ILLINOIS POLLUTION CONTROL BOARD
    December 19, 1974
    ABBOTT LABORATORIES
    PETITIONER
    v.
    )
    PCB 74—338
    ENVIRONMENTAL PROTECTION AGENCY
    )
    RESPONDENT
    MR. RONALD L. SCHERUBEL, ATTORNEY, in
    behalf of ABBOTT LABORATORIES
    MR. JOHN T. BERNBOM, ATTORNEY,
    in
    behalf of the ENVIRONMENTAL PRO-
    TECTION
    AGENCY
    OPINION AND ORDER OF THE BOARD (by Mr. Marder)
    This action involves a Petition for Variance, filed by Abbott Lab-
    oratories on September 19, 1974, in order to discharge effluent from
    its North Chicago treatment plant, in excess of the standard set in
    Rule 404 (d) of Chapter 3, Water Pollution Control Regulations. The
    standard in Rule 404 (d) is 4 mg/i BOD and 5 mg/i suspended solids.
    Variance is requested until late 1975, when Petitioner will divert
    its entire flow to the new Gurnee treatment plant of the North Shore
    Sanitary District.
    The Agency filed its Recommendation on October 24, 1974. In the
    Recommendation the Agency suggests variance be granted, subject to
    certain conditions.
    Hearing was held in North Chicago, Lake County, Illinois,
    on Octo-
    ber 31, 1974. Members of the public were present.
    Abbott Laboratories is a world—wide manufacturer of pharmaceuticals,
    with its largest facility in North Chicago. The plant turns out a wide
    range of drugs and consumer products and employs almost 6000 persons.
    The Petitioner maintains an activated sludge treatment plant for
    treatment of process waste water in the plant. Seventy—five percent
    of the waste water in the plant is recycled for reuse, whereas 25 of
    the water is treated for discharge. Discharge is to Lake Michigan at
    about 700,000 gallons per day.
    In 1972 Abbott was considering ways of bringing its
    effluent into
    compliance with Rule 404 (d) by December 31, 1974. Two plans were con-
    sidered. The first was to upgrade the treatment plant, so that the
    discharge would meet the Lake Michigan standards. Pilot plant work
    was done to determine how this could be done. The second plan was to
    divert the entire flow from Abbott to the North Shore Sanitary Dist-
    rict plant in Gurnee, Illinois.
    14—749

    —2—
    Abbott chose the second plan. Going to Gurnee would involve less
    cost for Abbott over the long run (even though Abbott would pay a share
    of capital and operating costs as related to its contribution) because
    of economies of scale in plant construction and operation. Further,
    Abbott felt it would be a better policy to end its discharge to the
    lake completely.
    In 1972 the Agency accepted the diversion to Gurnee as an acceptable
    compliance plan (Exhibit 1 attached to Petition).
    All would have been well had the Gurnee plant proceeded on schedule
    and been completed in December 1974. Through no fault of Abbott’s, the
    Gurnee plant is now scheduled to have secondary treatment by September
    of 1975 and tertiary treatment by August of 1976.
    Hardship:
    Abbott alleges, and the Agency agrees, that it would be an unreason-
    able hardship for Abbott to spend the time and money to upgrade its
    plant to handle these discharges when the Gurnee plant will be on line
    in less than one year. The Board agrees and notes that even if Abbott
    were to start work today to upgrade the plant, it probably would not be
    in operation by the time the Gurnee plant was ready to receive the eff—
    luent.
    Environmental Impact:
    It is noted in the Petition and confirmed in the Agency’s Recommend-
    ation, that other than BOD and suspended solids the Abbott effluent com-
    plies with all the other criteria in Rule 408 (a). It is noted in the
    record that part of the problem with maintaining the suspended solids
    criteria is that at times the intake water to the plant from the lake
    is higher than the effluent standard (R. 29-30). The BOD discharge
    will have a minimal impact on the lake. Also, it appears better for
    the lake to end the discharge completely, as is contemplated by divert-
    ing the effluent to Gurnee. Effluent discharges for a. recent six—months
    period are as follows:
    Date
    BOD
    SS
    March 1974
    15
    25
    April 1974
    47
    75
    May 1974
    25
    15
    June 1974
    31
    18
    July 1974
    22
    14
    August 1974
    17
    9
    (Agency Rec. Pg. 2)
    The only controversy in this matter relates to conditions the Agency
    wants placed on the grant of this variance. One condition relates to
    the maximum discharge of BOD and suspended solids during the term of
    the variance. The Agency feels that the limit should be BOD, 17 mg/i,
    and suspended solids, 25 mg/l. This falls into the average that the
    14
    750

