ILLINOIS POLLUTION CONTROL BOARD
    July 11, 1985
    CITY OF SYCAMORE,
    Petitioner,
    v.
    )
    PCB 83—172
    ILLINOIS ENVIRONMENTAL
    )
    PROTECTION AGENCY,
    Respondent.
    MR. CHARLES L. FIERZ, CITY ATTORNEY, APPEARED ON BEHALF OF
    PE~TITIONER; and
    MR. E. WILLIAM HUTTON and MR. THOMAS DAVIS, ATTORNEYS, APPEAREI.J
    ON BEHALF OF RESPONDENT.
    OPINION AND ORDER OF THE BOARD (by J. Anderson):
    This matter comes before the Board on a petition filed by
    the City of Sycamore (Sycamore) requesting a variance from 35
    Ill. Adm. Code 306.304 in order to modify its NPDES permit to
    allow a sanitary sewer bypass pursuant to 35 Ill. Adm. Code
    309.184. The original petition was filed on November 17, 1983
    and then amended pursuant to Board orders for more information on
    January 17, 1984, March 12, 1984 and July 3, 1984. Supplementary
    information was filed on November 14, 1984.
    The Illinois Environmental Protection Agency (Agency) made
    several recommendations and motions that the petition be denied
    or dismissed for lack of information. Agency Rec., April 16,
    1984 (recommending denial); Agency Motion to Dismiss, August 1,
    1984 (no action taken, J. Anderson dissenting, August 2, 1984);
    Agency Second Rec., August 20, 1984 (recommending denial or
    dismissal); Agency Supplemental Motion to Dismiss, December 20,
    1984.
    The Agency’s Supplemental Motion to Dismiss was taken up at
    the Board’s January 10, 1985 meeting. However, the motion failed
    to muster the four affirmative votes required under 35 Ill. Adm.
    Code 101.109 to become a “final determination.” Consequently, no
    action was taken on the motion and the case proceeded to
    hearing. Hearing was held on January 28, 1985 and briefs were
    subsequently filed by the Petitioner on May 1, 1985 and by the
    Agency on June 3, 1985.
    Before discussing the variance petition itself, it is
    necessary to address an objection raised by the Agency to the
    admission of a written study prepared by Sycamore’s present
    65-11

    —2—
    engineering consultants, Greeley and Hansen, on the grounds that
    it is hearsay (R. at 126—7). The Agency also objects to each
    anh
    every exhibit tendered by the City at hearing on the grounds of
    hearsay and lack of foundation.
    The Agency argues that the Hearing Officer improperly
    received this evidence contrary to the dictates of 35 Iii. Adm.
    Code 103.204 (Ag. Brief in Opp. at 2). Section 103.204 provides
    that Hearing Officers “shall receive evidence which is admissable
    under the rules of evidence as applied in the Courts of Illinois”
    and “may receive evidence which is material, relevant and would
    be relied upon by reasonably, prudent persons in the conduct of
    serious affairs
    . .
    First, the Board notes that Sycamore claims that the report
    was not offered to prove the truth of the matter asserted
    therein, but only to illustrate what steps were being taken to
    correct the City’s overflow problems. Assuming however that the
    study was submitted as proof of the facts therein, it does
    constitute hearsay. The Board finds, however, that it was
    properly admitted under Section 103.204 as material and
    relevant. The Board notes that the Agency itself made a written
    cequest for the entire report (Second Rec. at par. 2) which
    request was apparently met (R. at 34—5). The Board also finds
    that the rest of the exhibits were properly admitted under this
    Section.
    The City of Sycamore is located in Dekalb County,
    Illinois. Sycamore has a sanitary sewer system and owns and
    operates three wastewater treatment plants at two locations, the
    North Site and the South Site. According to the Greeley and
    Hansen report, the rated capacities of. each of the plants, in
    millions of gallons per day (MGD), is as follows:*
    Plant
    Flow Rate
    Design
    Design
    Average
    Maximum
    North Site
    Original Plant
    0.8
    2.5
    New Plant
    3.5
    9.64
    South Site
    Southwest Plant
    .45
    1.0
    The plants serve a population of approximately 9,800. The
    subject of this petition are the two plants, the “original” and
    *At the outset, the Board wishes to note that where information
    supplied by the City is unclear or contradicted by other filings
    made by the City, the Board has generally referred to that
    information submitted last in time.
    65-12

