ILLINOIS POLLUTION CONTROL BOARD
    January 3, 1974
    CITY OF CARBONDALE
    PETITIONER
    v.
    PCB 73—430
    ENVIRONMENTAL PROTECTION AGENCY
    RESPONDENT
    JOHN PAUL WOMICK, ATTORNEY, in behalf of the CITY OF CARBONDALE
    DEL HASCHENIVIEYER, ASSISTANT ATTORNEY GENERAL, in behalf of the EN-
    VIRONMENTAL PROTECTION
    AGENCY
    OPINION
    AND ORDER OF THE BOARD (by Mr. Marder)
    This case comes to the Board on Petition of the City of Carbon-
    dale for variances from: Rule 203 A, Rule 203F, Rule 404, Rule 405,
    and Rule 1002 of Chapter 3 of the Water Pollution Regulations of Ill-
    inois, filed with the Board October 10, 1973. The Agency filed its
    recommendation on November 20, 1973. A hearing was held and testimony
    taken on November 30, 1973. No citizens appeared to be heard at the
    hearing.
    Petitioner made two motions at the hearing. The first was to the
    fact that a hearing was taking place. It was the contention of the
    Petitioner that because the Agency recommendation was filed late, that
    it should be held for naught, and since there would then be no object-
    ions to a grant of the variances, hearing should not be held. Section
    37 of the Environmental Protection Act (Chap. 111 1/2 Ill. Revised
    Statutes 1037) states:
    “If the Board, in its discretion, concludes that a hear-
    ing would be advisable, or if the Agency or any other per-
    son files a written objection to the grant of such vari-
    ance within 21 days, then a hearing shall be held...”
    The Board determined that a hearing should be held and so ordered
    on November 29, 1973.
    The second motion related to the Agency’s failure to file its
    recommendation within the 21-day limit as prescribed in Rule 403 (a)
    Procedural Rules of the Illinois Pollution Control Board. The Petit-
    ioner contends that because the recommendation is so late, it should
    be stricken.
    10
    543

    —2—
    In Benjamin Harris & Company v. Environmental Protection Agency,
    PCB 73-215, the Board allowed a recommendation filed 48 days late to
    remain in the record, even though it was filed only two days before
    the hearing.
    The Board said, “We do not interpret it (Rule 403 tafl
    to mean that a recommendation must be stricken if filed after 21 days.”
    The Petitioner has not shown that it was prejudiced because of late
    filing of the recommendation.
    Petitioner’s
    motions are denied and the record as submitted by the
    hearing officer shall be considered in its entirety.
    Petitioner is a municipal corporation located in Jackson County,
    Illinois.
    It encompasses an area of approximately 10 square miles,
    and has a population presently estimated at 26,756 (Pet. P. 2). It
    is the home of Southern Illinois University.
    The city and the univers-
    ity have grown dramatically as reflected by the city’s population of
    14,670 in 1960 to its present level.
    Existing Facilities: Northwest Treatment Plant
    This plant is a trickling filter plant with anaerobic sludge diges-
    tion and sludge drying beds. It discharges an effluent, the average
    quality of which is BOD, 21.2 mg/l and suspended solids 30 mg/l, to
    Little Crab Orchard Creek, tributary to Crab Orchard Creek and the Big
    Muddy River. The plant’s capacity is .75 mgd or a population equiv-
    alent of 7500 (R. 8).
    Southeast Treatment Plant:
    This plant employs the contact stabilization type of activated sludge
    treatment system. It discharges an average effluent the quality of
    which is BOD 15.5 mg/l and suspended solids 13.5 mg/l to Crab Orchard
    Creek, which is tributary to the Big Muddy River. The plant’s design
    capacity is 5.0
    ingd
    or a population equivalent of 40,000 (R. 8).
    Petitioner reports (Pet. P. 37) that the quantity and type of raw
    wastewater processed is as follows (influent)
    N.W. Plant
    S.E. Plant
    Average daily flow
    0.622 mgd
    3.53
    rngd
    Average BOD5
    149 mg/i
    221 mg/l
    Average temp.
    64° F.
    64.5°F.
    Average S/S
    131 mg/i
    145.6 mg/l
    Average Set. Solids
    1.1 mg/l
    4.6 mg/l
    Average PH
    7.0
    7.1
    The Agency in its recommendation (Pg. 4) reports the following
    data as it pertains to recent operations of both the Northwest and
    Southeast plants:
    10
    544

