ILLINOIS POLLUTION CONTROL
BOARD
October 9, 1975
ILLINOIS CENTRAL GULF RAILROAD,
)
CENTRALIA SHOP,
Petitioner,
)
v.
)
PCB
75—222
)
ENVIRONMENTAL PROTECTION AGENCY,
)
Respondent.
OPINION AND ORDER OF THE BOARD (by Mr. Goodman):
This case comes before the Pollution Control Board
(Board) upon a petition for variance
filed
by Illinois
Central
Gulf Railroad (hereinafter “Illinois Central”) on
May 29, 1975. Illinois Central seeks variance from Rules
202(b) and 302(a) of the Air Pollution Regulations until
March 1, 1976. On November 22, 1974, the Board granted the
Petitioner a similar variance until May 30, 1975. (PCB 73—
547, 14
PCB
489). Illinois Central now requests an exten-
sion of this date. No hearing has been held in this matter.
Illinois Central owns and operates a facility known as
the Centralia Shop located in Wamac, Illinois. It is Illinois
Central’s largest facility for building new freight cars and
making major repairs on damaged freight cars. An integral
part of this facility is an outdoor area in which the cars
are spray painted--including interior arid exterior painting
and identification stencilling.
The average number of cars
painted per day
is 12.4. The petition set forth the follow-
ing
calculations for current particulate
emissions:
Average density of paints used
9
•
3 pounds/gallon
Average paint use (w/interior paint)
=
34 gallons/hour
Average process weight rate
=
316.2 pounds/hour
Overspray
25 overall
Current particulate emissions
=
79.05 pounds/hour
Allowable emissions under Rule 203(a) are 0.95 pounds/
hour. Since the earlier variance Illinois Central has been
proceeding on a compliance plan which proposes to reduce
19—31
emissions to 0.79 pounds/hour. This plan calls for con-
struction of an enclosed facility utilizing a floor water
wash booth, two down draft dynaclean water wash booths and a
series of four wall mounted dry filter booths. In the
earlier case, Illinois Central sought variance until March
1, 1976. The Board granted the variance until only May 30,
1975, indicating that inadequacies in the record prevented a
decision as to whether a longer variance was warranted.
Specifically, the Board indicated that the record did not 1)
disclose the effectiveness of temporary walls built to
protect neighbors from overspray, 2) explain the tardiness
in applying for the variance and in initiating the com-
pliance plan, or 3) disclose whether compliance could ac-
tually be achieved
by March, 1976.
Illinois Central stated in its petition that construc-
tion of the permanent
spray
painting facility was begun on
December 5, 1974. As of the date of the petition the fol-
lowing progress had been made:
I. All demolition, removal, and pile driving has been
completed.
2. Materials for the building have been received and
erection is approximately 60 percent complete.
3, Excavation, filling and grading is approximately 98
percent complete.
4. Concrete work is approximately 90 percent complete.
5. Plumbing work is approximately 75 percent complete.
6. Fire protection is approximately 39 percent complete.
7. Structural steel work is approximately 25 percent
complete.
8. Electrical work is approximately 25 percent complete.
The long completion schedule was explained by the size
($2,727,000) and uniqueness of t~project. It is claimed
that no other railroad is operating a facility of the same
type, therefore requiring more engineering time. Financing
has been obtained from the Ililenie ir~.lewtrial Pollution
Control Financing Authority. I1JLI:noes Central further
stated in its petition that the contractor is required to
complete the job by mid-January, 1976, and is almost two
weeks ahead of schedule.
Illinois Central alleged several hardships which would
result if the variance were denied, Painting the freight
cars, it is alleged, is necessary to prevent deterioration,
to ensure visibility for purposes of safety and to comply
with “marking” requirements of the Association of American
Railroads and the Interstate Commerce Commission. To re-
place spray pointing with brush or roller painting would
19—
32
—3—
increase costs from $8.25 to $154 per car and make a large
scale operation infeasible. Finally, Illinois Central
alleges that a denial would ultimately detract from the
companyle future revenue by inhibiting the publicity and
marketing functions of the painting.
The Agency filed its Recommendation in this matter on
August 26, 1975. It indicated that an Agency investigation
confirmed most of the foregoing facts, It recommended in
favor of the variance, conditioned on monthly progress
reports, and submittal of a performance bond equal to the
cost of the compliance program. It further recommended that
construction be required to be completed by February 1,
1976, since Illinois Central was already ahead of schedule.
In response to a June 6, 1975, Board Order seeking
additional information, Illinois Central filed an amended
petition which set forth ambient air quality data as ob-
tained from the Agencyle 1973 and 1974 Air Sampling Network
Reports. The nearest monitoring stations to the Centralia-
Wamac area are at Carlyle and Mt. Vernon, Illinois, Par-
ticulate data for both stations indicate compliance with
National Ambient Air Quality Standards as they relate to
both 24~hour and annual geometric mean concentrations.
Furthermore, from the nature of the emissions there would
seem to be more of a local nuisance problem than one of
contribution to ambient air problems at distant locations.
The Agency Recommendation indicated that although the area
surrounding the railroad yards is partly residential, the
population density is low, While several residents lodged
complaints with regard to “film” and “paint specks” settling
on their property, only one objected to granting the current
variance request. The Agency claims that the failure of
other residents to object is conditioned upon continued good
faith efforts to remedy the oversprs~ eroblem., Such good
faith seems indicated by Illinois
Central s completion of
its temporary shielding walls, which it claims has reduced
the distance of overspray
by
a fictor of five.
It
is fur-
ther indicated by the progress made to date on the new
enclosed
facility.
On the basis of the evidence presented above, the Board
is of the opinion that a sufficient case of hardship and
good faith has been made to warrant granting the requested
variance. The inadequacies in the earlier record have been
cured, since it appears that the temporary restraining walls
have been effective and that compliance can in fact be
achieved by March 1, 1976, We feel that a performance bond
in this instance is unnecessary, since Illinois Central has
19 —.
33
—4—
already
evidenced good faith in expending over half of the
estimated $2.7 million cost of the project, as it so alleges
in its reply to the Agency~sRecommendation. We agree with
the Agency that the earliest possible completion of the new
facility should be accomplished. Although Illinois Central
objects to moving up the completion date one month to Feb-
ruary 1, 1976, thus allowing no leeway for possible winter
construction delays, we note that the construction contract
calls for completion by mid-~January and that the contractor
was in fact two weeks ahead of schedule. Construction of
the new facility has already taken a long period of time and
we feel that Illinois Central should be able to meet this
advanced deadline,
This Opinion constitutes the findings of fact and
conclusions of law of the Board in this matter.
ORDER
It is the Order of the Pollution Control Board that
Illinois Central Gulf Railroad, Centralia Shop is granted
variance from Rule 202(b) and 203(a) of Chapter Two from
May
30, 1975 until February 1, 1976, subject to the following
conditions:
I. Petitioner shall submit monthly reports indicating
progress on the control program outlined in its construction
permit. Such reports shall be due no later than the 15th of
each month following the month detailed in the report, and
be submitted to:
Illinois Environmental Protection Agency
Division of Air Pollution Control
Control Program Coordinator
2200 Churchill Road
Springfield, Illinois 62706
2. Petitioner shall operate
itb
temporary paint spray
facility so as to minimize overspray impact on the public
until completion of its new enclosed facility.
MR. DUMELLE DISSENTS.
I, Christan L. Moffett, Clerk of the Illinois Pollution
Control Board, hereby certify the above ODinion and Order
were adopted on the
___________
day of
1975 by a vote of
~
19
34