T’XACO fl~C
(LO ‘KP3RI RFFINFR
PL~IlIIONER
~ a
coac~
t~c 3
ci a
pet
t x ~ I~xa~ In
Va ra e
ii
r ~u1e O~
g
i a a a aye ~t
i~
un~
ct
a.
LO- OOt~
1
0
,
Y
ne
a Sc
i
Pe~iLi
is ~ ~e a Zuie
c3~r ~
‘~
3
a~d
I~
Tue Ag n v ~ccommer d~ t.
g r t
fecommend t
i~led
3
2
,
7’
T~e Loc Tort rc ir~r
It
has a
cap
rackarg
Jiarge eoct~
called coas dr~n~
as aug oae ation waiT o~y
ore aruir te~ne used ~t a a u~ 1
o ~‘har o a routed
a di r
where rackirci tat
~ e~3) of tTc ~ra
ano ~omc of
tue c~argc a laid
OvL
a Lhe dir
1h aapo~ pr case t
the iractionatana
ow~x for ccpa~at n
Wher ~e batck is eompl~cd
LTe drum a~ complete~y ± II of por r ~ohe
A thas point
there
no f rther _np~t iito
Trur
vapors a
£
stal) goirg off t
the frac ronating tower fo: p oceslng
At this
oiut b1owdo~n f
the uni~ takes places
~.
yap ~s are erouted t a blowdown k~o Y-~
out drum
Steair is ther ~njected
into the druri to purge the vapors
from the coke drura~ Then the aag r is water~cooled in the blowdowr~
quench drums Part of the vapo~ are liquefied and are i~scharged
to the sewers
The renai~arg vapor’~ are discharged to the atma
phere and are the vaporr ar quest o~
Vapor emissions o~hydrocarooru~ are as foI1ows~ 253~4 lbs/hr.
-
13
—
301
31,500 ppm.. The
limit
set in Rule 205 (g) (2) is 10 ppm.. Such emiss-
ions are of a periodic nature, existing only when the unit is being
blown down..
The control proposed for these vapor emissions is a knockout pot
to
collect and condense the vapors further.. Non-condensable vapors
will then be routed to a smokeless flare.
Petitioner~s compliance schedule
to
complete installation
of
the
proposed equipment is as follows:
Jan.. 28,
1974
Apply
for
IEPA
construction
permit
Feb.. 22,
1974
Contract for concrete construction
to
be awarded (other construction
work
to be done by in—house per-
sonnel)
March 15, 1974
Start construction
Sept.. 1, 1974
End construction
Sept.. 1, 1974
Start operations
This project is, estimated to cost $80,000..
The Board takes notice of the fact that though Rule 205 (g) (2)
went intc effect on December 31, 1973, a permit ~.oconstruct
this
equipment
was
not applied for
until
January 28, 1974, a month later..
Nowhere (Ices Petitioner allege any reason for this delay. Attached
to the Petition is a chart indicating that this project has
been in
the
works since May of 1972. The Board fails to understand why in-
itiating the construction of this project did not begin until 22
months after initial consideration was given by Texaco to this pro-
ject. It appears that there is no new or novel technology being
used to control this emission source.. This Board cannot speculate
as to why this project could not have been accelerated to meet
the
December 31, 1973, deadline. While there may have been acceptable
reasons for this delay, the Petition is devoid of such evidence.. It
is clearly the burden of Petitioner to supply such data, and without
it the Board must find that Petitioner has failed to establish due
course for the grant of variance..
Hardship:
Petitioner alleged that it would suffer unreasonable and arbitrary
hardship if this variance is not granted? for the reasons that follow..
1, It cannot comply with Rule 205 (g) (2) before September 1,
1974, because of fixed delivery dates from equipment vend-
ors, beyond Petitioner~s control..
2. A shutdown of the unit from May
1,
1974, until September
1, 1974, would decrease production by 960,000 barrels of
gasoline, 678,000 barrels of middle distillate, and 28,320
tons of coke. Backup in tankage causes a loss of 184,000
barrels of recovered gas oil. These products would be lost
to the public and would cost the Petitioner $1,376,322. Pet-
itioner would have to lay off 22 persons for four months and
31 persons for one month..