    —3—
    AGENCY EFFLUENT
    GRAB
    SAMPLES
    Northwest Sewage Treatment Plant
    BOD
    TSS
    Fecal Coliform
    NH -N
    Date
    (nig/l)
    (mg/i)
    (Counts/i00 ml)
    (m~/l)
    Jan 17/73
    3
    37
    ~i00
    3.8
    Feb 26/73
    12
    14
    ‘lOO
    1.5
    Mar 16/73
    11
    24
    ~O0
    0.43
    Apr 16/73
    3
    16
    ~100
    1.7
    May 18/73
    4
    21
    ‘~l00
    0.88
    Jul 12/73* 45
    340
    1,600
    32.0
    *
    Samples collected after the drawing off of anaerobic digester sup—
    ernatant.
    AGENCY EFFLUENT
    GRAB
    SAMPLES
    Southeast Sewage Treatment Plant
    BOD
    TSS
    Fecal Coliform
    NH -N
    Date
    (mg/i)
    (mg/i)
    (Counts/100 ml)
    (m~/l)
    Jan 17/73
    4
    6
    2,900
    14.0
    Feb 26/73
    3
    1
    ~l00
    12.0
    Mar 16/73
    17
    6
    ‘100
    8.8
    Apr 16/73
    4
    18
    ~100
    13.0
    May 18/73
    18
    22
    .l00
    18.0
    Jun 8/73
    10
    7
    ~l00
    8.5
    Jul 12/73
    10
    20
    U00
    8.0
    Rule 203 (a) provides that the state’s waters shall be free “from
    unnatural sludge or bottom deposits, floating debris, visible oil, odor,
    unnatural plant or algae growth, unnatural color or turbidity, or mat-
    ter in concentrates or combinations toxic or harmful to human, animal,
    plant, or aquatic life of other than natural origin.” Petitioner re-
    quests relief from this rule only to the extent that a variance from
    Rule 404 would cause Petitioner to violate this rule for both the
    Northwest and Southeast plants.
    Rule 203 (F) provides that there shall not be a concentration of
    ammonia nitrogen exceeding 1.5 mg/i. Petitioner requests relief from
    this rule for both the Northwest and Southeast plants.
    Rule 404 (b) as it applies to this case provides that on and after
    July 1, 1972, no effluent source whose untreated wasteload is 10,000
    population equivalent or more shall exceed 20 mg/l of BOD or 25 mg/I
    suspended solids. Petitioner requests relief from this rule for the
    Northwest plant.
    Rule 404 (c) as it applies to this case provides that on or after
    December 31, 1974 (this rule amended by new Rule 406 as applied to Pet-
    itioner by Board Order date July 19, 1973, In the Matter of Water Poll-
    ution Regulation Amendments, PCB R-73-3, R—73-4) no effluent whose dil-
    ution ratio is less than five to one shall exceed 10 mg/i BOD5 or 12
    10—545

    —4—
    mg/l suspended solids. Relief is requested for both plants (Northwest
    and Southeast)
    Rule 404 (f) as it applies to Petitioner states that on or after
    December 31, 1974 (amended by Board Order PCB R-73-3, R-73-4)
    ,
    no ef-
    fluent whose dilution ratio is less than one to one shall exceed 4
    mg/i of BOD5 mg/i.
    Rule 405 states that no effluent covered by Part 4 of Chapter 3 of
    the Rules shall exceed 400 fecal coliforms per 100 ml after July 31,
    1972.
    Rule 1002 states that a project completion schedule for modifica-
    tion of wastewater facilities to comply with effluent standards other
    than Rules 407 and 408 that were originally set to go into effect on
    December 31, 1973, was to be filed by September 1, 1972.
    It is understood that in the past the City of Carbondale has done
    a commendable job in controlling water pollution (Agency Rec. P. 7).
    The problem that faces the city of Carbondale is that which faces other
    municipalities in upgrading their wastewater systems: That problem is
    funds. The city has been attempting to obtain grant funding from the
    Federal government. In its petition the city alleges, and the Agency
    denies in its recommendation, that through administrative errors and
    poor advice from the Agency, the city lost an offered grant to upgrade
    the Northwest plant, and a #2 priority position for FY 1973 funding was
    lost by a decision of the Agency that the old Northeast plant should
    be closed and cost effectiveness analyses be prepared within 7 days as
    to the one plant versus the two plant concept. The city was then rele-
    gated to the 21st position in the priority list. Further delays took
    place which took the city past July 1, 1973. As of that date infiltra-
    tion-inflow studies are required to be submitted with grant applications.
    Such studies are now in progress, but their completion time is estimated
    •at 12-18 months from now.
    The Agency denies allegations as to its own culpability as to the
    delays that the city has encountered over the past three years. The
    record at hearing did not bring out these points, and so the Board
    reaches no conclusions as to their truth. They are noted as one of Pet-
    itioner’s reasons for delay in compliance.
    The city further alleges a very tight financial situation. The
    city now has a bonded indebtedness of $13 million (R. 46), which is only
    $1 million away from its debt limit ceiling. Also, because of changes
    in the Federal government’s arrangement with the city for supplying
    water from Crab Orchard Lake, the city has had to embark on a $7 mill-
    ion project to construct a new water resrvoir. Water and sewer rates
    in the city have increased 63 over the past 3 1/2 years (R. 53). The
    city doubts that the citizens would approve another bond issue that
    would increase their rates still further. They also feel that it would
    be extremely difficult to find buyers for bonds issued, since the debt
    limit is already so high (Pet. P. 48).
    Petitioner should be cognizant of the Board’s power to order bonding
    over a community’s debt limit (League of Women Voters v. North Shore
    Sanitary District, PCB 70—7, 12, 13, 14).
    10
    546

