ILLINOIS POLLUTION CONTROL BOARD
    December 2, 1993
    WILMER BROCKNAN, JR.
    AND
    FIRST MIDWEST BANK OF JOLIET
    )
    AS TRUSTEE UNDER TRUST NO. 757,
    )
    )
    Petitioner,
    )
    v.
    )
    PCB 93—162
    (Permit Appeal)
    ILLINOIS ENVIRONMENTAL
    )
    PROTECTION AGENCY,
    )
    )
    Respondent.
    ORDER OF THE BOARD (by G. T. Girard):
    On November 24, 1993, the Board received a motion for
    summary judgement filed by Illinois Environmental Protection
    Agency (Agency). The Board has not received a response from
    petitioner and the response time pursuant to Section 101.241 has
    not run. However, a hearing is scheduled for December 6, 1993,
    and the Board finds that undue delay would result if the Board
    does not rule today.
    The Board notes that there are several factual issues
    presented in this permit appeal. For example, based on a reading
    of the petition for appeal and the Agency’s motion, there is an
    issue as to whether the entire facility was closed or whether
    only a portion of the facility closed in 1982. Further, the
    Agency deemed the instant application for permit not filed
    “because it lacked the information, documents, and authorizations
    in the form”. (Mot. at 1.) Therefore, the Board finds that
    there are genuine issues of fact to be resolved in this
    proceeding. The motion for summary judgement is denied.
    IT IS SO ORDERED
    I, Dorothy N. Gunn, Clerk of the Illinois Pollution Control
    Board, here~ycertify that the( above order was adopted on the
    _________________
    day of
    ~
    ,
    1993, by a vote
    of ~
    .
    /
    7/
    _~//J’/_~
    /~:
    /
    -
    ~
    ~‘--
    ~
    -
    -Dorothy N. ~unn, Clerk
    Illinois Pollution Control Board