ILLINOIS POLLUTION CONTROL BOARD
    September 12, 1974
    AMERICAN CYANANID COMPANY,
    )
    Petitioner,
    vs.
    )
    PCB 74—227
    ENVIRONMENTAL PROTECTION AGENCY,
    Respondent.
    OPINION AND ORDER OF THE BOARD (by Mr. Henss):
    American Cyanamid Company requests variance from Rule
    204(f) (2) of the Air Pollution Control Regulations until
    May 1, 1975. Variance is sought in order to allow sufficient
    time to install and operate an acid mist eliminator on
    Petitioner’s contact sulfuric acid plant in ~3oliet. The
    Agency requested consolidation of this case with EPA vs.
    American Cyanamid, PCB 74—209, an enforcement case. However,
    consolidation was not possible because of the short time
    available for deciding this variance case.
    Petitioner’s sulfuric acid plant, which is located
    adjacent to a residential area, produces 150 tons of sulfuric
    acid per day (12,500 lbs./hr.)
    .
    Rule 204(f) (2) limits 1\merican
    Cyanamid to emissions of 0.15 lbs. acid mist/ton of acid produced.
    The Company conducted stack tests in 1973 which showed a sulfuric
    acid mist emission rate of 1.5 lbs./ton of acid produced. American
    Cyanamid is going to install a Brink Fibre Bed High Efficiency
    Mist Eliminator in its process at a point before the discharge
    stack. The $133,500 mist eliminator was ordered on May 17, 1974
    and delivery was promised by September 20, 1974.
    Cyanamid originally estimated that the control device would
    not be operative until May 1, 1975. In its Recommendation, the
    Agency objected to the long installation and shake down period.
    Petitioner answered that the long period was selected to allow
    for possible delays in delivery, installation problems or initial
    operating problems. Petitioner now states that it. hopes to have
    the control device installed by December 1, 1974 but requests that
    it be given at least until December 31, 1974 to allow for any
    unforeseen problems.
    13—599

    The Agency believes the device will allow Petitioner to
    achieve compliance with the Regulation but, because of past delays
    created by Petitioner, recommends denial of this variance. The
    Agency claims to have received complaints of sulfur odors from
    persons in the adjacent residential area and at least three area
    •~residents have voiced strong objections to the granting of this
    variance. Cyanamid answers that the odors experienced by its
    neighbors were a result of abnormal or accidental operating
    conditions
    in the alternative, the Agency recommends granting the
    variance only until December 1, 1974 subject to the posting of
    a bond, stack tests, monthly progress reports and the securing
    of all required permits.
    We are empowered to grant a variance if compliance with the
    Rule would cause an unreasonable or arbitrary hardship. Rule
    204(f) went into effect on December 31, 1973. Petitioner has
    not offered any explanation whatsoever for its failure to meet
    that deadline. The burden is on Petitioner to show that com-
    pliance would cause an unreasonable and arbitrary hardship and
    we cannot grant a variance unless there is some evidence on
    that issue. Since the record is totally silent as to the reason
    for Petitioner~s failure to meet the deadline we must find that
    Petitioner has failed to sustain its burden.The variance will be
    denied.
    This Opinion constitutes the findings of fact and the
    conclusions of law of the Illinois Pollution Control Board.
    ORDER
    It is the Order of the Pollution Control Board that Petitioner~s
    request for variance from Rule 204(f) (2) be denied.
    I,
    Christan L. Môffett, Clerk of the Illinois Pollution
    Control
    Board, hereby certify the above Opinion and Order was adopted
    this j~~day of\~t~1974 by a vote of _____to ~
    O4~LA2~J~
    f~&jkth1
    13—600

    Back to top