ILLINOIS POLLUTION CONTROL BOARD
    October 1~. 1983
    ILLINOIS ENVIRONMENTAL
    )
    PROTECTION AGENCY
    )
    )
    Complainantr
    )
    )
    PCB 79—26
    )
    CONTINENTAL GRAIN COMPANY
    )
    Respondent.
    MR. GREIG R. SEIDOR, ASSISTANT ATTORNEY GENERAL, APPEARED ON
    BEHALF OF THE ILLINOIS ENVIRONMENTAL PROTECTION AGENCY.
    MR. ROY £4. HARSCH OF MARTIN, CRAIG, CHESTER R. SONNENSCHEIN
    APPEARED ON BEHALF OF THE CONTINENTAL GRAIN COMPANY.
    OPINION AND ORDER OF THE BOARD (by J. D. Dumelle)
    This matter comes before the Board upon a February
    5.
    1979
    complaint and a June 28, 1979 amended complaint filed by the
    Illinois Environmental Protection Agency (Agency) alleging
    certain violations of the Illinois Environmental Protection Act
    (Act) in the operation of Continental Grain Company’s
    (Continental’s) grain handling facility located on the
    Mississippi River in East St. Louis. Hearings were held on
    March 9 and on December 16, 1982. Depositions, which were later
    admitted into evidence, were taken on March 9, 10 and 18. 1982.
    The Agency’s closing brief was filed on March 2, 1983.
    Continental’s closing brief was filed on June 8, 1983 and the
    Agency’s reply brief was filed on July 5, 1983. The latter two
    briefs were accompanied by motions to file instanter which are
    hereby granted.
    Continental is alleged to have violated Rule 203(d)(8)(B)(iv)
    (c)(2) of Chapter 2~ Air Pollution (Watercraft Loading Rule),
    Section 9(a) and (b) of the Act and Rule 103(b)(2) of Chapter 2
    for operating without a permit. Both parties agree. as stated in
    the Agency’s opening remarks that “the only issue remaining is
    the question of what should the company (Continentall have done,
    when should it have done it and to what extent the company should
    be penalized for its failure to come into compliance” (3/9/82
    R.5).* The only penalty requested is monetary (3/9/82 R.7).
    W~áü~ófthe ~ThIquedeveT~ments in this case, including the
    illness of both the hearing officer, who was ultimately replaced,
    54-215

    2
    Continental contends, briefly, that it is not suh~ectto the
    Watercraft Loading Rules because its East St. Louis elevator was
    an existing elevator not located in a ma’~orpopulation area and,
    therefore, was exempted from coverage, However, the Board,
    today. has held in a related permit appeal action (PCB 79—167)
    that the facility was not in fact, exempted.
    Continental contends further that it has participated in the
    development of technology to control watercraft loading
    emissions. that by the time of filing of the complaint in this
    matter it had been engaged for nearly a year in a ma~iorproject
    to attain compliance, and that it carried out the project in “an
    extremely timely, efficient manner” (Cont. Br. p.3). Continental
    has now installed pollution control equipment using aspiration at
    the end of the loading spout (Cont. Ex.20, p.2) and has received
    the required permits.
    Continental’s East St. Louis elevator was built in two
    phases with the old house (A house) having been constructed in
    the 1920’s and the new house (B house) having been built in the
    1950’s (Gibson P. 13), The East St. Louis elevator is part of
    Continental’s Midsouth Region which has two export terminals
    located at West Weigo and Reserve. Louisiana which are fed grain
    by 23 interior elevators (12/16/82 R. 20). Due to its location
    on the Mississippi River near highway and rail transportation.
    the East St. Louis elevator is considered by Continental to be
    its most important facility (12/16/82 R.23). Its operation is
    of great importance to Continental during the winter months when
    the Illinois River freezes as does the Mississippi River above
    St. Louis. thereby eliminating the possibility of barge use
    (12/16/82 R. 23). During such periods the East St. Louis
    elevator is the northern most grain elevator located on the
    Mississippi River which can ship qrain by barge (Gibson p. 56).
