ILLINOIS POLLUTION CONTROL BOARD
February 7, 1991
Shell OIL COMPANY,
)
Petitioner,
V.
)
PCB 91—24
(Provisional Variance)
ILLINOIS ENVIRONMENTAL
)
PROTECTION AGENCY,
Respondent.
ORDER OF THE
BOARD
(by J. C. Marlin):
This matter comes before the Board upon receipt of an Agency
Recommendation dated February 5, 1991. The recommendation refers
to a request from Petitioner, Shell Oil Company for a 30 day
provisional variance from the 90—day on—site limitations for
hazardous wastes set forth in 35 Ill. Adm. Code 722.134(b).
Upon receipt of the request the Agency issued its
recommendation, finding that the hazardous wastes must remain on—
site for longer than 90 days due to unforeseen, temporary and
uncontrollable circumstances and failure to grant the requested
30—day provisional variance would impose an arbitrary or
unreasonable hardship on Petitioner.
The responsibilities of the Agency and the Board in these
short—term provisional variances are different from the
responsibilities in standard variances. See Ill. Rev. Stat.
1989, ch. 1l1~,pars. 1035(b) & (c). In provisional variances it
is the responsibility of the Agency to make the technical
determinations and finding of arbitrary or unreasonable
hardship. The Boardts responsibility is to adopt a formal Order,
to assure the formal maintenance of the record, to assure the
enforceability of the variance, and to provide notification of
the action by a press release.
Having received the Agency recommendation finding that a
denial of the request relief would impose an arbitrary and
unreasonable hardship the Board hereby grants Petitioner a
provisional variance from 35 Ill. Mm. Code 722.134(b) from
January 8, 1991 to February 7, 1991.
IT IS SO ORDERED.
B. Forcade and J. Theodore Meyer concurred.
118—293
—2—
I, Dorothy M. Gunn, Clerk of the Illinois Pollution Control
Board, hereby certify that
above Order was adopted on
the ?~‘ day of
-ç
,
1991, by a
vote of
_________.
Dorothy M. ~(inn,Clerk
Illinois Pollution Control Board
118—294