ILLINOIS POLLUTION CONTROL BOARD
    February 27, 1975
    MARBLEHEAD LIME
    M,
    )
    Petitioner?
    vs.
    )
    PCB 74—146
    ENVIRONMENTAL PROTECTION AGENCY,
    Respondent.
    Richard Elledge, Attorney for Marblehead Lime Company
    Tom Casper and John Palincsar7 Attorneys for the Agency
    ~OPINION AND ORDER OF THE
    BOARD (by Mr. Henss):
    Marblehead Lime Company filed its Petition for
    Variance
    on
    April 24, 1974 seeIçing relief from Rule 203 (particulates) of
    the Air Pollution Control Regulations pending installation and
    operation of air pollution control equipment, The parties
    engaged in a number of pre—hearing procedures, including
    discovery. Marblehead waived its right, which exists under
    Section 38 of the Environmental Protection Act, to have its
    Variance Petition decided in 90 days. The matter finally went
    to hearing on September 23, 1974. During this hearing Marblehead
    sought to introduce testimony dealing with the economic feasi-
    bility of alternative control systems. This testimony was not
    allowed by the Hearing Officer. Marblehead also sought a
    continuance in order to prepare rebuttal testimony. This Motion
    was also denied.
    On October 2, 1974 Marblehead filed a Motion to Reconvene
    the hearing alleging that the Hearing Officer had erred in
    excluding testimony on the economic feasibility of alternative
    control systems. Over Agency objection the, Board ordered that
    one additional hearing be held at a time convenient to both
    parties but no later than December 1, 197.4. For some reason the
    additional hearing was not held, but the Agency requested and
    the Hearing Officer ordered additional discovery.
    On December 18, 1974 Marblehead filed a ~‘Moticnfor Leave to
    Amend and for Consideration of the Merits of Said Petitionu. We
    infer that the company wished to avoid the rather extensive
    discovery then being sought by the Agency. The Marblehead motion
    15
    —567

    —2—
    was in substance a request that the Board decide the case on the
    basis of the record which had already been established. It was
    in effect an abandonment of the company’s request for additional
    hearing and the abandonment of further opportunity to introduce
    evidence regarding economic feasibility of alternative control
    systems. The Board granted the Marblehead request and will now
    consider the Amended Variance Petition and the record which was
    presented.
    Marblehead operates a calcimatic kiln in Meirose Township,
    Adams County, Illinois for the production of pebble lime. The
    facility, also known as the “Quincy operation”, is situated on
    Illinois Route 57 approximately 1 1/2 miles south of Quiricy.
    Marblehead sold its entire Quincy operation to Calcium Carbonate
    Company while this action was pending. Under terms of the sale,
    Marblehead has leased the calcirnatic kiln from Calcium Carbonate
    for an initial term of five years with the option to extend the
    lease for two successive five—year periods. Calcium Carbonate
    has agreed to provide Marblehead with sized limestone for the
    kiln.
    Terms of the sale also provide that Marblehead shall indenmify
    Calcium Carbonate ag~install expenses, liabilities, losses,
    damages, injunction suits, fines, penalties, claims and misdemeano~
    arising out of violation of any law, ordinance or regulation.
    In the Amended Petition for Variance Marblehead seeks relief
    from Rules 203(a) and 203(b) in order to operate the kiln pending
    installation of control equipment and for an indeterminate period
    of time after installation of the control equipment.
    This petition seeks relief from two mutually exclusive regulations
    for an indefinite period of time.
    Two
    problems are immediately
    apparent. Petitioner’s operation is governed either by Rule 203(a)
    or Rule 203(b) but not both. Further, the Board is not authorized
    by the Environmental Protection Act to grant indefinite variances
    (See: Environmental Protection Act, Section 36).
    Stipulated facts show that:
    1. As of April 14, 1972 and for a period of 60 days
    thereafter, Petitioner had neither applied for nor
    been granted a variance from any operation at its
    Quincy facility,
    2. Petitioner had not commenced actual on—site fabri-
    cation of equipment to control emissions from the
    calcimatic kilns, and
    3. As of April 14, 1972 no control equipment was in-
    stalled or operational for the calcimatic kiln.
    15—568