    The elevator normally draws grain from a 150 mile radius
    extending out into both Illinois and Missouri (Gibson p.40), and
    has had an annual grain throughput of approximately 35 million
    bushels per year. Between 25 and 50 people are employed at the
    elevator on a seasonal basis on a two shift per day schedule
    (Gibson p. 9).
    ~
    fEg transcri~Econ~its of the hearing
    transcripts of March 9 and 10 and December 16. 1982, as well as
    evidence depositions of Mr. Artis Talley and Mr. Jerry Gibson of
    March 9 and March 18, 1982, respectively, and a deposition of Mr.
    Hendrick Hartsuiker which was taken sometime in November,. 1982.
    Transcript citations will include the date of the transcript,
    followed by “R.~and the page number of the referenced
    transcript. Evidence depositions will be cited using the last
    name of the deponent followed by the page number.
    54-216

    3
    The existing watercraft loading dock was located approxi-
    mately 700 feet west of the A and B houses (Gibson p. 14). Grain
    was moved from the elevator to the existing loading docks via a
    conveyor belt which was elevated above the street. railroad
    tracks and Mississippi levee, Photograph #5 from Continental
    Exhibit 33 shows the old conveyor to the left of the new
    conveyor. Grain was discharged from the belt into a telescoping,
    inclined barge loading spout (Gibson p. 29). The then—existing
    spout, shown in Photograph #11 of Continental Exhibit 33, loaded
    barges at an average rate of approximately 10,000 to 12,000
    bushels per hour (Hartsuiker p. 94), The then—existing loading
    dock and tower were supported on four concrete pilings (Photo #3
    of Cont. Ex, 33).
    In order to achieve compliance with the Watercraft Loading
    Rules, Continental replaced the entire loading system at a cost
    of approximately $7 million (Hartsuiker p. 64). In addition,
    Continental replaced its barge haul system at an additional cost
    of approximately $250,000 (Hartsuiker p. 53). The new watercraft
    loading system involved the installation of a vertical spout
    equipped with aspiration at the tip using a Midwest Loader (Cont.
    Ex. 41, Hartsuiker p. 83), The new and old systems are shown in
    Photographs 1, 2, 3, 5 and 7 of Continental Exhibit 33.
    Continental applied for a construction permit to install the
    Midwest Loader on June 19, 1979 and was issued a construction
    permit on August 30, 1979 (Cont. EX~S 25 and 26), On May 28, 181
    Continental was issued an operating permit for a Midwest Loader
    (Cont. Ex. 27),
    BACKGROUND OF GRAIN HANDLING RULES
    In order to understand the allegations made by the Agency it
    is useful to review the background to Air Rule 203(d)
    (8)(B)(iv)(c)(2). In December, 1972, the Board opened docket
    R72—18 to consider the imposition of grain—loading rules (WIn the
    Matter of: Amendments to Chapter 2, Air Pollution Regulations
    for Grain-Handling and Grain-Drying Operations~’). The Illinois
    Feed and Grain Association, of which Continental was (and is) a
    member, participated fully in the development of the final
    regulatory product (see the Board~sOpinion of June 13, 1975, 17
    PCB 355). In that proceeding, the Board adopted the Watercraft
    Loading Rules pertinent to this case.
    The Board established in ~ir Rule 203(d) (8)(B) (iv) (1) two
    classes of watercraft grain—loading facilities’ (1) those which
    either loaded 2 million bushels of grain per year or less or were
    located outside a ~‘maiorpopulation area~ (as that term was
    defined in Air Rule 201), and (2) those which both loaded in
    excess of 2 million bushels per year and were situated within a
    major population area. In the latter case, covered by Rule
    203(d)(8)(B)(iv)(c)(2), the Board required capture of
    particulate emissions occurring in grain—loading of watercraft
    through an “induced draft air stream” with 98 removal efficiency;
    54~217

    4
    in the former, the efficiency demanded was only 90. Since
    Continental’s East St. Louis facility met both criteria of the
    more restrictive rule, it was required, as of April 30, 1977 (Air
    Rule 203(d)(8)(J)), to comply with this 98 removal efficiency.
