ILLINOIS POLLUTION CONTROL BOARD
    December 19, 1996
    SHELL OIL COMPANY,
    Petitioner,
    v.
    ILLINOIS ENVIRONMENTAL
    PROTECTION AGENCY,
    Respondent.
    )
    )
    )
    )
    )
    )
    )
    )
    )
    )
    PCB 97-99
    (Waterwell Setback Exception)
    ORDER OF THE BOARD (by J.Yi):
    On December 5, 1996, the Board received from Shell Oil Company (Shell) a petition
    for Waterwell Setback Exception. The request concerns Shell’s facility located at 9560 West
    159
    th
    Street, Orland Park, Cook County, Illinois. This matter is accepted for hearing.
    The hearing must be scheduled and completed in a timely manner. The Board will
    assign a hearing officer to conduct hearings consistent with this order, and the Clerk of the
    Board shall promptly issue appropriate directions to that assigned hearing officer.
    The assigned hearing officer shall inform the Clerk of the Board of the time and
    location of the hearing at least 40 days in advance of hearing so that public notice of hearing
    may be published. After hearing, the hearing officer shall submit an exhibit list, a statement
    regarding credibility of witnesses and all actual exhibits to the Board within five days of the
    hearing.
    If after appropriate consultation with the parties, the parties fail to provide an
    acceptable hearing date or if after an attempt the hearing officer is unable to consult with the
    parties, the hearing officer shall unilaterally set a hearing date in conformance with the
    schedule above. The hearing officer and the parties are encouraged to expedite this proceeding
    as much as possible.
    IT IS SO ORDERED.
    I, Dorothy M. Gunn, Clerk of the Illinois Pollution Control Board, hereby certify that
    the above order was adopted on the _____ day of ___________, 1996, by a vote of
    ______________.

    ___________________________________
    Dorothy M. Gunn, Clerk
    Illinois Pollution Control Board