    -5—
    The Agency questioned the relationship of the city’s compliance plan
    to obtaining grant money (Agency Rec. P. 7)
    .
    To this question, the
    city through its treasurer and finance director, Paul T. Sorgen, stated
    that if Federal money would not be available, the city would attempt to
    comply by gathering whatever available money it could to meet its obli-
    gation to its citizens and. the state to provide for environmental con-
    trol to preserve the state’s water quality.
    The Board takes notice of the fact that control of sewage is not done
    oy hooking up a simple control device to a unit at a small cost and
    short construction lead time. It is expensive and time-consuming work
    that should be done in a thorough manner and done right the first time.
    To have a “crash program” of compliance would be inordinately expensive
    and wasteful.
    The city has been working to bring its facilities into compliance
    for quite some time in furtherance of its desire to upgrade its facili-
    ties. It has retained the engineering firm of Clark Dietz & Associates
    of Urbana, who prepared extensive reports as to population growth and
    how the present system must
    be upgraded to handle the population. These
    reports contained data as to the upgrading of sewage collection facili-
    ties, along with future needs of the entire wastewater system through
    the year 2000. Though most of these reports are not relevant to the
    questions before the Board, they are appreciated. Their inclusion al-
    lowed the Board to put into perspective the magnitude of the work fac-
    ing the city.
    The city, with the aid of its consulting engineers, has determined
    that to bring its system into compliance in the most reasonable yet in-
    expensive way, the following actions must be taken:
    Project I: Chlorination, effluent pump station, and outfall sewer
    from Northwest plant to the Big Muddy River (this last proposal is to
    allow the plant’s effluent to be discharged to a waterway where it
    would have a higher dilution ratio and thusly allow for a higher BOD
    and suspended solids in the effluent (R. 11).
    Project II: Expansion of the Northwest plant (It is unclear from
    the record whether this would be a rise to 2.5 mgd, 2.0 mgd, or 1.5
    mgd).
    Project III~ An outfall sewer from the Southeast
    plant to the Big
    Muddy River.
    Project IV:
    Sewer system repair and reconstruction.
    These actions
    are to be completed in three steps. Based on the re-
    quirements to get grant money:
    Step I. 1. Infiltration-inflow analysis: Northwest sewer system
    begun July 1973.
    2. Infiltration—inflow analysis: Southeast sewer system
    work begun August 1973.
    10
    547

    —6—
    3. Sewer system evaluation
    -
    Northwest system.
    4. Sewer system evaluation
    -
    Southeast system.
    5. Revised preliminary design report
    -
    Northwest plant
    and sewer system.
    6. Preliminary design report Southeast plant and sewer
    system.
    7. Prepare and enact equitable use charge and industrial
    waste recovery system as per U.S. Environmental Pro-
    tection Agency guidelines.
    8. Revise environmental assessment and hold public
    hearings.
    Step 2.
    Final engineering designs based on data collected in
    Step One.
    Step 3.
    Construction
    Project I
    Chlorination, effluent, pump station and out-
    fall sewer from Northwest plant to the Big Muddy River.
    Project II
    -
    Expansion of the Northwest plant to 1.5 or
    2.0 mgd.
    Project III
    -
    Outfall sewer from existing Southeast plant
    to the Big Muddy River.
    Project IV
    Sewer system repair, sealing, and extension
    required (Pet. P. 43-45).
    The time schedule for compliance is as follows:
    Step 1:
    1. Infiltration-inflow analysis Northwest system
    3/1/74
    2. Infiltration-inflow analysis Southeast system
    3/1/74
    3. U.S. Environmental Protection Agency review and 6/1/74
    analysis
    4. Sewer system evaluation Northwest system
    12/1/74
    5. Sewer system evaluation Southeast system
    4/1/75
    6. Revised preliminary design report Northwest
    12/1/74
    plant and sewer system
    7. Preliminary design report Southeast plant and
    4/1/74
    sewer system
    10—548