    THE PERIOD OF NON-COMPLIANCE
    Continental now possesses all of the required permits and
    has installed and is operating all of its required pollution
    control equipment. An operating permit for watercraft loading
    was issued on May 28, 1981 (Cent. Ex. 27). However, Continental
    was not in compliance from April 30, 1977 (when the rules became
    effective) until May 28, 1981.
    In the fall of 1976, Continental submitted an operating
    permit application to the Agency for the entire grain—receiving,
    storing and loading facility (Cont. Ex, 1). That application
    was denied on October 21, 1976 because the truck dump, internal
    grain transferring equiment, screening and cleaning equipment,
    and grain load-out operations did not comply with Rule
    203(d)(9)(B) (Cent. Ex. 1). On December 16, 1976, Tom Marlow,
    then Continental’s engineer for the Mid—South region (which
    includes East St. Louis), wrote to Keith Conklin, Manager of the
    Air Permits section at the Agency, concerning the barge loading
    situation, and requesting a meeting (Cent. Ex. 2).
    That meeting, the first of six meetings Continental
    representatives had with Agency personnel regarding permits
    for the East St. Louis facility, took place on January 21, 1977.
    The Company was represented by Mr. Marlow, Tom O’Laughlin, then
    superintendent of the East St. Louis Operation, and Stanley
    Gasawski (3/9/82 R. 12 and 12/16/82 R. 130), Mr. Conklin
    and Walter Franke, the Agency’s Air Pollution Division regional
    manager, discussed the pertinent regulations, the reasons why
    Continental’s permit application had been denied, and
    Continental’s inability to meet the new standards (12/16/82 R. 29,
    3/9/82 R. 17 and Cent. Ex.
    2).
    The Agency advised that this prob-
    lem could be met if Continental received a variance for barge
    loading emission control equipment (Agency Ex. 1 and Cont. Ex. 3).
    A second meeting occurred on March 24, 1977, at which
    Continental representatives included its attorneys. Continental
    had, apparently, ruled out pursuing a variance, but agreed to
    submit permit applications for those separate units at the
    facility which satisfied the new air regulations (Agency Ex. 2
    and Cont. Ex. 4). Although Continental asserted emission
    controls for barge loading were technically not feasible, the
    Agency staff suggested that Continental view the Peavey grain—
    loading facility in Alton, Illinois, which had some emission
    controls for barge loading and had been permitted in 1975
    (Agency Ex. 2, Cont. Ex. 4 and 3/9/82 R. 20).
    54-218

    5
    On March 30, 1977 Mr. Marlow wrote to the head of Continental’s
    engineering department in New York, Max Spencer. recommending
    that Continental “defer” any further mention of the barge
    loading permit situation “at some risk of citation.” He
    observed further that “barge loadout, of course, is an
    area which can be very costly if full control is required.
    (Token control mentioned above could probably he done for
    $50,000 in duct work.)” (Cont. Fx. 4).
    A third meeting took place in May, 1977, at which Mr. Franke
    and Mr. Otis Banes, an inspector working under Mr. Franke, went
    over the Agency permit engineer’s notes with Mr. Marlow and
    Mr. O’Laughlin (3/9/82 R. 21). The Agency personnel indicated
    specifically which sources could he permitted and asked Continen-
    tal for a written compliance program for the remaining emission
    sources. Continental agreed to provide such a written program
    within three weeks, but failed to provide the program within that
    period (3/9/82 R. 21—22 and Agency Ex. 5).
    Mr. Franke and Mr. Banes next met with Mr. Marlow and
    Mr. Gasawski on August 24, 1977 (3/9/82 R. 22—23 and Agency
    Ex. 3). This meeting concerned Continenta.’s compliance
    plan for the as—yet unpermitted emission sources, which plan
    was rejected by Mr. Franke on the grounds that compliance
    would take too long to accomplish (3/9/82 R. 24), Mr. Marlow
    agreed to shorten the timetable, but did not make any commitment
    as to when Continental would come into compliance with respect
    to the barge loading system (3/9/82 R. 24—25).
    Mr. Marlow presented the reworked compliance plan at the
    fifth meeting, held on September 27. 177 (Agency Ex. 4).