13— 302
The hardship case
thus rests
on
th~epossibility of
an enforcement
action being filed should Petitioner/fail
to
cease operations in vio-
lation of Rule 205 (g) (2)..
It must be
noted that even
if
this Board
were to grant variance, Petitioner
is
still liable to enforcement
for the period of January 1, 1974,
to
April 2, 1974 (the date of fil-
ing of the original variance petition).. This Board cannot help but
wonder why, if Petitioner is concerned with possible enfOrcement act-
ion, they waited until April 2, 1974, to file for variance, If the
project for abatement was initiated in 1972, Petitioner should have
filed its petition by October 1, 1973, to assure itself total protect-
ion. Surely Petitioner was aware that
it
would not be in compliance
by December 31, 1973.. Therefore, Petitioner by its own inaction has
left itself open for enforcement proceedings for a significant per-
iod of time. In
light of this the Board’must
find that Petitioner
has not met its burden of proof regarding hardship, or even that such
hardship was not self-imposed.
Environmental
Impact:
Petitioner alleges that there will be no injury to the public from
the grant of this variance,
in
that its emissions do not contribute
to photochemical smog.. Air monitoring performed for Petitioner
by
Air Resources, Inc., taken between November 19, 1973, and December 17,
1973, showed the following results:
Ill, ppm
Pollutant
Ambient Air
~n~~Con~ibution
Standard
Oxidants
0.059
0,001
0.08
NO~
0.017
0.001
0.05
No data
is
presented
to show how the refinery
contribution was cal-
culated,
Petitioner alleges that
its discharges will not contribute
to photo-
chemical smog.. This conclusion is
based on tests which show that less
than five percent of
its emissions are olefinic compounds. This
con-
clusion, however, is not sufficient
to meet
the criteria as outlined
in Chapter 2 of the Board Rules..
The definition of photochemically
reactive material includes three distinct categories of organic emiss-
ions. Petitioner explores only one
—
olefinics. There is no mention
of aromatics of eight carboh
atoms or
more,
or of ethylene, branched
hydrocarbons, or
toluene.. ~The
combination of any
of the
above may
not
exceed 20, nor can
the aromatics alone exceed 8 to be considered
non-photochemically reactive.. Without such data the Board cannot accur-
atel~assesss the contribution such vapors will add to the potential of
photochemical smog.
The Board takes note of the recent high ozone levels in the Chicago
major metropolitan areas.. As such we must be even more aware that
photochemical smog can no longer be assumed a potential problem, but
one which becomes more real as time goes on..
On April 4 an Agency inspector noted no odors outside the refinery
boundaries. The refinery is in an industrial area with no residential
buildings within 1/4 mile of the facility.. The Agency has received
no citizen complaints..
13
—
303
OS
rt~
~ mb
U
g
ho So id
S
o icasor
0
a
nu~ coral da U
a
or:
fo~ TO
urar
a a ~r
tha
a a ci as
are e
U
U
emertal
ro~ U a
t
a or
d
P~tm
i,i
e
~~or
~
Te ar cut
r
~“i
a ~y
deq aU o
ta a’~ ra~e x r giaa
e t
t
3
to
d ~ort ose ar
rru~ Cc
C
ci i~
w le
ch ate nay ear St at las
t
~e
do a ~l
p esented
t~
e So r
TU ‘a~ian e v all cc U
tl
U
o:e
di e ~o alio
00t ~ ne to ‘~eir~tiate ~his proceed ro ~r 3
a a adequate pro
r ror
arpose~ delay
U a
a
rIm a
~ non cors ~‘t ~
Ia
Lb
lard
IT IS THE OR~U f tIe So 1 at
octro
3oa I
pel-itior. for
~n e ~Ueb
apra~
5,
1951
.~
~
~s
‘~ —~
withoU
prejudice
1, Chris~an L.. Moffett, Clerk of tIme ~ lano s P Ilution ContoU
Board, o~rtafy that the above OpanUn a d drder ‘gas adoptea by ~he
Board on the 8th 3c~y of August, 1 4, by a vot~ f 4 to 0
13— 304