    —7—
    8. Prepare user charge industrial waste cost re— 10/1/75
    covery system
    9. Revised environmental assessment and public
    10/1/75
    hearing
    Step 2:
    1. Complete design and secure easements, project I, 2/1/75
    new effluent pumping, chlorination, outfall Big
    Muddy River
    2. Complete design Project II expansion Northwest 5/1/75
    plant
    3. Complete design, easements Project III, outfall 4/1/76
    sewer from Southeast plant to Big Muddy River
    Step 3: Construction
    1. Environmental Protection Agency Review Project I 5/1/75
    2.
    Open bids Project I
    6/1/75
    3. Award contract Project I
    7/1/75
    4. Begin operation Project I
    12/1/75
    5. Environmental Protection Agency Review Project 8/1/75
    II
    6. Open bids Project II
    9/1/75
    7. Award contract Project II
    10/1/75
    8. Begin operation Project II
    6/1/76
    9. Environmental Protection Agency Review Project 7/1/76
    III
    10. Open bids Project III
    8/1/76
    11. Award contract Project III
    9/1/76
    12. Begin operation Project III
    12/31/77
    The Board feels that this is a fair and adequate schedule, based on
    the size of the job to be done, and on the financial constraints on
    the city, which does not allow it to employ an army of people to do all
    the projects concurrently. The Board would appreciate in the future a
    breakdown as to the construction time as outlined in the schedule.
    This extensive discussion of the background of the case is not nec—
    10—
    549

    —8—
    essary to reach the conclusions that will follow. The purpose of the
    discussion is to allow the city in future variance petitions concern-
    ing this subject to rely on the record herein submitted with updates
    as to plans and costs as each new petition is filed.
    To summarize the above numerical data the city’s plans are simply
    as follows: To do nothing to the Southeast plant except divert the flow
    from the present receiving stream to the Big Nuddy River. This project
    alone will allow conformance with the 1974 rules. This is a very im-
    portant point. The existing plant is not overloaded as is the case in
    many similar actions before the Board; it merely suffers from poor geo-
    graphy. The regulation requiring 4 mg/i 130D and 5 mg/i S/S came into
    effect after this plant was constructed and thus is a new constraint
    put on the facility. The Agency noted in its investigation no visible
    pollution downstream of the plant (Agency Rec. p. 4). The plant as of
    now is producing effluent which would be acceptable in all but the most
    stringent conditions. The same is true for the Northwest plant. The
    only reason for Project II is to meet future growth
    -
    the plant is pres-
    ently producing a quality effluent (from Agency Recent Data).
    Perhaps the best indication of what the plants’ effect on the recei-
    ving stream is could be gleaned from a review of the operating reports
    (Appendix B & C of Variance Petition)
    .
    This was referred to by Mr.
    Schwegman (P. 26). The following table is a summary of results.
    STREAM
    DATA
    Plant
    -
    Date
    D.O. Upstream
    D.O. Down. BOD Up BOD Down
    Southoast 1/73
    12.2
    12.3
    4.3
    5.3
    2/73
    12.6
    12.7
    4.3
    4.3
    3/73
    3.2
    3.2
    4/73
    13.9
    13.1
    4.4
    3.2
    5/73
    8.0
    7.9
    7.5
    7.5
    6/73
    7.3
    6.0
    Northwest 11/72
    1.00
    .75
    12/72
    10.0
    8.3
    3.1
    3.6
    1/73
    83
    68
    34
    79
    2/73
    79
    70
    32
    80
    3/73
    9.1
    8.7
    4.2
    7.4
    4/73
    9.9
    9.2
    6.8
    4.1
    From the above it would seem that the Southeast plant has a very
    small effect on the receiving stream, and
    the
    Northwest plant has a
    much greater effect. The Board notes that the compliance plan present-
    ed calls for completion of Project I by December 1975. This will re-
    move the worst offender first.
    The Board finds as follows:
    1. The variance from Rule 203 A is denied.
    2.
    The
    variance from Rule 203 F is granted.
    3. The variance from Rule 404 (b) is denied.
    10—550