    Mr. Marlow, Mr. Franke and Mr. Banes attended. The compliance
    plan (Cont. Ex. 8) spelled out in detail Continental’s plans for
    bringing three of the particulate sources at the facility into
    compliance. With respect to barge loading, Continental stated
    it was “hopeful” of presenting “a solution W/Schedule” to
    the Agency by March 1. 1978. Mr. Franke responded that it would
    be acceptable for Continental to bring the other sources into
    compliance in phases, rather than all at once. in part so as
    to relieve some of the financial burden on the company (3/9/82
    R. 27).
    The phases involved installing dust control on rail load—
    out, rail hopper car unloading pits, dust control on dust
    loadout tanks, truck dump pit dust control, replacement of
    existing cyclones with bag houses which control aspirated
    internal transfer points, as well as watercraft loading
    (3/9/82 R. 42). The phased compliance program included a
    general commitment for developing control strategies and their
    implementation for the barge loadout, truck dust loadout and
    truck unloading (3/9/82 R. 44).
    54-219

    6
    Continental, however, did not submit any written compliance
    plan for the barge loading source by March 1, 1978, and at the
    sixth meeting on March 14. 1978, Mr. Marlow stated that there was
    still no written compliance program for barge loading. hut that
    Continental intended to submit a construction permit application
    on April 15, 1978 for barge load—out (3/9/82 R. 28-29) which
    would propose controls at the conveyor belt discharge points and
    the top of the barge loading spout, but not the bottom of that
    spout (Cont. Ex. 12). Mr. Franke said that he doubted that the
    Agency would find this application acceptable, but that
    Continental should forward the permit application to the Agency’s
    Air Permit section for its review (Cont. Ex. 12, 13 and 3/9/82 R.
    48—5). That construction permit was submitted on May 16, 1978
    (Resp. Ex. 18), and was denied on June 16, 1978 on the basis that
    no aspiration or equivalent control was provided at the loading
    spout tip (Cont. Ex. 19).
    In April, 1978, Continental hired Mr. Robert Pacquer, an
    engineering consultant, to evaluate various methods of complying
    with the Watercraft Loading Rule (12/16/82 R. 150). Beginning in
    June,. 1978. and continuing through most of 1979, Mr. Pacquer and
    various Continental personnel, including Mr. Hendrik Hartsuiker,
    Manager of Engineering; Mr. Jerry Gibson, the superintendent of
    the East St. Louis facility; Mr. Marlow; and his successor as
    regional engineer~ Mr. Richard Tohetz, developed plans for
    substantial modifications to the entire facility (12/16/82 R. 122
    and 124), including an, as yet unimplemented, plan to expand the
    facility from its present 35 to 50 million bushels per day. The
    loading spout tip emissions were to he controlled through a Midwest
    Loader, a device installed on the end of the loading spout employ-
    ing aspiration for grain dust control (Agency Fix. 8; Hartsuiker
    p. 47—48).
    The Agency issued a construction permit for the work on
    June 20, 1979, bids were first requested in December,. 1979. a
    contract was awarded on March 20, 1980. construction was
    completed in mid—1981, and an operating permit was issued by the
    Agency of July 23, 1981 (Flartsuiker pp. 50—61).
    EXISTENCE OF CONTROL TECHNOLOGY
    Continental argues that as of the effective date of the
    Watercraft Loading Rules, technology had not developed to the
    point where it was feasible to apply aspiration on existing
    inclined loading spouts. However, that argument is unpersuasive
    in that eventual compliance was achieved through the use of a
    Midwest Loader on a newly constructed vertical dron spout rather
    than on its existing inclined spout (see Agency Ex. 8).
    Continental elected to install a Midwest Loader in a June,
    1978, meeting attended by Continental engineering and operations
    personnel and Mr. Pacquer, who had been hired by Continental
    54-220

    7
    two months earlier to help Continental comply with the Watercraft
    Loading Rule (Hartsuiker R. 47—48 12/16/82 R.150). Mr. Pacquer
    had been in touch with the manufacturer of the Midwest Loader
    prior to the June, 1978 meeting (Partsuiker R. 47), and 20
    months earlier the manufacturer of the Midwest Loader had mailed
    a document detailing various versions of the Midwest Loader,
    including two for barge loading, to various “environmental
    personnel” (Agency Ex. 8). That document indicates that the
    Midwest Loader was available for purchase as of October 11, 1976.
