ILLINOIS POLLUTION CONTROL BOARD
August 14, 1975
WESTERN ILLINOIS POWER COOPERATIVE, INC.,
Petitioner,
v.
)
PCB 75—192
ENVIRONMENTAL PROTECTION AGENCY,
Respondent.
OPINION AND ORDER OF THE BOARD (by Mr. Zeitlin):
This case involves a request for a Variance submitted
by Western Illinois Power Cooperative, Inc., (WIPCO) to the
Illinois Pollution Contrpl Board (Board), on May 6, 1975.
The WIPCO petition seeks extension of an existing variance
from Rules 203 (particulates) and 204 (sulfur dioxide) of
the Air Pollution Regulations from July 1, 1975 to September 30,
1975. PCB Regs, Ch. 2, Rules 203, 204. No hearing was held
in this matter. A Recommendation from the Environmental
Protection Agency (Agency) was received on July 23, 1975; a
minor amendment to that Recommendation was received on
~Iu1y 30, 1975.
The Board first granted WIPCO a Variance from the
corresponding Rules and Regulations Governing the Control
of
Air Pollution, promulgated by the old Air Pollution Control
Board, predecessor of this Board, on January 30, 1973.
PCB 72-441 (January 30, 1973). Subsequent variances were
granted on January 24, 1974, July 18, 1974, and December 19,
1974. PCB 73—471, PCB 74—150, PCB 74—394, respectively.
The last of those variances recognized that the old Rules
and Regulations Governing the Control of Air Pollution would
be superseded on May 31, 1975, and granted a further variance
from Rules 203 and 204 of the Board’s Regulation until July 1, 1975.
A.3. of the variances were subject to the same conditions
contained in the original Variance grant, and those added in
the subsequent variances.
The original Variance, and all the subsequent variances
have been granted to allow the installation of a wet scrubber
control system at WIPCO’s Pearl Station generating plant, in
Pike County, Illinois. The plant is a 22 megawatt coal-
burning steam turbine power plant, with one unit fired by
four burners; it is also equipped with a mechanical multiple
cyclone dust collector. The single unit exhausts into a 203
foot stack.
18— 372
—2—
WIPCO once again claims that factors beyond its control
have prevented completion of the wet scrubber system by July 1,
1975. In this instance, redesign of the induced draft fans,
low labor productivity, and equiPment procurement problems
have been alleged. As was noted in the Agency Recommendation,
which recommended that the variance be granted, these delays
do seem to be beyond the control of Petitioner. WIPCO has made
extensive good faith efforts to complete scrubber installation
within the times co~teniplated in our earlier Orders. In
the instant case, this has included a requirement that
contractors work on extended work—day and work—week schedules.
In examining this request for a Variance, the Board
finds no reason to change its earlier approval of the
proposed compliaflce plan. The period of time here requested
is small, and the record contains no evidence of any damage
which might result from a grant. The only remaining issue
will be our consideration of the United States Supreme Court
case, Train v. N.R.D.C., 43 EJ.S.L.W. 4467 (1975).
In an Order dated Nay 8, 1975, the Board found that the
petition submitted by WIPCO did not sufficiently address the
questions raised in the Train decision. Although the Board
did note that the ambient air quality in the vicinity of the
Pearl Station was, in PCB 72—441, found to be within the
federal Ambient Air Quality Standards, current and specific
information was requested. In a subsequent Order, on June 6, 1975
the Board allowed WIPCO additional time to submit the information
requested. The requested information was submitted on June 16,
1975, and confirms the Board’s earlier finding on ambient
air quality in the area concerned.
Although the Agency questioned the ability of WIPCO to
conduct sufficient air monitoring within ten days, we find
that the information submitted is sufficient. WIPCO engaged
consultants to conduct a fairly thorough testing for sulfur
dioxide, particu’~ates, and nitrogen dioxide in the area of
the station. The test result, along with a computer model
submitted, show that no ambient air quality problems are
generated by the Pearl Station. The readings taken indicated
values which are far below both primary and secondary ambient
air quality standards.
18— 373
—3—
Based on WIPCO’s good faith, the shorL period of time
involved, and the ambient air quality data submitted, we
feel that a grant of this Variance is well justified.
This Opinion constitutes the findings of fact and
conclusions of law of the Board in this matter.
ORDER
IT IS THE ORDER OF THE POLLUTION CONTROL BOARD THAT
Petitioner Western Illinois Power Cooperative, Inc., is
granted a variance from Rules 203 and 204 of Chapter 2: Air
Pollution, from July 1, 1975 until September 30, 1975,
subject to the applicable conditions imposed in PCB 74-394.
I, Christan L. Noffett, Clerk of the Illinois Pollution
Control Board, hereby certify the above Opinion and Order
were adopted on the
-
day of August, 1975 by
a vote of ~—O
Christan L. Moffett, yi~r
Illinois Pollution Cq~n~tolBoard
18
—
374