    —j—
    These stipulated facts clearly show that Petitioner failed
    to meet the two conditions of Rule 203(c) by which it could have
    been allowed to comply with Rule 203(b) instead of the more re-
    strictive Rule 203(a). Therefore, emissions from the calcimatic
    kiln are now subject to compliance with Rule 203(a). Rule 203(b)
    is not applicable.
    The calcimatic kiln is a gas—fired rotary hearth lime kiln.
    Preheated limestone is fed onto the hearth which rotates at a slow
    speed under six burners. During one revolution of the hearth,
    limestone is calcined and then swept off the hearth as it approaches
    the charging station. The kiln processes an average of 1.5 tons
    of limestone per hour.
    Petitioner’s Chief Engineer, Charles Norton, testified that
    he had observed emissions from this kiln and numerous other Marble-
    head kilns over a period of years. In particular, he visually
    compared emissions from the Quincy kiln to emissions from Petitione’r’s
    South Chicago operation. These visual comparisons indicated that
    the Quincy emissions were more clear than the South Chicago emissions.
    Therefore, Norton believed that the Quincy emissions were in com-
    pliance with the limitations of Rule 203(b).
    Agency employee, Ed Campbell, testified that he first informed
    Ma~rb1eheadof possible violations in a letter dated May 12, 1972.
    Campbell and another Agency employee then visited the Quincy
    facility
    in June 1973.
    During this visit Campbell again informed
    Marblehead representatives that emissions from the kiln were, in
    his opinion, in violation of applicable emission limitations.
    Norton apparently persisted in his belief that visual comparisons
    did not show any violation. Because of these differences in
    opinion, Marblehead agreed to perform a stack test on the kiln
    emissions.
    Two stack tests were conducted on September 29, 1973 by
    Marblehead personnel in the presence of two Agency observers. At
    a limestone feed rate of approximately 15,000 lbs./hr. the two
    tests showed emission rates of 359 and 464 lbs. of particulates
    per hour. These figures are in excess of the allowable emission.
    rate. At this process weight rate Rule 203(a) allows emissions
    of 7.55 lbs./hr.
    Norton testified that he had no reason to believe the emissions
    were this high before the test and that he was surprised by the
    results (R. 90). As a result of these tests, Marblehead decided
    to send a sample of the particulates to an outside consulting firm
    for a particle sized distribution analysis. This analysis indicated
    that about 87 of the particles were in excess of 10 microns.
    Norton testified that it was the “extremely large size” of the
    particles that caused his visual observation to be in error (R. 90)
    15— 569

    Marblehead proposes to control emissions from the calcinatic
    kiln by installing two #50 series, 43A Buell cyclones in parallel.
    These particular
    cyclones were previously used at Petitioner’s
    South Chicago facility for a number of years.
    Nortcn testified
    that the cyclones were
    refurbished in 1967 and removed from service
    in 1969 when Petitioner installed baghouses at the
    South Chicago
    facility. The parties have stipulated that the cyclones would
    be
    expected to have a collection efficiency of between 94 and 97
    under normal operations. At
    this level particulate emissions
    would
    range from 14 to 28 lbs./hr.
    Norton testified that Petitioner could install
    the
    two cyclones
    in six months on a “crash program”.
    Routine installation
    of the
    two cyclones would take about one year.
    Some delay could be expected
    in the crash program if steel delivery were
    delayed. The cyclone
    installation project would cost about $25,000 exclusive of the
    value of the cyclones.
    Petitioner has installed the baghouse control devices on every
    kiln it operates
    except for the Quincy kiln. Norton estimated that
    a baghouse for the QuIncy kiln would cost between $6 and $8 per
    ACFM CR. 108) or $150,000 to $200,000 CR. 70)
    .
    Agency Engineer
    Campbell disagreed with Norton’s assessment stating that Norton’s
    figures were high and that values of $5 to $7 per ACFM and totals
    of $75,000 to $120,000 were more realistic CR. 158). Campbell
    conceded that recent inflation would tend to favor the higher
    estimated cost.
    The Quincy operation represents approximately 1 to 2 of
    Marblehead’s total production capability.
    Clarence Jorgensen,
    Marblehead’s Vice President of Operations, testified that fuel
    for the kiln was uncertain and that use of oil was questionable
    because of cost and possible contamination of product.
    According to Marblehead fluctuating market conditions, kiln
    operating costs and kiln capacity would make the installation of
    a baghouse economically unreasonable. Ten or eleven men now
    employed to operate the kiln could no longer be employed by
    Marblehead if the kiln were shut down.
    The Agency rejects Petitioner’s contention that control efforts
    were not implemented at an earlier date because the company believed
    that emissions from the kiln were within the allowable rate. The
    Agency believes that visual observation, citizen complaints and
    Agency communications over the past several years should have
    warned Petitioner that it had a problem.
    Only one citizen witness testified about problems caused by
    emissions from the Quincy facility. Mrs. Charles Dyer, who
    resides one block from the Quincy facility, testified that her
    husband had complained to Marblehead about the emissions “a long
    time ago” (R. 44). Mrs. Dyer is unable to open windows in her house
    15
    570