    —3—
    “sew” plants, located at the North Site. These facilities
    generally consist of two largely separate treatment plants with
    grit removal, primary clarifiers, aeration tanks and final
    clarifiers. While the design average flow (DAF) to these two
    plants is 4.3 MGD the actual average daily flows to the site
    range from 1.0 to 1.5 MGD, far below the rated capacity.
    Sycamore explains that two water—intensive industries, with a
    combined impact of 0.9 MGD, have departed from the City (Third
    Am. Pet. at 2). Since both plants were not needed, all flow was
    sent to the new plant and the original plant was taken out of
    service. The new plant is more than adequate to handle all
    normal dry weather flows and in fact, produces effluent of a
    higher quality than that mandated by its NPDES permit (Second
    Rec. at par. 13). However, during wet weather flows, shortfalls
    in capacity at the new plant occur which the City contends
    results in sewer surcharging and the subsequent back—up of sewage
    in basements. Consequently, the City requests a variance to
    permit the use of a 24 inch diameter bypass pipe during periods
    of extreme wet weather to “Martin’s Ditch” which is a tributary
    of the East Branch of the Kishwaukee River.* The variance is
    requested for five years or until rehabilitation or
    reconstruction of the system is accomplished.
    The cause of the sewer surcharging and subsequent basement
    flooding, and whether the bypass will, in fact, alleviate these
    problems is vigorously disputed by the Agency. Moreover, the
    Agency contends that the petition should either be dismissed or
    denied because Petitioner has not met its burden of proof.
    Specifically, the Agency points to the lack of a definite
    compliance plan, and an inadequate consideration of 1) possible
    measures to minimize any adverse impact; 2) the extent of any
    environmental impact; and 3) possible compliance alternatives.
    Apparently, the City has had basement flooding problems
    which predate construction of the new plant (R. at 14). However,
    the City contends that the new plant, which was intended to
    ameliorate the flooding, has only exacerbated it (R. at 14). The
    plant was constructed with grant funding pursuant to an
    engineering study prepared by W. Duechier and Associates. The
    study concluded that there was excessive infiltration and inflow
    (I/I) in the collection system and recommended 1) reduction of
    1/I on cost—effective basis; 2) construction of a new treatment
    plant at the North Site; 3) expansion of the North Cross Street
    Pumping Station; and 4) replacement of the old Parkmoor Lift
    Station with a new East Interceptor (Greeley and Hansen report
    at 3).
    *Additionally, the City requested that it be able to use eleven
    existing small portable pumps as well as a 10” portable pump but
    conceded that this request should be dismissed. (Objections to
    Motion to Dismiss, August 13, 1984). Accordingly, the Board
    dismisses the requested relief with respect to these pumps.
    65-13

    4—
    The City contends that the whole system is now a “lemon”
    because during at least two rainfalls “extensive, tragic, flooded
    basements occurred”. (Pet. Brief at 2). According to the City,
    sewer surcharging occurs during wet weather because the entire
    system was not designed for peak hourly flows. Inadequate
    capacity exists at the treatment plant, pumping station,
    interceptor sewers and lift station (R. at 35). For instance,
    the design maximum pumping capability at the North Site is 18.16
    MGD and the peak flow rate during a 2.9 inch rainfall is 25 MGD
    (Third Am. Pet, at 3). The Board will not reiterate here all of
    the alleged design shortfalls.
    The City further contends that all cost—effective I/I has
    already been eliminated to no avail and thus, has concluded that
    “only massive reconstruction of the entire system offers a real
    cure.” (Pet. Brief at 6). A schedule for compliance was
    submitted as follows:
    ITEM
    DATE COMPLETED
    Research and Report on Design Error
    August 1984
    Planning and Report on Various
    January 1986
    Alternatives and Solutions to Problems
    with Cost—Effective Analysis
    Design of Excess Flow Facilities
    July 1987
    and/or Flow Reduction Measures
    Construction of Excess Flow Facilities
    July 1989
    and/or Flow Reduction Measures
    The only cost estimate provided was that of an 8.0 million gallon
    bypass storage tank estimated at $2.7 million.
    The City contends that the schedule as submitted is the only
    responsible course of action. The City asserts that it is
    committed to a long term solution but that it needs time to
    develop its alternatives. As proof of its commitment the City
    has proffered a study prepared by its new engineering
    consultants, Greeley and Hansen. However, this engineering study
    concerns itself solely with alleged design flaws made by the
    previous engineers. While the identification of possible flaws
    may be a necessary prelude to correcting the overall problem, the
    study fails to demonstrate what positive steps will be taken to
    correct the problem as required by the Illinois Environmental
    Protection Act (Act). The Board notes that this petition has
    been pending for close to two years without any progress towards
    a compliance plan.
    The Agency is correct in maintaining that a compliance plan
    is to be submitted as part of the petition and not developed over
    the pendency of the variance itself, Modine Manufacturing
    Company v. IEPA, PCB 79—112 (August 18, 1982). The compliance
    65-14