    Further, Continental worked on installation of aspiration at
    the tip of the loading spout at its Port of Tacoma facility
    beginning in early 1973 (Cont. Ex. 36). It installed a similar
    piece of equipment at its West Wiego export elevator and at its
    Evansville grain loading site (Hartsuiker R. 20~90 and 108—113).
    Engineering work at Evansville began in January. 1977
    (12/16/82 R. 263).
    Aspiration as a means of controlling dust in grain trans-
    ferring operations, according to Continental’s own former
    regional engineer, has been used for 80 to 90 years (12/16/82
    R. 223 and 225), and application of this method for dust control
    in grain loading has occurred in the last seven to ten years
    (12/16/82 H. 226).
    Finally, representatives of the Illinois Feed and Grain
    Association (of which Continental is a member) viewed a Midwest
    Loader being used for watercraft loading in Minnesota on May 3—4,
    1977 (Cont. Ex’s 7 and 40; 12/16/82 R. 65 and 105—107). Attached
    to Continental’s Exhibit 40 is a letter dated June 17.. 1976 from
    H. A. Campbell, an engineer, stating that he believed the Midwest
    Loader design “can totally eliminate the dust normally associated
    with grain load out operations.”
    Based on these facts, the Board finds that the technology
    for aspiration at the tip of a vertical drop spout existed as
    early as October of 1976 and that control technology was.
    therefore, available to Continental at that time. While the
    Board recognizes that there may have been no acceptable tech-
    nology in use in Illinois on inclined loading spouts as of
    January 24,. 1978 (Cont. Ex. 42) and that the Agency was unaware
    of any means to add aspiration to the tip of existing inclined
    spouts as of May. 1q78 (Hartsuiker p. 30), there is no evidence
    in the record demonstrating that Continental could not have
    proceeded with construction of its present facilities beginning
    as early as the start of 1977.
    54-221

    8
    FINL)ING OF VIOLATION
    Count I of the amended complaint alleges violation of
    Rule 203(d)(8)(B)(iv)(c)(2) and Section 9(a) of the Act,
    in that Continental failed to have the required pollution
    control equipment for removal of particulate emissions generated
    in the loading of barges. Count tI alleges that Continental
    operated its East St. Louis facility without an operating
    permit in violation of Rule 103(b)(2) and Section 9(b) of
    the Act.
    Continental presented no evidence demonstrating that it
    had the proper permits or emission controls under the Watercraft
    Loading Rule. While it did argue that it was not covered under
    that rule, as noted above, the Board has rejected that contention.
    Continental also argues, albeit briefly, that the Agency
    “accepted” its compliance schedule and cannot now prosecute
    this case, arguing, in effect, that the Agency granted some
    form of an informal variance, or that the Agency is estopped
    by its “acceptance”. The Board, not the Agency, has the power
    to grant variances and the “acceptance” of a compliance plan,
    under the circumstances of this case, where Continental failed
    to comply with that plan, cannot rise to the level of estoppel.
    Therefore, the Board finds that Continental has violated
    Rules 103(b) and 203(d)(8)(B)(iv)(c)(2) of Chapter 2: Air Pollution,
    and Section 9(a) and 9(b) of the Act during the time periods
    alleged.
    PENALTY
    Having found a violation, the Board is required to consider
    “the facts and circumstances bearing upon the reasonableness
    of the emissions” pursuant to Section 33(c) of the Act.
    First, little evidence was presented regarding injury
    to “the health, general welfare and physical property of the
    people” (Section 33(c)(1) of the Act). As detailed more fully
    below, Continental’s East St. Louis facility is located in a
    relatively isolated area. Continental’s regional manager,
    Mr. Fisher; the elevator manager, Mr. Gibson; the special
    assistant to the Mayor of East St. Louis, and Mr. Talley,
    each testified that they were unaware of any complaints
    having been made regarding dust emissions from the facility
    (12/16/82 H. 46, Gibson p. 47, Talley p. 15). Further,
    emissions occur at a low point relative to the surrounding
    terrain since they are at river level (12/16/82 H. 166).
