ILLINOIS POLLUTION CONTROL BOARD
    March 14, 1974
    NATIONAL CASTINGS DIVISION,
    MIDLAND-ROSS CORPORATION,
    Petitioner,
    vs.
    )
    PCB 73—531
    ENVIRONMENTAL PROTECTION AGENCY,
    Respondent.
    Mr. John J. Pallarn, Attorney, on behalf of Petitioner;
    Mr. Peter B. Orlinsky, Attorney, on behalf of Respondent.
    OPINION AND ORDER OF THE BOARD (by Mr. Seaman):
    On December 14, 1973, National Castings Division,
    Midland-Ross Corporation, filed its Petition For Variance,
    seeking therein variance for a period of one year from the
    provisions of Rule 203(a) of the Air Pollution Regulations.
    Rule 203(a) governs particulate emission standards and
    limitations for new process emission sources. A hearing was
    held in this matter on February 25, 1974.
    On January 24, 1974, the Agency recommended that
    the Board deny the variance, or in the alternative, dismiss
    the Petition with leave to file an Amended Petition. The
    Agency’s recommendation was based upon the absence of a firm
    and viable compliance program. On February 4, 1974, Petitioner
    filed its Amended Petition For Variance, including therein
    its schedule of compliance. Based upon this compliance
    schedule, the Agency has recommended that the variance be
    granted, subject to certain conditions.
    Petitioner is the operator of a steel foundry lo-
    cated in Meirose Park, County of Cook, Illinois. Petitioner
    manufactures 400 tons per week of steel castings and employs
    350 persons.
    Petitioner’s facility utilizes a 20 ton electric
    arc furnace, 2 core sand mullers, 4 core ovens, 4 mold sand
    mullers, a shakeout operation,~ a sand reclaimer and other
    related sand handling and finishing operations. The Agency
    states that, ~ith the exception of the uncontrolled shakeout
    11 — 587

    —2—
    operation, the other operations are apparently adequately
    controlled with respect to particulate emissions.
    Petitioner~s shakeout operation is the subject
    of its Petition For Variance, The poured castings in
    the sand molds are conveyed to the shakeout area. This
    operation utilizes a vibratory floer to separate the sand
    from the castings. The dust generated from these big
    vibrating floors is collected. by a side-draft hood with
    two 60,000 CFM fans. After being shaken out the castings
    are pulled away and the sand fails down through the floor.
    The dust (sand) emissions generated from the
    shakeout operation are ducted directly to the atmosphere
    through the roof. A type of deflector cap has been added
    above the exhaust vents for the purpose of knocking some
    of the dust emissions out of the airborne plume and onto
    the roof. This was observed by the Agency to have a rather
    limited degree of effectiveness.
    Petitioner processes 2O~000 lbs. per hour of steel
    castings and 105,000 pounds per hour of 98,8 silica sand
    and 1,2 clay through its shakeout facility. The shakeout
    area operates during the day shift and stack tests have
    revealed emissions to be 54,8 pounds per hour. Allowable
    emissions are 21 lbs/hr, not 44~6lbs/hr as stated in the
    Petition. Because Petitioner was in violation of the par-
    ticulate regulations prior to April 14, 1973, it is conse-
    quently subject to Rule 203(a)
    Petitioner has indicated to the Agency that until
    recently it was not aware that its emissions were in excess
    of those allowed by Rule 203 which became effective
    December 31, 1973. There are no published emission factors
    for shakeout operations similar to that of Petitioner. In
    July, 1973, Petitioner conducted a stack test, the results
    of which demonstrated that shakeout emissions were excessive.
    Petitioner immediately hired the Purity Corporation to conduct
    an engineering study in order to establish a control program.
    The results of that study led to the proposed installation
    of a Pentapure Impinger to control particulate emissions.
    Petitioner’s compliance schedule is as follows:
    Present to 2-1-74
    Obtain quotes from:
    I. Purity Corporation
    2.
    American Air Filter
    3, Kirk and Blum, ~nc.

    —3—
    3-1-74
    Release contract for
    pollution equipment
    3-1—74 to 6—1-74
    Engineering
    6—1—74 to 9—1—74
    Installation
    9-1-74
    Startup and debug
    Petitioner’s compliance program states that the
    date for startup and debugging of the pollution control
    equipment is September 1, 1974. Petitioner has, however,
    requested a variance for one year. The Agency states
    that the proposed control equipment will bring Petitioner
    into compliance with Rule 203(a). The Agency believes
    that a one year project completion schedule is more rea-
    listic than one which envisions startup by September 1, 1974.
    Petitioner estimates the installation cost of the proposed
    control device to be $150,000.
    The nearest residential area is approximately
    200 feet to the east of Petitioner’s facility. A number
    of residents were contacted from this area. In general,
    the people contacted reported either no problems or minor
    dust problems. Not one resident contacted objected to
    granting of the variance..
    This Opinion constitutes the findings of fact
    and conclusions of law of the Board.
    IT IS THE ORDER of the Pollution Control Board
    that Petitioner be granted variance from the provisions
    of Rule 203(a) of the Air Pollution Regulations i.antil
    December 31, 1974, subject to the following conditions:
    1. Commencing 30 days from the date of this
    Order, Petitioner shall submit quarterly reports to the
    Agency detailing its progress toward compliance. Said
    reports shall be addressed to:
    Environmental Protection Agency
    Division of Air Pollution Control
    Control Program Coordinator
    2200 Churchill Road
    Springfield, Illinois 62706
    2. Petitioner
    shall apply for all necessary con-
    struction and
    operating permits from the Agency.

    -4-
    3. Within 30 days from
    the completion of installation of
    the subject pollution control equipment, Petitioner shall have
    performed a stack test acceptable to the Agency.
    The
    Agency shall be
    notified at least
    5
    days prior to the testing, and shall be allowed
    to have representatives present to observe the testing. The results
    of all tests shall be submitted to the Agency.
    4. Within 35 days from the date of this Order, Petitioner
    shall post a performance bond in a form satisfactory to the Agency
    in the amount of $25,000, guaranteeing the installation of the subject
    control equipment.
    I, Christan L. Moffett, Clerk of the Illinois Pollution Control
    Board certify that the a ove Ooinion and Order was adopte on this
    /44 ‘
    day of
    fr~
    1974 by a vote of
    ______________

    Back to top