ILLINOIS POLLUTION CONTROL BOARD
    May 8, 1975
    MT. CARMEL PUBLIC UTILITY COMPANY,
    Petitioner,
    v.
    )
    PCB 75-41
    ENVIRONMENTAL PROTECTION AGENCY,
    INTERIM OPINION AND ORDER OFRespondent
    THE BOARD0 (by Mr. DuInelle)
    This petition for variance was filed on January
    27,
    1975~. It contains a waiver from a right to decision within
    ninety days. Petitioner, Mt. Carmel Public Utility Company
    (Mt. Carmel), seeks an extension of a variance from Rule 2—
    2.53 of the Rules and Regulations Governing the Control of
    Air Pollution and from Rule 203(g) (1) (B) of Pollution Control
    Board Regulations, Part II, Chapter 2 until December 31,
    1975.
    The City of Mt. Carmel, located in Wabash County,
    operates a facility for generating electricity and supplying
    process steam. The facility’s boilers No. 1 and 4, the
    subject of this petition, utilize approximately 25,000 tons
    of coal per year with an approximate ash and sulfur content
    of 7.5 and 2.28, respectively. Heating value of the coal
    is 12,026 BTUt5 per pound.
    This operation has been the subject of numerous prior
    Board actions. For purposes of brevity the reader is referred
    to our Opinion in PCB 74-280, 14 PCB 211 for a summary of
    these actions. That Opinion, issued on October 17, 1974,
    granted Mt. Carmel a variance from Rule 2-2.53 until April
    30, 1975 but required additional evidence to justify granting
    the variance for the full extent of the requested period
    (October 31, 1975). In this petition, Mt. Carmel seeks to
    supply such evidence and further seeks a new extension until
    December 31, 1975.
    Mt. Carmel’s compliance program consists of two steps.
    First, it intends to retire Boiler No. 4 upon the completion
    of an interconnection with Central Illinois Public Service
    (CIPS) at its substation at Albion. Second, it proposes to
    install equipment to control particulate emissions from
    Boiler No. 1.
    16 —599

    —2—
    The petition contains an extensive explanation of Mt.
    Carmel’s attempts to secure completion of the interconnection.
    Segments of this interconnection have been constructed
    and
    completed. A 69 KV transmission
    line from the Company~s
    generating
    station at Mt. Carmel to
    a substation located at
    the Amax Coal Mine near the Village
    of Keensburg was completed
    before January 30, 1973 as
    ordered by the Board in an Order
    entered on November 11,
    1971 and extended on October 31,
    1972. Another segment of 69 KV line
    from the Amax Coal Mine
    to the eastern terminal point of a proposed 138 KV line has
    also
    been completed, Mt. Carmel alleges that a third phase
    of
    this construction program
    the
    acquisition of easements
    required for the 138
    NV
    line ran into opposition
    from
    landowners along the proposed route. The petition records
    the
    protracted legal steps, beginning on October
    4, 1972,
    taken by Mt. Carmel to effectuate
    the necessary
    condemnations.
    Filing
    of the condemnation judgments with respect to the
    last remaining parcels of land was finally accomplished on
    October 1, 1974. Meanwhile, clearing operations and some
    erection of
    H-frame structures
    for the 138 Ky line
    were
    commenced in early August, 1974. In the middle
    of
    November
    bad weather forced a temporary discontinuance, and construction
    operations have continued intermittently as the weather
    permits. Mt. Carmel expects to complete construction by
    December 31, 1975. Mt. Carmel alleges that it
    has already
    expended a sum totalling
    over
    $850,000
    in the
    construction
    of
    this interconnection. It
    estimates additional expenditures
    for completion of the
    138 KV line at
    $40,000,
    The
    Environmental Protection Agency, in
    a Recommendation
    filed March 11, 1975, stated that
    it is
    of the opinion
    Mt.
    Carmel has made reasonable progress toward completing the
    interconnection,
    and that the delays
    did
    not appear to have
    been
    caused
    by
    the Comeany. Accordingly
    it
    recommended the
    grant of a variance for :Boiier No.
    4.
    We agree that a
    variance would
    be appropriate here, since the petitioner has
    acted in good
    faith, at a considerable expense and for a
    period of time stretching over several years, to achieve
    compliance.
    We note that, unlike
    other cases
    in which
    we have
    denied variances
    based on interconnection proposals, the
    petitioner here
    has
    actually progressed toward construction
    and
    completion
    of
    the necessary lines as opposed to simply
    awaiting the approval of
    an
    interconnection
    agreement.
    16—600