    Therefore, the Board finds that there has been little or
    no injury to the health, general welfare or physical property
    of the people.
    54-222

    9
    Second, the East St. Louis elevator has an unquestioned
    social and economic value in that it is a major grain market for
    the St. Louis area, and shutting down the East St. Louis elevator
    would have a significant impact on farm economy in the area
    (12/16/82 R. 54). Continental is one of the few major employers
    left in East St. Louis (12/16/82 R. 59), adds appreciably to East
    St. Louis’ assessed valuation, and contributes to the City’s
    economy through utility taxes and employment (Talley pp. 8 and 20).
    Third, the elevator (which was originally constructed over
    60 years ago) is well suited to its location on the banks of the
    Mississippi River where it can load barges and adjacent to a
    complex rail and highway system to aid in the receipt of grain.
    The elevator is located in an isolated area that is approximately
    1½ miles from the City of East St. Louis (Talley p. 15 and Cont.
    Ex. 34). A railroad owns all of the property surrounding the
    elevator including to the immediate south an abandoned railroad
    warehouse (Gibson p. 17), Farther south is a rail car repair
    facility, the terminal railroad ship yard, an abandoned vacant
    landfill, and another barge loading dock. The elevator and the
    land surrounding it is physically separated from the City of East
    St. Louis by an elevated highway system (Gibson p. 21 and
    12/16/82 R. 169). There are no residents between the elevator
    and these elevated highways (Gibson p. 21).
    Fourth, Continental has demonstrated that it is technically
    feasible to comply with the Watercraft Loading Rule by replacing
    an existing inclined telescoping spout with a new watercraft
    loading dock employing a vertical drop Midwest Loading spout.
    While the record also demonstrates that it was not technically
    feasible at the time Continental began its compliance program to
    install aspiration at the tip of a telescoping inclined
    watercraft loading spout, that is irrelevant except as to
    economic reasonableness.
    Continental spent approximately $7 million in order to
    comply with the watercraft loading emission rule, The elevator
    was a 35 million bushel per year elevator before Continental’s
    renovation program and remains such today.. Approximately 2—½
    years of construction and
    $4½
    million would be needed to upgrade
    the elevator to increase its capacity to 50 million bushels per
    year (Hartsuiker p. 122). The fact that Continental has
    completed the system shows that compliance was economically
    feasible, although expensive. The fact that these improvements
    could ultimately result in increased throughput, thus resulting
    in an economic benefit, further supports the economic reasonable-
    ness. Thus, the Board finds that compliance was both technolog-
    ically feasible and economically reasonable.
    54-223

    10
    Continental argues that the imposition of any penalty would
    he contrary to the Act in that it would be punitive and would not
    aid in the enforcement of the Act see C~y~of Monmouth v. PCB,
    57 Ill. 2nd 482 arid 490, 33 N. E. 2nd 161 (1974)1. While it is
    true that the Board need not impose a penalty whenever a
    violation is found Metropplitan Sanita~ District v. PCB, 62
    Ill. 2nd 38 and 45, 338 N. H. 2nd 392 (1975) and. Southern
    iUinois_~halt v. PCB, 60 Ill. 2nd 204 and 207, 326 N. F.. 2nd
    406 and 408 (1975), the Board concludes that a penalty is
    ~iustifiedin this case despite present compliance in that “the
    assessment of penalties is appropriatel against recalcitrant
    defendants who have not sought to comply with the Act voluntarily
    but who have by their activities forced the Agency or private
    citizens to bring action against them may cause other violaters
    sic to act promptly and not wait for the prodding of the
    Agency” Fry Roofing Co. v. PCB, Ill. App. 3d, at 419. The
    record here demonstrates that Continental’s refusal to obey the
    watercraft loading rule made Agency enforcement action necessary.
    The effectiveness of the Act is premised upon voluntary
    compliance in that neither the Board nor the Agency has the
    resources to “force” all dischargers into compliance through the
    enforcement mechanism. The Board, further, is committed to the
    attainment of universal compliance as soon as is reasonable. It
    is unlikely that the goal will he reached if polluters learn that
    no adverse consequences and, indeed, positive economic consequences.
    may flow from delay.