    —5—
    plan, as submitted, does not satisfy this requirement. In
    reality, the plan is nothing more than a vague sketch which fails
    to commit the City to a specific course of action. In specific
    instances, where there is no apparent solution to the problem,
    compliance plans may include time for research leading to an
    ultimate but as yet unidentified resolution. However, in this
    instance, sufficient time to study as well as develop a
    compliance plan has already transpired. The “plan” also fails
    because no explanation is given as to why it will take five years
    to correct the problem or why the time intervals between each
    “step” are so lengthy. The Board finds the City’s failure to
    proceed with a permanent solution surprising in light of the long
    history and gravity of the situation.
    Also surprising is the City’s apparent failure to take into
    account possible measures to alleviate the impact of the flooding
    on its residents and on the environment. For instance, the
    Agency feels that the old plant could be better utilized to
    provide some level of treatment for at least 18.16 MGD. The City
    states that the old plant is used during wet weather but its
    usefulness cannot be determined without re—engineering studies
    (Third Am. Pet. at 3). The Agency also contends that an
    aggressive program to reduce illegal connections and seal leaking
    manholes would have a positive impact and is a relatively low—
    cost measure available to the City in the interim. While the
    estimated maximum total daily I/I during wet weather was about
    12.34 MGD, only 1.44 MGD was eliminated during the sewer
    rehabilitation program. More than 70 percent of the I/I was
    unlocated and “speculated to be on private property and beyond
    the scope of the study” (Greeley and Hansen report at 8). As
    early as 1976 it was known that an estimated 1,200 footing drains
    were connected to the sanitary sewer system at unidentified
    locations (Ex. E at 39). The City’s failure to investigate and
    eliminate these sources of I/I, then and now, remains
    unexplained. While the City initially had professed to commit
    itself to eliminating excess I/I as part of this variance, by the
    hearing date this plan had been abandoned in favor of
    investigating “design flaws”. Given the apparent extent of
    Sycamore’s I/I and the relative ease, low cost and timely results
    which could be expected from an aggressive program to reduce it,
    the City’s explanation for rejecting the program is simply
    unconvincing.
    The City apparently sees its dilemma as either bypass and
    “kill a few fish” or risk the health and safety of its citizens
    (R. at 118—120). However, because the bypassing does not cure
    basement flooding the City continues to risk both its residents
    and the environment. The City has made no formal assessment of
    the environmental impact of its bypassing activities. The City
    simply argues that any environmental impact will be minimal
    because the bypasses are expected to occur only once or twice
    yearly and at such times when the Kishwaukee is at extremely high
    water levels. The City estimates the dilution ratio during these
    occasions to approach 5000 to 1. It expressly rejects the
    65-15

    —6—
    necessity of performing a more detailed impact analysis because
    it argues that this would entail breaking the very regulations
    from which the variance is sought (R. at 39). The Board rejects
    this argument as specious; bypassing activities have been going
    on for a number of years, each event presented an opportunity for
    data gathering.
    The Agency questions Sycamore’s conclusions that any
    environmental impact would be minimal. The Agency feels that the
    petition grossly underestimates the actual amount of bypassing
    and that the dilution ratio provided is unreliable since it is
    founded on only one date. The Board also notes that the dilution
    ratio, on its face, appears highly questionable. Also lacking is
    a plan of operation for the bypass. Limitations as to how much
    and how often is to be bypassed under various rainfall conditions
    are necessary to minimize the environmental impact attendant with
    bypassing raw sewage. The Act requires that Sycamore do more
    than make conclusory statements as to the “minimal” effect on the
    K ishwaukee.
    The crux of Sycamore’s hardship claim is that its faulty
    sewer and treatment system causes basement back—ups and that j~~o
    facto bypassing is justified to protect the health and welfare of
    its citizens. The Board notes that the first flooding incident
    attributed to the new plant occurred on May 23, 1983, over 2
    years ago, and yet the City has not proceeded to identify a
    viable compliance option, much less embark on a course toward its
    implementation. Moreover, the City apparently intends to take no
    measures to alleviate the continuing impact of the sewer
    surcharging on its residents while developing options. As
    previously noted, the relatively low—cost alternative of reducing
    excessive I/I has been expressly rejected. The Board is highly
    concerned about Sycamore’s declared resistance to active pursuit
    of any interim measures, which would alleviate the plight of its
    residents during heavy storm conditions, other than a crisis
    response that, at best, only partially addresses the potential
    health and other problems resulting from basement backups, and
    fails to address the environmental consequences at all.
    Compounding the situation is Sycamore’s less than aggressive
    pursuit of a compliance plan to ultimately cure the problem.
    Consequently, it appears that much of Sycamore’s hardship is
    self—imposed.
    Even were the Board to ignore the gross factual deficiencies
    in this variance petition, a grant of variance would be
    inappropriate and, indeed, could serve to aggravate the
    problem. Any variance which would be granted by the Board would
    require interim compliance measures and demonstrable progress
    towards ultimate compliance: the record makes clear that these
    essential conditions of the variance have already been either
    rejected or resisted by Sycamore. To grant the type of variance
    as requested by Sycamore, thus fostering Sycamore’s otherwise
    non—complying actions and removing the threat of enforcement,
    would be an unacceptable encouragement of the status quo.
    65-16

