ILLINOIS POLLUTION CONTROL BOARD
November 22, 1974
PRECISION FABRICATOR, INC. and
CITY OF SOUTH BELOIT,
Petitioners,
vs.
)
PCB 74—337
ENVIRONMENTAL PROTECTION AGENCY,
Respondent.
OPINION AND ORDER OF THE BOARD (by Mr. Henss):
Petitioners seek variance from a sewer extension ban in order
to connect a metal fabrication plant to the sewer system of the
City of South 13e’oit. The ban has been imposed by the Agency
pursuant to the requirements of Rule 921 of Chapter 3, Water
Pollution Regulations.
The record reveals that the City of South Beloit operates a
sewage treatment facility employing brush aeration providing
secondary treatment for a design average flow of 1 million gallons
per day and a maximum flow of 2.5 mgd. After receiving chlorination
the plant effluent is discharged directly into the Rock River.
Influent flows exceeding 2.5 mgd are by—passed to the Rock River
without receiving even primary treatment. Storm water infiltration
has been a problem. Flows in the past have reached 5 mgd at times
but the City has expended $100,000 to curtail excessive infiltration
and did thereby reduce the average influent flows to 3.3 mgd for
the months of January through December 1973.
This plant is required to meet the following standards: 20 mg/i
for BOD, 25 mg/l for suspended solids and 400 per 100 ml. for fecal
coliform. Grab samples taken in 1974 showed the plant consistently
meeting the standard for suspended solids and slightly over the
standard for BOD on only one occasion. However, fecal coliform
counts substantially exceeded the limitation on every date samples
were taken with counts ranging from 2,000 per 100 mu to 32,000 per
100 m/l.
The chief products of Precision Fabricators are weidments varying
from sheet stock to heavy plate stock. However, the only facilities
that will require sewer connection are the toilets and basins. These
14 —521
—2—
facilities provide accomodations for 13 full—time employees in
the day shift and 7 second shift employees. The company has
existed at its present location for a number of years and was
serviced by a private sewage disposal system until the “Easter
weekend” flood of 1973 which rendered this private system in-
operative. Since the Spring flood of 1973 the septic system has
remained flooded and attempts to drain the septic field have been
unsuccessful. The Agency agrees that ground water conditions may
make proper operation of a septic system impossible.
At the present time sewage from this septic system is spilling
upon the top of the ground causing a serious nuisance and health
hazard. The President of Precision Fabricators states that the
sewage problem interferes with the hiring of new employees pre-
sumably because potential employees do not wish to work in such
unhealthy conditions. He states that he needs 25 men to handle
his work backlog but that two more men are now quitting and he
cannot maintain the shop with just 11 people on his work force. The
President states that if his Company is not granted a permit to
attach to the sewer the Company will be forced out of business.
The plan is to construct a 310’ extension to the existing sewer
line of the City of South Beloit. According to Thomas Nee, a
Professional Engineer and Land Surveyor, this sewer connection
is “the most economically feasible alternative, considering the
life of
the
system and the ground water condition for a new septic
or holding tank installation”. Mr. Nee also states that the
extension will cause no overflows upstream or downstream of the
connection.
The Agency states that the additional load from the Petitioner
would be inconsequential at the South Beloit sewage treatment
plant and recommends that the variance be granted.
The Board finds that the faulty septic system causes a health
hazard which is a substantial hardship to Precision Fabricator, Inc.,
its employees and the public generally. The health hazard will be
eliminated by a sewer connection to the South Beloit sewage system.
The health hazard apparently cannot be reduced by minor maintenance
of the existing sep~ic system. Therefore, the variance will be
granted and the parties uiged to take the necessary steps to make
this sewer connection as soon as possible.
This Opinion constitutes the findings of fact and conclusions
of law of the Illinois Pollution Control Board.
14—522
—3--
ORDER
It is the Order of the Illinois Pollution Control Board that
Petitioners, Precision Fabricators, Inc. and City of South
Beloit, be granted variance from the sewer extension ban in order
to connect the metal fabrication plant at 200 Oak Grove Avenue
to the sewer system of the City of South Beloit. Petitioner
Precision Fabricators, Inc. shall apply for all necessary permits.
I,
Christan L. Moffett, Clerk of the Illinois Pollution Control
Board, hereby certify the above Opinion and Order was adppted
this _____________day of
f)~’~r4~i.4.4&~
,
1974 b~a vote of ton.
14—523