ILLINOIS POLLUTION CONTROL BOARD
    September 1, 1994
    CITIZENS UTILITY COMPANY
    )
    OF ILLINOIS,
    Petitioner,
    v.
    )
    PCB 94—199
    )
    (Permit Appeal)
    ILLINOIS ENVIRONMENTAL
    )
    PROTECTION AGENCY,
    )
    Respondent.
    ORDER OF THE BOARD (By E. Dunham):
    On August 25, 1994, the Illinois Environmental Protection
    Agency (Agency) filed a “Motion for Extension of Time to Answer”.
    The Agency requests an extension until March 31, 1995 to file its
    answer. The deadline in this matter has been waived through July
    1, 1995. The parties are presently involved in discussions
    towards resolution of the issues on appeal. The Agency contends
    that the filing of the answer is not necessary at this time. The
    Agency believes that filing of the answer by March 31, 1995 will
    allow sufficient time for notice, briefing and decision by the
    Board. The Agency indicates that petitioner has no objection to
    the extension.
    The Board encourages negotiated settlements of permit
    appeals, and does not object to the grant of an extension of time
    for filing the Agency’s answer. The Board, however, also
    encourages expeditious resolution of cases before it. Granting
    an extension of seven months for filing an answer may provide
    excessive delay if the parties become aware that negotiations are
    not going to lead to a workable settlement.
    The Board therefore grants the Agency’s motion for an
    extension of time to file an answer subject to the following
    conditions:
    1. The Agency must file its answer within 30 days of any
    party’s request for a hearing in this matter.
    2. The Agency’s answer must be filed no later than March 31,
    1995.
    IT IS SO ORDERED.

    2
    I, Dorothy M. Gunn, Clerk of the Illinois Pollution Control
    Board hereby certify that the a~oveorder was adopted on the
    ~
    day of
    ~
    ,
    1994, by a vote of
    ~
    Dorothy N. c14n, Clerk
    Illinois Pollution Control Board

    Back to top