    —3—
    (See City of Highland v. EPA, PCB 73-288, 13 PCB 167 (July
    25, 1974) and City of Carlyle v. EPA, PC~73-264 (January
    16, 1975)
    With respect to Mt.
    Carmel’s
    compliance program
    for
    Boiler No. 1, the
    Agency
    has recommended denial of
    the
    variance on the ground that the boiler can now operate on
    iueL oil.
    It recommended that the Company continue to seek
    Thean
    allocationAgency
    grantedby
    workingMt.
    Carmelwith athepermitIllinoisto convertEnergy thisOffice0
    boiler from
    coal
    to dual fuel on January 16, 1974, it was
    taken
    out of
    service October
    30, 1974
    and
    conversion was
    completed
    by January 10, 1975 at a cost of oVer $4:L,000
    (~p~ndifnr~s
    to December 31,
    1974)
    Mt. Camel has now
    poseponea the fuel oil operation of th.is boiler as a result
    of supply ~
    ff1
    ~‘ii1 f~
    i
    ~
    ,
    and now proposes a. program to install
    particulate
    control equipment to achi.eve compliance with
    Rule 203(g) (1) (B)
    .
    Ou.r Order of October :L7, 1974 in ICE ~
    280, cirantina Mt. Cammel a. varier cc extension, critlc:Lzed.
    that petition for its omission of any discussion of the
    possibility
    of installing such control devices,
    The instant
    petition satisfies that omission,
    Moreover, ii: indicates
    that a mechanical dust collector for the system has already
    been ordered, at a cost of $15,510, with delivery expected
    the last week in February, 1975. In addition, a new induced
    draft fan
    has been ordered, with delivery expected by July
    1,
    1975. Mt. Carmel alleges that since this latter delivery
    cannot be accomplished prior to the period of peak demand,
    the particulate control system cannot he completed
    prior to
    the winter of 1975.
    in its petition and in a reply to the Agency P~~mm~nd~tthn,
    filed on March 20, 1975, Mt.
    Cannel
    related its attempts to
    secure additional fuel oil, It expressed limited confidence
    in
    the promise of aid :Erom the Illinois Energy Office in
    obtaining an additional allocation of fuel oil since the
    Federal Energy Administration had already denied an
    application
    on December 3, 1974, It did indicate, however, that it had
    written to the Illinois Energy Office and asked for advice
    and assistance in gaining the additional allocation.
    We are of the opinion that
    Mt.
    Carmel has made out a
    case that it cannot at this time secure the necessary allocation
    to run its Boiler No. 1 on fuel oil. Again we find the
    sufficient degree of good faith here, both in the original
    conversion of the boiler and in the instant progress toward
    installation of control equipment, to normally warrant the
    grant, of a variance until the controls are installed, or
    until an additional allocation is obtained.
    16
    —601

    —4—
    We feel precluded, however, by a recent United States
    Supreme Court case, from granting a variance beyond July 1,
    1975
    —-
    the date Illinois, is to have attained national
    primary ambient air standards under the Clean Air Act
    --
    without a showing that the variance will not jeopardize such
    national standards. Train v. National Resources Defense Council,
    et al., 43 LW 4467 (April 16, 1975). In this instance, no
    information has been submitted indicating ambient air quality
    with respect to particulates with which to enable us to make
    such a determinatidn, We therefore remand this case to
    allow the city 120 days within which to supply such data.
    Finally, Mt.
    Carmel requests the release of a $500,000
    performance bond required by the Board on November 11,
    1971.
    It cites the fact that
    it has already spent over one million
    dollars on its compliance plan
    -
    compared to an original
    estimate of $680,000. It expects the completion of the
    program to cost an additional $100,000, including $60,000
    for the particulate control system on Boiler No. 1 and
    $40,000 for additional expenditures for the completion of
    the 138 NV line. It also cites expected difficulty in
    refinancing a $270,000 bond issue due December 1, 1975 if
    the performance bond is not released because of the contingent
    liability involved. In light of Mt. Carme1~s past performance,
    we accept the Agency Recommendation to lower the performance
    bond and lower it to $25,000.
    This Interim Opinion constitutes the Board’s findings
    of fact and conclusions of law.
    ORDER
    It is the Order of the Pollution Control Board that:
    1. Petitioner, Mt. Carmel Public Utility Company,
    supply the Board, within 120 days of the date
    ~of
    this Order,
    with ambient air quality information with respect to particulates.
    2. The Mt. Carmel Public Utility Company performance
    bond posted in PCB 7l-l5R to guarantee completion of its
    program of compliance shall be in the amount of $25,000
    instead of $500,000 heretofore required under PCB 74-280.
    I, Christan L. Moffett, Clerk of the Illinois Pollution
    Control Board, hereby certify ~he above Interim Opinion and
    Order were adopted on the ~~day
    of May, 1975 by a vote of
    A
    Christan L. Moffe~t.;~~Clerk
    /
    Illinois Pollutionl Oôntrol Board
    16—602

    Back to top