in fact, I
    11
    think enough to make a decision on most issues.
    12
    There's been concern about the Board adopting
    13
    rules that are contrary to state and federal
    14
    law not in the habit of doing that. We're
    15
    supposed to ask -- we've got a legal staff who
    16
    can help us make sure that we don't wrongfully
    17
    adopt rules that are in contradiction to state
    18
    statute.
    19
    My big question was, it is the Agency's
    20
    position that there's no need to work in
    21
    further defining the scope of work in these
    22
    particular areas? Or is that something that
    23
    you think you can make some headway over the
    24
    next couple of weeks?
    Keefe Reporting Company
    (618) 244-0190

    234
    1
    MR. CLAY: I think it's our position that
    2
    there's nothing more we need to do as part of
    3
    defining the scope of work. I mean, the LUST
    4
    rules that we have proposed, it's what it takes
    5
    to put together a plan of report. It is the
    6
    same in water, in air and in other portions of
    7
    land. I mean, that's the way the regulations
    8
    are written. What it takes to get an approved
    9
    plan, budget, in our case, and report. I mean,
    10
    that's, you know, the scope of work, if you
    11
    will.
    12
    BOARD MEMBER JOHNSON: Thank you.
    13
    BOARD MEMBER GIRARD: So but in other
    14
    words, what you're saying is, you don't feel
    15
    that you're going to delineate the scope of
    16
    work any further than you already have? I
    17
    mean, you've got a scope of work in there.
    18
    It's just that it's a very broad scope of work?
    19
    MR. CLAY: Correct.
    20
    MR. KING: And we have made a couple of
    21
    changes. In response to Mr. Goodwin's
    22
    testimony, we simplified stage one, and we
    23
    clarified some of the well survey procedures as
    24
    we talked about today as well. So we have made
    Keefe Reporting Company
    (618) 244-0190

    235
    1
    those changes.
    2
    HEARING OFFICER TIPSORD: Was there anyone
    3
    else who wanted to comment on that?
    4
    You know what; let's take a very brief
    5
    break, five minutes, because we're returning up
    6
    on 4:30. So let's take five minutes.
    7
    (WHEREBY A SHORT BREAK WAS
    8
    TAKEN.)
    9
    HEARING OFFICER TIPSORD: I think we're
    10
    ready to go back on the record.
    11
    Is there any additional comment regarding
    12
    whether or not there's a need for another
    13
    hearing at this time? Go ahead.
    14
    MS. MANNING: Prior to going to first
    15
    notice?
    16
    HEARING OFFICER TIPSORD: Yes.
    17
    MS. MANNING: I think Dan Goodwin gave a
    18
    good reason to have another hearing prior to
    19
    going to first notice. And I think PIPE feels
    20
    as well that there's more work to be done in
    21
    this proposal.
    22
    HEARING OFFICER TIPSORD: Could PIPE have
    23
    something ready in, say, 30 days?
    24
    MS. MANNING: Yes.
    Keefe Reporting Company
    (618) 244-0190

    236
    1
    HEARING OFFICER TIPSORD: Would it be -- I
    2
    guess the problem I'm having right now is that
    3
    what I see coming -- and even with what you had
    4
    to say, Mr. Goodwin, the three areas you talked
    5
    about specifically, Mr. Goodwin, the type of
    6
    scope of work and proposed Subpart H numbers.
    7
    I guess my question is, do we need a hearing
    8
    for you to continue that dialogue? Or can we
    9
    give you, let's say, 30 days after the
    10
    transcript comes in, in this hearing, before
    11
    final comments are due -- that doesn't mean
    12
    that you all can't have a dialogue during that
    13
    time.
    14
    I guess the thing is, is I don't want to
    15
    schedule another hearing for PIPE to hand me 10
    16
    more exhibits, and the Agency say we don't have
    17
    any questions; we're okay with everything. You
    18
    know, I'm not sure that's the best use of our
    19
    resources at this time.
    20
    We've had some excellent hearings. We've
    21
    had some excellent information come in. I
    22
    guess where I'm sort of leaning is, wondering
    23
    if we shouldn't go ahead and have the
    24
    transcript come in, and in 30 days have a round
    Keefe Reporting Company
    (618) 244-0190