    —5—
    or hang out clothes to dry because of
    the emissions. She
    claimed
    that
    paint on their
    last three
    automobiles has been
    ruined by the emissions.
    Although the record shows the
    existance of several sources of particulates
    other than the
    Quincy kiln, Mrs. Dyer was positive in her identification
    of
    the kiln as the source of problems she and her husband have
    encountered CR. 47).
    In this case, as in others (See:
    EPA v. Marblehead, PCB
    73-223) we find that excessive particulate
    emissions from a
    limestone processing plant can cause nuisance and short term
    health effects in the community.
    This variance cannot be granted based on the record pre-
    sented.
    Emissions from the calcimatic kiln are clearly in violation
    of the allowable emission rate. Although Petitioner plans to
    install equipment to reduce these emissions, the record clearly
    shows that this equipment simply is not capable of bring~~Lnqthe
    Quincy facility into compliance.
    Testimony shows that it would be technically feasible to
    install a baghouse on the kiln. The dispute boils down to the
    issue of whether or not the installation of a baghouse is
    economically reasonable. As the Agency asserts, the mere fact
    that installation of a baghouse would be more expensive to
    Petitioner than installation of the cyclones does not justify
    granting a variance. Section 3(b) of the Environmental Protection
    Act states that adverse effects upon the environment are to be
    fully considered and borne by those who cause them. The record
    shows that Petitioner seeks to operate in continuous violation
    of the environmental standard under the protection of the variance.
    We are unable to grant Marblehead that type of relief and would
    not be inclined to do so if we had the authority.
    The record shows that Petitioner has the expertise and
    capability to design and install baghouse control devices. This
    capability is clearly shown by the fact that Petitioner has
    already installed at least 13 baghouse control devices at other
    installations throughout the country. We do not wish to cause
    unnecessary expenditures of funds. We favor compliance with
    environmental standards by the most inexpensive methods available.
    Petitioner should now re—evaluate its position in order to bring
    its emissions into compliance. We believe that Marblehead has
    both the engineering and financial capacity to do this.
    We have carefully considered the character and degree of inter-
    ference with the protection of health, welfare and physical
    property of the people; the social and economic value of the
    pollution source; the suitability of the pollution source to the
    area in which it is located; and the technical practicability and
    economic reasonableness of reducing the emissions. We conclude
    that Marblehead has not established its right to the variance
    requested.
    15—571

    —6—
    This Opinion constitutes the findings of fact and conclusions
    of law of the Illinois Pollution Control Board.
    ORDER
    It is the Order of the Pollution Control Board that the
    Amended Variance Petition be denied without prejudice.
    I, Christan L. Moffett, Clerk of the Illinois Pollution Control
    Board, hereby certify the above Opinion and Order was adopted
    this j~~day of
    , 1975 by a vote of ~

    Back to top