    Continental offered considerable evidence showing that its
    efforts to comply with the Watercraft Loading Rule after
    June, 1978 were timely and expeditious (see e.ci. 12/16/82 P..
    158—160). This evidence however, fails to address Continental’s
    recalcitrance in complying with that rule from the time it was
    enacted (June 13, 1975), through the time it became effective
    (April 30, 1977), to the time the Agency sent its Notice of
    Violation to Continental (April 10. 1978).
    Taking the view most favorable to Continental, that time was
    spent in an unsuccessful attempt to develop or discover a control
    program compatible with its existing equiprnent.* However,
    nothing in the Watercraft Loading Rule exempts dischargers who
    cannot control their emissions using existing equipment, and Conti-
    nental never attempted to prove arbitrary or unreasonable hard-
    ship through a variance petition. Continental had been on notice
    since June 13, 1975 that it would be expected to comply with the
    rule by April 30, 1977. The Board has found that the technoloqy
    *The Board finds no merit in Continental’s argument that the
    delay was occasioned, in part. by possible eminent domain
    proceedings on the part of the City of East St. Louis; such
    action appears to have been highly speculative at best and
    Continental would assumedly have been recompensed ‘for any
    improvements.
    54-224

    11
    ultimately used to attain compliance was available by that date~
    and as of that date Continental should have ~ither come into com-
    pliance or obtained a variance. However, it did neither. Conti-
    nental has not established that compliance could not have been
    attained seventeen months earlier than it was (February 1980) by
    commencing its 37—month control program in January. 1~77.*
    The Agency argues that “at the interest rates in effect
    during these periods, Continental’s recalcitrance saved it
    hundreds of thousands, if not millions, of dollars” and that “it
    must not he allowed to profit from its disobedience of the law”
    (Ag. Brief p. 24). It does not, however, recommend a particular
    penalty.
    The Agency’s argument is overly simplistic in that it
    ignores the Section 33(c) factors, Continental’s early attempts
    to retrofit, and the fact that delay also results in construction
    cost increases. Given the lack of harm. the suitability of the
    site, the social and economic value of the site, and the fact that
    considerable new construction had to he completed at a cost of
    $7 million in order to install effective controls, a penalty of
    hundreds of thousands of dollars is not ~iustifled. On the other
    hand, the corporate attitude expressed through slow action toward
    compliance and the concomitant disregard of environmental rules is
    in aggravation. Continental should have come into timely compli-
    ance or received a variance or regulatory change, but did not.
    Upon full consideration of all of these issues. the Board finds
    that a penalty of $10,000 is appropriate.
    This Opinion constitutes the Board’s findings of fact and
    conclusions of law in this matter.
    ORDER
    1. The Board finds that the Continental Grain
    Company has violated Rules 103(h) (2) and
    203(d)(8)(B)(iv)(c)(2) of Chapter 2~
    Air Pollution, and Sections 9(a) and (h)
    of the Environmental Protection Act.
    ~
    ~5~Tff~7une.
    1978 to July. 1981). As the Agency as shown, it could have begun
    work in January, 1q77, by which date it knew of the Midwest
    Loader and could have made the decision to proceed. This 17
    month calculation does not take into account the six to eight
    weeks added to construction because Continental souqht to remain
    open during construction (~artsuiker B. 78-79).
    54-225

    12
    2. The Continental Grain Company shall, within
    45 days of the date of this Order, pay a
    penalty of $10,000 by certified check or money
    order payable to the State of Illinois, to be
    sent to:
    Illinois Environmental Protection Agency
    Fiscal Services Division
    2200 Churchill Road
    Springfield, IL 62706
    IT IS SO ORDERED.
    I, Christan L. Moffett, Clerk of the Illinois Pollution
    Control Board, hereby certify that th above Order was
    adopted on the
    /q71
    day of
    ,
    1983
    byavoteof ~-O
    .
    3i~~
    Christan L. M~f(~tt,
    ~
    Clerk
    Illinois Pollution Control Board
    54-226

    Back to top