ILLINOIS POLLUTION CONTROL BOARD
March 16, 1995
KALO GASOLINE COMPANY,
)
)
Petitioner,
v.
)
PCB 95—41
PCB 95—74
ILLINOIS ENVIRONMENTAL
)
(Consolidated)
PROTECTION AGENCY,
)
(UST
-
Appeal)
)
Respondent.
ORDER OF THE BOARD (by C.A. Manning):
This matter is before the Board on two motions for summary
judgment which were both filed by the Illinois Environmental
Protection Agency (Agency). The first motion, filed in PCB 95-41
on February 24, 1995, challenges only those portions of Kalo
Gasoline Company’s (Kalo) petition for review concerning “early
action” activities conducted at Kalo’s UST site. The Agency
argues that PCB 95-41 was brought for the purpose of challenging
the Agency’s December 16, 1994 final determination rejecting
Kalo’s Site Classification Completion Report, and at the time
the petition for review was filed on January 20, 1995, the Agency
had not made a decision on the issue of early action activities.
The Agency subsequently made a decision on Kalo’s submission of
early action costs on January 27, 1995.
In an attempt to cure the Agency’s concerns regarding the
timing and ripeness of the issue of “early action costs”, on
March 3, 1995, Kalo filed a second appeal solely challenging the
Agency’s January 27, 1995 decision denying early action costs in
amount of $56,000. This case is docketed as PCB 95—74 and was
consolidated with PCB 95-41 on March 9, 1995. The Agency’s
second motion for summary judgment essentially argues that
summary judgment is proper in this second appeal because the
Environmental Protection Act, 415 ILCS 5/57.6(b), prohibits
reimbursement for early action activities when they are conducted
after the submission of site classification plans to the Agency.
(3/13/95 Agency Motion at 2.)
Regarding the partial motion for summary judgment in PCB 95-
41, to which Kalo has not filed a response, Kalo does state in
its second petition for review, PCB 95-74, that it believes the
Agency’s motion for partial summary judgment to be moot. (PCB
95-74 Petition at 2.) We agree. Because Kalo timely filed a
petition for review of the Agency’s final determination regarding
early actions costs (PCB 95-74), an appeal which was consolidated
with PCB 95-41, the issue of early action costs is now properly
before the Board. The Agency’s motion is, therefore, moot.
2
Regarding the motion for summary judgment in PCB 95-74, no
response has yet been filed but the response time of seven days
has not yet expired. However, because this matter is scheduled
for hearing on April 12, 1995, we find that undue delay or
prejudice may result if the motion for summary judgment is not
now addressed. (35 Ill. Adm. Code 101.241.)
The Agency argues that Section 57.6(b) is a bar to
reimbursement if early action is performed after a site
classification plan is submitted. We disagree. Section 57.6(b)
allows an owner or operator the latitude to perform early action
activities, including tank removal, without having to go through
a plan—submittal process before the Agency. On its face, Section
57.6(b) is not necessarily a bar to reimbursement as the Agency
contends. Instead, seeking reimbursement from the UST Fund is
limited by Section 57.5(a), which provides that costs will not be
reimbursed if they exceed the minimum requirements necessary to
comply with this Environmental Protection Act and by the Board’s
regulations governing early action at 35 Ill. Adm. Code 732.200
et
seq.
Thus, factual issues remain for hearing such as whether
the early action performed by Kalo exceeded the minimum
requirements necessary to comply with the Environmental
Protection Act or whether the activities performed at the site
constitute “early action.” Summary judgment in PCB 95—74 is
therefore denied.
IT IS SO ORDERED.
I, Dorothy M. Gunn, Clerk of the Illinois Pollution Control
Boa~, hereby certify that the above order was adopted on the
/~‘
day of
7~
~
,
1995, by a vote o~
-~1~
I
/
Dorothy M.iGunn, Clerk
Illinois 1?1ollution Control Board