ILLINOIS POLLUTION CONTROL BOARD
October 24, 1974
J. RUSSEL MILLER,
Petitioner,
v.
)
PCB 74—230
ENVIRONMENTAL PROTECTION AGENCY,
Respondent.
DISSENTING OPINION (by Dr. Odell)
I dissent from the decision adopted by Pollution Control
Board (Board) for several reasons. First, the facts of the
case do not establish that Petitioner has met his test of
arbitrary or unreasonable hardship under Section 35 of the
Environmental Protection Act. The majority Opinion admits in
the second paragraph of page three that “Petitioner’s hardship
was largely self-imposed.” While it is clear that a
denial of the variance will impair the Petitioner financially,
and will delay service to the City of North Chicago, it is not
the responsibility of the Board to see to it that every community
has dental care by granting variances to the first contractor
——
albeit financially con5trained
——
who makes such care possible.
Second, the case sets a bad precedent. While the majority
through “very close weighing of the particular balancing con-
siderations” obviously wants the decision to quietly evanesce,
it cannot be so. Not only may the decision encourage others to
take unnecessary risks in expectation of Board rescue, but the
decision also may be a disservice to more needy individuals who
have been denied variances in the past. To dilute the test of
arbitrary or unreasonable hardship leaves the Board standardless;
it lowers the public’s estimation of and confidence in the Board.
I would deny the variance for the above reasons stated.
c~7T~Wt
Russell T. Odell
I, Christan L. Moffett, Clerk of the Illinois Pollution Control
Board, hereby certify that the above Dissenting Opinion was sub-
mitted on the/~~day of
/
y
~j.__d,
1974.
14
—
265
-2-
Dr. Ron Stanczak, D.D.S., for the remaining floor. Petitioner further
claims that he has previously built two commercial buildings (a Yankee
Doodle Hamburger Restaurant and a Pizza Hut Restaurant) on the land
for which the variance is sought; and that these were connected to
the sewer after the rezoning, but prior to the sewer ban. It is
further claimed that the increase in sewage load will be very low, and
that two-thirds of the proposed load is now entering this sewer.
Petitioner alleges that the only alternatives to connecting onto the
said public sewer are to haul the sewage away or to construct a septic
system, either of which, it is alleged, would be a costly expense
in comparison to the requested sewer connection.
From the Amended Petition and discussions with Petitioner, the
Agency has gathered the following information:
a) The subject building has been completed.
b) Petitioner has let one floor of the three—story building
to two dentists at a monthly rental of $1200. Their
lease begins November 1, 1974.
c) Petitioner plans to let no other space in the building
until the sewer ban is lifted.
d) Petitioner has investigated the use of a holding or
septic tank and has found that the City of North Chicago
will not permit these alternate systems.
e) Petitioner is in deep financial trouble due to this business
venture and another in which he has invested $70,000 of
his own money. He is well over $350,000 in debt and is
having a difficult time selling condominium units (the subject
of the other venture) due to the present tight money situation.
Of 21 units which comprise the condominium structure built
by Petitioner, ten have been sold. Three others have been
purchased but they have been unable to obtain financing.
All of the money received as payment for the condominiums
has gone to the bank to pay off the loan.
f) Petitioner estimates that the additional load on the North
Chicago treatment plant will be about 40 gallons per day.
The Agency states that the additional load that Petitioners proposed
connection will add to the North Chicago sewage treatment plant is minimal.
In addition to the fact that only forty gallons per day of wastewater
is estimated, many of the dentists’ patients reside in the area served
by the North Chicago waste treatment plant and would thus add no additional
load to the plant.
The Agency believes that Petitioner has established a substantial
hardship. The lack of available alternative methods of treatment leaves
Petitioner the choice of either obtaining a sewer connection or allowing
his building to remain vacant until the ban is lifted.
14
—
266
—3—
We are disposed to grant this variance for connection, subject
to the condition that said connection shall service only the floor
leased by the two dentists. A balancing of Petitioner’s economic
hardship, minimal additional sewer load, and service provided to
the community weighs in favor of a grant of the subject petition.
A denial of this variance would impair Petitioner financially,
further delay a needed service to the City of North Chicago, and do
little to protect the environment.
In reaching the decision to grant this limited relief, we
are not unmindful that Petitioner’s hardship, onerous as it may
be, was largely self-imposed. We note also that this Petition could
have been and should have been filed at a much earlier date. It
was only after very close weighing of the particular balancing
considerations detailed above and the specific facts presented that
we decided to grant the minimal relief necessary to sustain Petitioner.
This Opinion constitutes the findings of fact and conclusions of
law of the Board.
IT IS THE ORDER of the Pollution Control Board that 3, Russel
1liller be granted a variance to allow connection of the subject
property; provided that said connection shall service only the floor
leased by the two dentists.
Mr. Dumelle and Dr. Odell dissent and Mr. Duinelle will
file a dissenting opinion.
I, Christan L. Moffett, Clerk of the Illinois Pollution Control
Board, certify that the abo e pinion and Order was adopted on this
_____________
day of
,
1974 by a vote of
.3— ~
(~.
~
H-
14
—
267