ILLINOIS POLLUTION CONTROL BOARD
    October 24, 1974
    )
    CATERPILLAR TRACTOR COMPANY
    )
    (Joliet Plant)
    )
    )
    )
    v.
    )
    PCB 74-233
    )
    )
    ENVIRONMENTAL PROTECTION AGENCY
    )
    )
    OPINION AND ORDER OF THE BOARD (by Mr. Dumelle):
    Petition for variance from the Water Pollution Regulations
    (Chapter 3) was filed on June 19, 1974. Variance was requested
    from Rules 203, 205, 401, 402, 404(a), 404(b) (ii), 902, 903, and
    1002. On June 27, 1974 the Board entered an order for additional
    information asking the reasons for the delay in meeting the
    biochemical oxygen demand standard (BOD5).
    Caterpillar filed an amended petition on July 26. The Agency
    filed its recommendation on August 29. No public hearing was held.
    The Caterpillar plant, on Route 6 in Joliet, manufactures
    earthmoving and construction machinery and equipment and employs
    approximately 6,000 persons. Industrial wastewater amounting
    to 770,000 gpd is generated by plant utilities, metal removal,
    and cleaning and coating operations. The plant processes about
    16,400 tons of raw materials (castings, forgings, unformed steel,
    etc.) per month. Discharge is to the Des Plaines River.
    Caterpillar alleges that the discharge was recently found to
    contain levels of BUD5 from 30-100 mg/l compared to the Rule
    404(a) standard of 30 mg/i. Using a 7-day, once-in-lU-year, low
    flow of 1000 MGD the petitioner alleges a contribution of only
    0.3~o additional BOD5 to the Des Plaines River over that normally
    present.
    The petitioner states that a consulting firm, Clark, Dietz
    and Associates, was retained on April 25, 1974 and their final
    report is due November 1, 1974. The amended petition also states
    that Caterpillar’s regular sampling “until very recently indicated
    compliance with existing standards”. An independent comparative
    analysis was made and the higher strength discharges were then
    discovered. No dates are given for these events.
    14
    273

    —2—
    The Agency presents Caterpillar’s own Operation Reports giving
    monthly averages of 24-hour composite samples:
    MONTHOctober,AND
    1973YEAR
    BUD345mg/i
    November, 1973
    46 mg/i
    December, 1973
    27 mg/i
    January, 1974
    23 mg/.l
    February, 1974
    25 mg/i
    March, 1974
    30 mg/i
    Aprii, i974
    35 mg/i
    May, 1974
    June, 1974
    116 mg/i
    The Agency points out that the October and November, 1973 values
    are above the 30 mg/i level set by Rule 404(a). It also points out
    that Rule 404(b) tightens the BODç effiuent limit to 20 ing/l after
    December 31, 1974 and that Caterpfliar should have filed a Project
    Completion Schedule prior to December 31, 1972 to tell how this
    tighter limit was to be met (Rule i002(b)(iii)). In fact, states
    the Agency, the Project Compietion Schedule filed on February 5,
    1973 was silent on BUD5 improvement.
    The history of the Sanitary Water Board (a predecessor board
    to the Pollution Controi Board) with this plant is given by the
    Agency. A permit was issued March 14, 1967 limiting BUD5 to 40 mg/i
    but the petitioner is quoted as indicating its treatment works
    would meet 30 mg/i.
    We
    do not feei that variance is necessary from Rule 203 because
    this rule deals with General Standards and the Des Plaines River
    is a “Secondary Contact” classification in the reach of the dis-
    charge. A variance from Rule 205 is unnecessary. Rule 401 is
    not applicable since it is in the nature of general philosophy
    and guidance. Rule 402 does not apply because no water quality
    standards violati.ons are shown.
    We are thus left withRules 404(a), 404(b)(ii), 902, 903 and
    1002. We grant the variance with respect to these Rules. Counsel
    for Caterpillar has pointed out that given the low apparent BUD
    values, a “tuning-up” or process improvement could have been con-
    templated by management without the necessity for new waste
    treatment plant construction and for a Project Completion Schedule
    which would mention BUD improvement.
    Management perhaps saw the December, 1973
    -
    April, 1974 BUD
    values as indicative that operational changes were possible.
    Later the true values of the BUD levels were discovered and are
    much higher than thought.
    14
    274

    -3-
    By this opinion we do not mean to excuse the failure of
    Caterpillar’s laboratory to adequately measure BUD levels.
    Caterpillar maintains responsibility for the actions of its
    agent; in this case, the laboratory. Other dischargers are
    well advised to periodically have independent checks run on
    their analyses to make certain that correct values are being
    determined.
    Caterpillar has shown good faith by engaging a consultant
    on April 25, 1974. A report is due November 1, 1974. However,
    Caterpillar might have discovered the incorrect levels of BOD
    much earlier had some laboratory quality control procedures
    been in effect.
    Rules 902 and 903 were replaced by Rules 952 and 953
    effective October 11, 1974. Both of the Operating Permit
    requirements have been suspended, from October 11, 1974 until
    the earlier of January 31, 1975 or the date the Administrator
    of the U.S. Environmental Protection Agency rejects the Illinois
    NPDES Permit Program submittal, for dischargers who have to
    obtain an NPDES permit.
    This Opinion constitutes the Board’s findings of fact
    and conclusions of law.
    ORDER
    1. Variance from Rules 203, 401 and 402 is dismissed.
    2. Variance from Rules 205, 404(a), 404(b) (ii), 902, 903
    and 1002 is granted from June 19, 1974 to January 1, 1975.
    IT IS SO ORDERED.
    I, Christan L. Moffett, Clerk of the Illinois Pollution
    Control Board, hereby certify the above Opinion and Order we e
    adopted on the
    ~
    day of October, 1974 by a vote of
    —~
    Illinois Pollution Control Board
    14—275

    Back to top