    237
    1
    of comments and see where we are when those
    2
    comments come in as to whether or not the
    3
    dialogue is sufficient, that we don't need
    4
    another hearing. Or if we do need another
    5
    hearing before first notice, perhaps looking at
    6
    it at that point. I sort of opened that up for
    7
    comments.
    8
    MS. MANNING: That makes sense to me.
    9
    MR. GOODWIN: I think that makes sense.
    10
    My only feeling isn't so much that we need more
    11
    hours in the hearing room, but I think we need
    12
    time to continue the dialogue about the Agency
    13
    language on several issues. And if that
    14
    doesn't really lead us to a consensus on the
    15
    language, maybe it will at least narrow things.
    16
    I do have a little bit of concern about
    17
    whether proposed alternative language that we
    18
    might submit later on will be given the same
    19
    weight as things that have been available for
    20
    question and answer at a hearing format. But,
    21
    you know, I'll defer to the Board on that.
    22
    HEARING OFFICER TIPSORD: Well, certainly
    23
    on that point, if there's proposed alternative
    24
    language, if you still feel a need for a
    Keefe Reporting Company
    (618) 244-0190

    238
    1
    hearing, that could be included in your final
    2
    comments. And then I or the Board can make the
    3
    decision based on those comments and where we
    4
    feel we're at, at that point.
    5
    MR. GOODWIN: That's fine.
    6
    HEARING OFFICER TIPSORD: All right.
    7
    Well, then, let's do it this way then. Let's
    8
    plan on comments due 45 days from today.
    9
    That's assuming 14 days from the transcript and
    10
    30 days beyond that. I'll give you 45 days
    11
    from today. I'll put a hearing officer order
    12
    out that gives a specific date, but it will be
    13
    45 days. So it will be approximately
    14
    September, about the end of September, in that
    15
    area. No. This is August already. Yeah, the
    16
    beginning of September. I'll put out a hearing
    17
    officer order with the specific date and make
    18
    sure it gets to everyone, and we'll proceed at
    19
    that point.
    20
    I really do appreciate all the comments,
    21
    all the cooperation we're seeing. I think
    22
    we're really getting to a good working proposal
    23
    here, and I'm looking forward to continuing to
    24
    work with all of you.
    Keefe Reporting Company
    (618) 244-0190

    239
    1
    Mr. Girard, do you have anything?
    2
    BOARD MEMBER GIRARD: No. Thank you. I'd
    3
    just like to echo the comments of the hearing
    4
    officer. I think this has been a very good
    5
    rule making, in that we've continued to get
    6
    closer and closer, and we certainly narrowed
    7
    the gap considerably.
    8
    Eventually at some point, the Board is
    9
    going to have to make a decision and put out a
    10
    first notice. And that doesn't mean that there
    11
    won't be continued discussion after that point,
    12
    but I think we're getting a lot closer than we
    13
    were back at the first hearing. So thank you
    14
    very much.
    15
    HEARING OFFICER TIPSORD: All right. Then
    16
    we'll have comments in 45 days. And thank you
    17
    very much. We're adjourned.
    18
    (End of proceedings.)
    19
    20
    21
    22
    23
    24
    Keefe Reporting Company
    (618) 244-0190

    240
    1
    C E R T I F I C A T E
    2
    3
    4
    I, Ann Marie Hollo, CSR, RMR, do hereby
    5
    certify that the foregoing proceedings came
    6
    before me on August 9, 2004, held in the
    7
    Department of Natural Resources building,
    8
    Illinois State Fair Grounds, Springfield,
    9
    Illinois, and was taken in shorthand by me and
    10
    later transcribed into computer-aided
    11
    transcription under my supervision, and that
    12
    the said proceedings is a true record of the
    13
    proceedings.
    14
    IN WITNESS WHEREOF, I have hereunto
    15
    subscribed my name and affixed my seal this
    16
    16th day of August, 2004.