ILLINOIS POLLUTION CONTROL BOARD
    March 11, 1976
    CITY OF OREGON, a municipal
    corporation,
    Petitioner,
    v.
    )
    PCB 75—497
    ENVIRONMENTAL PROTECTION AGENCY,
    Respondent.
    OPINION AND ORDER OF THE BOARD (by Mr. Young):
    This matter comes before the Board on the Petition for
    Variance filed on December 22, 1975, by the City of Oregon,
    seeking relief from the chlorination requirements of Rule
    305 of the Public Water Supply Rules and Regulations. An
    Agency Recommendation was filed with the Board on February 9,
    1976. No hearing was held in this matter.
    Rule 305 requires that each public water supply, except
    those purchasing water with an adequate chlorine residual,
    chlorinate its water prior to its entrance into the distri-
    bution system. This reiuirement became effective as of
    December 21, 1975, and is directed toward protecting consumers
    from the possible entrance of pathogenic organisms into the
    supply system.
    Accompanying the variance petition was a report prepared
    by a consultant to the City entitled “Waterworks Improvement
    Study” in which extensive and costly water system improvement
    projects were suggested to the City. Because Oregon is in the
    process of making a detailed review of this study, Oregon
    requests that a variance be granted from the chlorination
    requirements until December 21, 1977, to enable it to make some
    alleged cost savings. At the present time Oregon has three
    wells, although their consultant recommended that a fourth
    well be drilled to enable Oregon to meet its anticipated needs.
    The commencement date for drilling the fourth well is quite
    uncertain at present. The consultant recommended that Well
    #1 be abandoned or used only as a standby well after the fourth
    well is in operation. Because of this anticipated change, it
    is alleged that any costs expended to achieve compliance at
    Well *1 would be wasted. Oregon estimates a total project cost
    of $6,000.00 for a chlorination unit and housing to serve Well
    ~l. Since Well #1 may be abandoned or used only on a standby
    20—281

    —2—
    basis, Oregon alleges two reasons this total $6,000.00 expendi-
    ture would be improvident: First, money expended for building
    construction would be a complete loss; second, money expended
    for equipment at Well #1 would be a loss since that equipment
    could not be used at Well *4 because of the different water
    production rates of the two wells.
    The Agency contends that this particular economic hardship
    projected by Oregon is not accurate. If it were in fact necessary
    to provide a building for the chlorination equipment at Well *1,
    the Agency submits that a portable building could be used which
    could be transferred to Well #4, when and if Well #1 is abandoned.
    However, while visiting the site of Well #1, Agency field opera-
    tions personnel found that a utility building exists containing
    a pump which has been used in the past for the chemical feeding
    of polyphosphate. With minor modifications the Agency believes
    that this building could be used to house the chlorination equip-
    ment and that the pump previously used to feed the polyphosphate
    may now be acceptable for use in feeding liquid sodium hypochiorite.
    In the eventuality that new equipment is necessary for chlorination
    at Well #1, the Agency alleges that at least one manufacturer
    markets a chlorinator with six different chlorination capacities.
    Such a unit could be used at Well #1 until such time that Well
    #4 was in operation.
    In regards to the installation of chlorination facilities
    at Wells #2 and 3, Oregon alleges that more favorable bids could
    be obtained for such equipment if the bids were received when
    taking bids for the drilling of Well #4 and the construction of
    its related building. By doing this, Oregon could dictate that
    all equipment be of the same manufacturer, thereby allegedly
    providing for better operation because of the similar nature of
    the equipment, and also reducing cost by avoiding unnecessary
    duplication of repair parts.
    The Agency is not convinced that Oregon would receive more
    favorable bids for the installation of equipment at Wells #2 and
    3 by delaying such installation until the drilling of Well #4.
    Oregon has not offered any precise savings estimate which might
    result from purchasing all equipment at the same time, and the
    Agency believes that any such savings would be negligible and
    offset by probable increases in the cost of the equipment in
    the future. The Agency also submits that if similar equipment
    is desired, Oregon could specify a particular brand of equipment
    in setting its bids for the construction of Well *4. Whether
    such equipment is needed for Wells #2 and 3 seems to be in doubt
    however. While visiting these wells, Agency personnel discovered
    that in addition to the pump at Well #1, two other chemical feed
    pumps exist, one of which is idle while the other is presently
    being used for feeding polyphosphate at Well #3. The Agency
    20
    282

    —3—
    believes that Oregon can use these pumps to feed sodium hypo—
    chlorite at these wells.
    This Board has in the past stated that the burden of proof
    in variance matters is on the petitioner and that the evidence
    to justify the allowance must be substantial and convincing.
    Swords v. EPA, PCB 70-6, 1 PCB 5 (1970). We do not believe
    that Oregon has established a hardship sufficient to justify
    the grant of a two year variance; we will, however, grant a
    variance for a period of 150 days to allow for the installation
    of chlorination equipment at the existing facilities. Oregon
    can determine whether it wishes to use the existing equipment
    for feeding liquid sodium hypochiorite into the system, or
    whether it wishes to purchase new equipment for use in the gas
    chlorination of the system. The Board notes that the consultant
    for Oregon recommended that gas chlorination be installed at
    each of the existing wells and estimated the cost of compliance
    using such equipment to be $24,900.00. Compliance costs using
    existinq equipment would be considerably less initially, but
    this initial advantage would be offset after a period of time
    by the higher operating costs associated with the use of liquid
    sodium hypochlorite.
    The grant of this variance is conditioned on the fact that
    Oregon file a project completion schedule and bi-monthly progress
    reports with the Agency. In addition, a performance bond will
    be required along with a standard certificate of acceptance.
    This Opinion constitutes the Board’s findings of fact and
    conclusions of law in this matter.
    ORDER
    IT IS THE ORDER OF THE BOARI) that the City of Oregon be
    granted a variance from the chlorination requirements of Rule
    305 of the Public Water Supply Rules and Regulations for a period
    of 150 days from the date of this Order subject to the following
    conditions:
    1. Oregon shall file a project completion schedule with
    the Agency within 35 days of this Order and thereafter file
    bi-nionthly progress reports with the Agency until completion
    of the facilities.
    2. Oregon shall post a performance bond with the Agency
    in the amount of $24,900.00 in a form satisfactory to the Agency
    to assure completion of the construction and installation of
    its chlorination facilities. Such bond shall be posted within
    30 days of the date of this Order at the following address:
    Environmental Protection Agency
    Public Water Supply Division
    2200 Churchill Road
    Springfield, Illinois 62706
    20— 283

    —4—
    3. Within 30 days of the date of this Order, Oregon
    shall complete and submit to the Agency, at the above address,
    the following certification:
    I, (We), ________________________ having
    read the Order of the Illinois Pollution Control
    Board in PCB 75-497, understand and accept said
    Order, realizing that such acceptance renders
    all terms and conditions thereto binding and
    enforceable.
    SIGNED
    TITLE
    DATE
    Mr. Dumelle dissents.
    I, Christan L. Moffett, Clerk of the Illinois Pollution
    Control Board, herejy certify the above pinion and Order were
    adopted on the
    //~
    day of
    fr)
    ,
    1976
    by a vote of
    i/s.,
    QA~~4~
    Christan L. Moffe
    ,
    lerk
    Illinois Pollution ontrol Board

    Back to top