    —3—
    plant has had over the past 26 months (R. 27)
    .
    Abbott feels that there
    should be no
    standard
    for two reasons. First, they feel that the plant,
    for reasons of design characteristics and load constituents, cannot al-
    ways guarantee a 17/25 BOD/SS effluent. Abbott states that though the
    plant average over 26 months was 17/25 BOD/SS, there were days when the
    effluent was higher and days when it was lower (R. 27)
    .
    This is reme—
    died by the Agency’s recommendation that the effluent levels be averaged
    over a 30-day period with no more than 5 of the samples greater than
    2.5 times the levels in cuestion. Abbott’s second point is that the
    Agency’s recommended levels are more restrictive than the levels in
    Abbott’s NPDES permit, issued by the U.S. Environmental Protection Agen-
    cy. These levels are set in the permit at 20 mg/i BOD and 25 mg/l sus-
    pended solids (R. 23)
    .
    Though we~arenot bound by the federal permit,
    we feel it would be unfair for Abbott to have to worry about meeting
    two rather close standards. Therefore, we will order Abbott to maintain
    an effluent of 20 mg/i BOD and 25 mg/i suspended solids. Abbott is ask-
    ing the U.S. Environmental Protection Agency to drop these standards
    from the NPDES permit. Should such standards be removed, the Board
    still feels for the purpose of this variance that standards are necess-
    ary for its discharge.
    The second point raised relates to when Abbott must divert to the
    Gurnee plant. The Agency wants diversion within 30 days of the date
    the plant is completed for secondary treatment. Abbott suggests that
    in that time, the Sanitary District may not authorize Abbott to divert
    the flow, for reasons beyond Abbott’s control. We agree. Abbott should
    not be put in jeopardy of our Order because of actions by a third party
    out of Abbott’s control. Therefore, we will order Abbott to divert to
    Gurnee within 30 days of receiving notice to do so by the North Shore
    Sanitary District, but no later than 90 days after the completion of
    the treatment plant.
    This Opinion constitutes the findings of fact and conclusions of
    law of the Board.
    ORDER
    IT IS THE ORDER of the Pollution Control Board that:
    Abbott Laboratories is granted variance from Rule 404 (d), Chapter 3,
    Water Pollution Regulations, for the waste treatment plant in North
    Chicago, Illinois, for a period of one year, subject to the following
    conditions:
    1. That BaD5 and suspended solids concentrations be limited to
    a monthly average of 20 and 25 mg/i respectivelym determined
    on the basis of 24—hour composite samples averaged over any
    consecutive 30-day period. In addition, no more than 5 of
    the samples collected shall exceed 2.5 times the limitations
    herein established for BOD5 and suspended solids;
    2. That Petitioner shall divert its treatment flow to the Gurnee
    sewage treatment plant at the earliest practical date, but in
    no event later than 30 days from the date the North Shore San—
    14
    751

    —4—
    itary
    District gives Abbott notice to divert, or 90 days
    after secondary treatment facilities are completed, which-
    ever is Sooner;
    3. That Petitioner file monthly operating reports with the
    Agency indicating daily laboratory results on the parameters
    in question.
    I, Christan L. Noffett, Clerk of the Illinois Pollution Control
    Board, certify that the above Opinion and Order was adopted by the
    Board on the 19th day of December
    ,
    1974, by a vote of 4
    to 0
    /
    /
    ;~
    ~
    1
    .
    14
    752

    Back to top