    —9—
    4. The variance from Rule 404 (c) is denied.
    5. The variance from Rule 404 (f) is denied.
    6. The variance from Rule 405 is denied.
    7. The variance from Rule 1002 is granted.
    The variance from Rule 203 a is denied. The record shows that there
    is no actual violation of this rule by Petitioner (Agency Rec. P. 4-5).
    The granting of a variance presupposes a continuing violation of law
    (N. 56). (Swords v. Environmental Protection Agency PCB 70-6.) To be
    granted a variance the Petitioner must be in violation of the law (En-
    vironmental Protection Agency v. Borden Chemical Company, PCB 71-23)
    The variance from Rule 405 is denied for the same reason as 203 a.
    There is no violation. Rule 405 states that for a violation the ef-
    fluent must exceed 400 fecal coliform per 100 ml. The Agency recommend-
    ation (P. 4) shows coliforms of less than 100/100 ml. To avoid future
    prosecution, the City should continue to use chlorination on the North-
    west plant.
    The variance from Rule 404 (h) is denied for the same reasons as
    above. To violate this section, the effluent source must have an un-
    treated wasteload of 10,000 population equivalent or more. The North-
    c~estplant has a population equivalent, as shown in the record and not
    rebutted, of 7500. There is no violation.
    The variances from Rules 404 (.c) and (f) are denied because there is
    no violation at this time. As mentioned above, by Board order (July
    19,
    1973) in R 73-3 and R 73-4 these effluent standards do not go into
    effect until December 31, 1974.
    With no regulation in effect,
    there is
    no violation. When there is no violation, a variance cannot be granted
    (Swords v. Environmental Protection Agency, supra, and Environmental
    Protection Agency v. Borden Chemical Company, supra). The Board will
    look with favor on a variance petition brought by Petitioner at the
    proper time.
    The variance from Rule 203 f will be granted. It is shown that Pet-
    itioner is in violation of this rule. Petitioner’s hardships in bring-
    ing about compliance with this rule are outlined above as to the long-
    range improvements that must be done on the plants and funding for such
    projects. Environmental impact data is greatly lacking on this point,
    and nefore the Board will grant any future variances from this rule,
    such data must be provided to the Board.
    The variance from Rule 1002 is also to be granted. The city has showr
    in its petition that there have been certain delays beyond its control
    in formulating definite compliance plans. This variance will be limit-
    ed to 120 days. At this time a plan shall be submitted to the Agency
    detailing compliance, with cost figures and proposed financing arrange-
    ments included. These propQ~ed fi~ncing arrangements shall be based
    both on a possible federal funding and/or funding should no federal
    10— 551

    10
    grants be available.
    One further point will be made in closing. The Board finds that
    there is confusion between the parties as to which regulations are in-
    deed applicable.
    It would be incumbent for Petitioner to spend some
    time reviewing Regulation 404 and its subsections. This review should
    be made with the full cooperation of the Environmental Protection Agen-
    cy. It is clear that if both plants were to continue discharging to
    their present discharge streams, Rule 404 (f) would apply. However,
    404 (f) (ii) is in effect an exception clause.
    It would behoove Pet-
    itioner to explore the economics of meeting this exception clause in
    comparison with its proposed plan.
    This Opinion constitutes
    the findings of fact and conclusions of law
    of the Board.
    ORDER
    IT
    IS
    THE ORDER of the Pollution Control Board that:
    1. Variance from Rule 203 a is denied without prejudice.
    2.
    Variance from Rule 203 (f) is granted for one year from the en-
    try of this Order. Any subsequent variance petition from this
    rule shall be filed at least 90 days before this variance ex-
    pires.
    3. Variance from Rule 404 (Sections (b) (c) and
    (f) are dismissed
    without prejudice.
    4. Variance from Rule 405 is denied without prejudice.
    5. Variance from Rule 1002 is granted for 120 days from receipt
    of this Order by Petitioner. The compliance plan required
    shall include proposed financing for the project schedule as
    discussed in the Opinion.
    IT IS SO ORDERED.
    I, christan L. Moffett, Clerk of the Illinois Pollution Control
    Board, certify that the above Opinion and Order was adopted by the
    Board on the 3rd day of January, 1974, by a vote of 5 to 0.
    10—552

    Back to top