    —7—
    The City asserts that “to not grant a hardship variance to
    the City of Sycamore would be manifestly inconsistent and unjust”
    relying on variances granted by the Board in City of Farmington
    v. IEPA, PCB 83—63, October 6, 1983; Village of Bourbonnaisv.
    IEPA, PCB 83—71, October 19, 1983; village of Seneca v. IEPA
    PCB 83—76, November 18, 1983 (City’s Brief at 4—5). However, the
    petitioners in the above matters were in substantially different
    circumstances than Sycamore and succeeded in meeting their burden
    under the Act.
    In the City of Farmington, a variance for bypassing was
    granted to allow the City to conduct a flow monitoring study.
    The bypassing was simply the only mechanism available to the City
    to gather the data necessary to solve its severe environmental
    problem. Accordingly, the variance was only granted for the
    short period necessary to collect the data. The Board
    specifically noted that should the City request a variance
    extension beyond the data collection period a compliance plan
    would be necessary.
    Although the village of Bourbonnais case presented a more
    similar situation to that of Sycamore’s, in that matter the
    Village identified and committed itself to a compliance
    alternative. Specifically, it was contemplated that within four
    years of the grant of the variance a new plant would be finished
    capable of treating all of Bourbonnais’ waste. In the interim,
    the Village had made provision for treatment of 2.0 MGD above its
    treatment capacity by constructing an interceptor sewer
    connecting it to another treatment plant. The imposition of
    other expensive short—term solutions was found to constitute an
    arbitrary and unreasonable hardship. However, the Village was
    ordered to aggressively reduce I/I and deadlines were imposed for
    reduction of flows and use of the bypass.
    Finally, the Village of Seneca is also inapposite because it
    was demonstrated that the creek discharged to was already
    considered “degraded” and that elimination of the bypass would be
    of minimal beneficial effect. More importantly, it was
    contemplated that a sewer rehabilitation project, although
    principally concerned with dry flow, would eliminate enough I/I
    upstream of the bypass to offset the flow discharged from the
    bypass. The Village was also in the construction grants program
    to correct its wet weather flow problems.
    Although Sycamore’s pumping activities may have minimized
    the extent of basement flooding, as testified to, it did not
    serve to prevent it and thus is ineffective as a long—term
    solution. Rather, the health and welfare of Sycamore’s citizens
    depends primarily on the the City’s commitment to identify long—
    term solutions and then proceed to implement them as
    expeditiously as possible. Unfortunately, the ease of the “quick
    fix” approach has apparently slackened the City’s commitment to
    find an ultimate solution. For example, Mayor Johnson testified
    that he feels more bypasses are warranted (R. at 118). Variance
    65-17

    —8—
    may only be granted where it is demonstrated that the timely
    compliance called for by the Act and regulations is to be
    achieved. Sycamore has not made such a demonstration. For all
    of the foregoing reasons, the Board finds that Sycamore has
    failed to demonstrate the arbitrary or unreasonable hardship, as
    balanced against environmental harm, necessary to justify grant
    of variance. Accordingly, variance from 35 Ill. Adin. Code
    306.304 and 309.184 is hereby denied.
    The Board notes that this denial does not preclude Sycamore
    from initiating a new variance proceeding by filing a petition
    remedying the deficiencies outlined in this Opinion.
    This Opinion constitutes the findings of fact and
    conclusions of law of the Board in this matter.
    ORDER
    The City of Sycamore is hereby denied a variance for its 24
    inch diameter bypass pipe to Martin’s Ditch and its eleven “small
    portable pumps and 10” portable pump from 35 Ill. Adm. Code
    306.304 and 309.184.
    IT IS SO ORDERED.
    B. Forcade and J. Theodore Meyer concurred.
    J. D. Dumelle, R. Flemal and W. Nega dissented.
    I, Dorothy M. Gunn, Clerk of the Illinois Pollution Control
    Board, hereby certify that the above Opinion and Order was
    adopted on the
    /rc~~ day of
    _________________,
    1985, by a
    vote of
    ~‘—3
    .
    ~
    4
    ~
    ~
    /~t~ ~
    Dorothy M. ~unn, Clerk
    Illinois Pollution Control Board
    65-18

    Back to top