ILLINOIS POLLUTION CONTROL BOARD
November 22, 1974
ILLINOIS CENTRAL GULF RAILROAD,
)
Petitioner,
v.
)
PCB 73—547
ENVIRONMENTAL PROTECTION AGENCY,
Respondent.
Mr. Joseph W. Phebus, attorney for Petitioner.
Mr. Michael Ginsberg, attorney for Respondent.
Order of the Board (by Dr. Odell)
On December 21, 1973, Illinois Central Gulf Railroad
(Illinois Central) filed with the Pollution Control Board
(Board) a Petition For Variance from Rules 202(b), 203(b),
and 205(f) of the Illinois Air Pollution Regulations (Chapter
Two). Illinois Central sought a one—year variance from Rule
205(f) and a variance until June 30, 1976, from Rules 202(b)
and 203(b) of Chapter Two. Petitioner operates an open air
spray painting operation in Centralia, Illinois. The Illinois
Central paints approximately 3000 railroad cars yearly at the
facility. Some cars are painted inside and out, some are
stencilled for identification. In its Petition, Illinois
Central stated that a new painting facility was in the pre-
liminary design stage; it was not sch~du1edto be completed
until June 30, 1976.
On January 25, 1974, a Centralia resident filed with
the Board an objection to the grant of a variance claiming that
the spray painting operation was turning the town orange and
that “we no longer wash our windows, we scrape them.” The
Environmental Protection Agency (Agency) recommended on February
13, 1974, that a six-month variance be granted from Rule 205(f)
of Chapter Two and that a one—year variance be granted from
Rules 202(b) and 203(a). On March 8, the Illinois Central inde-
finitely waived the 90-day requirement of final Board action
under Section 38 of the Environmental Protection Act (Act).
The Petitioner filed an Amended Petition For Variance on
June 26, 1974, requesting a variance from Rule 202(b) and 203(b)
of Chapter Two to extend from January 1, 1974, through December
31, 1975. Petitioner estimated that it would have its new in-
door facilities completed by the end of 1975. Construction was
scheduled to begin on October 1, 1974, with completion fifteen
14
—
489
—2—
months later. A construction permit had been granted by the
Agency on May 25, 1974. At the present time, to minimize the
overspray problem, Illinois Central was building temporary
shielding walls around its outdoor operation. These walls
were expected to be completed by July 1, 1974. On an average
day 12.4 railroad cars are painted at the facility; the average
car receives 21.9 gallons of paint weighing 203.67 pounds.
Therefore, the average hourly process weight was calculated at
315.68 lbs,’hour.
The Agency filed its Amended Recommendation on August 21,
1974. The Agency felt that under Rule 203(c), Petitioner had to
comply with Rule 203 (a) not 203 (b). Since the Petitioner under
Rule 203(c) was in violation of Rule 203(b) on the effective date of
the Chapter Two Regulations, Illinois Central was required to
meet the Rule 203(a) standard by December 31, 1973. Based on
Illinois Central1s process weight of 315.68 lbs/hour, the allow-
able emission rate of particulates under Rule 203(a) is .95 lbs/
hour. The Agency stated that Petitioner’s proposed spray paint
facility with its four spray booths would limit particulate
emissions to .79 lbs/hour. The Agency noted that citizens
contacted did complain about spray paint from Illinois Central’s
operation on their automobiles and homes. However, the Agency
stated that the temporary painting facility would minimize over-
spray. The Agency did not state how effective the temporary
facilities would be in reducing the impact on area residents.
The Agency recommended that the Petitioner be granted a
variance from Rule 202(b) and Rule 203(a) of Chapter Two until
May 30, 1975, subject to certain reporting requirements as well
as the successful operation of the temporary overspray shielding
walls. The Agency stated that the December 1975 date was reason-
able.
A hearing was held on September 25, 1974, in Marion County,
Illinois. Respondent began the hearing by amending its Amended
Petition in two respects. First, Respondent agreed with the
Agency that Rule 203(a) not 203(b) was the applicable rule regard-
ing the particulate emissions. Second, Respondent sought a
variance until March 1, 1976, instead of the original December 31,
1975, date in the Amended Petition. Respondent called one witness
to establish arbitrary or unreasonable hardship under Section 35
of the Act. The Agency called no witnesses and no citizens came
forward to testify during the hearing. The testimony by the
Illinois Central employee established that the December 1975 dead-
line could not be met, because no bids had been submitted on
Petitioner’s original contract proposal; changes were made in
this contract, and all bid submissions were due by October 31,
1974 (R. 7). It is not known whether any contractors bid on this
revised contract. The witness testified that other facilities
were not available to do the paint work done at Centralia (R. 18).
The temporary shielding walls have been installed. Twenty-five
feet high walls have been constructed in an area relatively remote
from the homes of area residents on plant property to permit paint
spraying and undercoating.
14 —490
—3—
The highest rail cars painted at the fapility are
seventeen feet tall (R. 13). The witness was uncertain how
effective the walls were in controlling the 23 average over-
spray that occurs (R. 23, 25). He had only visited the site
once for a brief period (R. 22); he was also unsure of whether
overspray problems occurred near the ends of the shielding walls
(R. 22); he did not know how close neighbors were to the spray
operations (R. 22). The witness estimated that overspray was
reduced by a factor of five because of the walls (R. 32)
-
There
are no walls at the old stenciling area where cars are sprayed
for identification purposes. However, only 10 of the total
caint sprayed at the facility is consumed in the stenciling pro-
cedure (R. 29). The facility employs 540 people (R. 12).
We grant the Petitioner a variance from June 26, 1974,
until May 30, 1975. While we agree with the Agency that a
variance is warranted, the inadequacies in the record do not
permit us to decide whether a variance should be granted to a
later date. Specifically, the record does not disclose the
effectiveness of the temporary walls in protecting neighbors
from overspray. While we note that no citizens came forward to
the hearing to protest the variance grant, under Section 35 of
the Act, Petitioner has the burden of proof to show arbitrary or
unreasonable hardship. Second, it is unclear why the variance
petition was filed as late as December 1973. Chapter Two be-
came effective in April 1972. While delays after the decision to
undertake compliance can be explained, the belatedness in start-
up was not answered. Third, the evidence was unconvincing on the
issue of whether compliance would be achieved by March 1976. The
record does not disclose whether the contract has now been let or
whether the fifteen month completion schedule is a term in the
contract, not merely an estimate subject to continual revision.
ORDER
IT IS THE ORDER of the Pollution Control Board that
Illinois Central is granted a variance from Rule
202(b)
and
203(a) of Chapter Two from June 26, 1974, until May 30, 1975,
subject to the following conditions:
A. Petitioner shall submit monthly progress reports
to:
Illinois Environmental Protection Agency
Division of Air Pollution Control
Control Program Coordinator
2200 Churchill Road
Springfield, Illinois 62706
The first monthly report is due January 1,
1975. Each report shall indicate progress
made toward completing the control program
outlined in Petitioner’s construction permit.
14
—491
—4—
B. Petitioner shall operate the temporary paint
spray facility according to the specifications
and location detailed in Petitioner’s Exhibit 9
of the Amended Variance request.
C. Petitioner shall operate this temporary paint
spray facility to minimize overspray impact on
the public until the completion of its new
paint spray operation.
IT IS SO ORDERED.
I, Christan L. Moffett, Clerk of the Illinois Pollution Control
Board, hereby certify that the above Opinion and Order was
adopted on the
~
day of
4
~
,
1974, by a vote of
___
to p
Christan L~fett
14
—492