ILLINOIS POLLUTION CONTROL BOARD
January 3, 1974
GENERAL TIRE AND RUBBER COMPANY
)
(MOUNT VERNON TIRE PLANT),
Petitioner,
v.
)
PCB 73—371
ENVIRONMENTAL PROTECTION AGENCY,
Respondent.
Don Musick and William Henrick, Attorneys for Petitioner
Fred Hopper, Assistant Attorney General for the EPA
OPINION AND ORDER OF THE BOARD (by Mr. Henss)
General Tire and Rubber Company is in the final phase of
construction of a $40 million radial tire manufacturing plant
in Mt. Vernon, Illinois. Plant heat and process steam require-
ments for the plant are to be supplied by two 70 million Btu/hr.
Murray-Trane boilers.
On July 23, 1973, Petitioner applied to the Environmental
Protection Agency for a construction permit for the oil fired
boilers. At that time, Petitioner specified that *6 fuel oil
with a sulfur content of 0.74 would b~used for fuel. Satisfied
that Petitioner’s emissions would he in compliance with all Rules
and Regulations, the Agency granted the construction permit on
September 12, 1973.
After making application for the construction permit but
before the Agency approval, Petitioner discovered that it was
unable to secure any firm commitment for the low sulfur fuel
oil. General Tire then filed a request for variance from Rule 204
of the Illinois Air Pollution Control Regulations in order to
temporarily allow the burning of #6 fuel oil containing 3 maximum
sulfur content (2.5 typical).
In the Petition for Variance, Petitioner stated that the plant,
designed to produce 2,000 radial tires per day, was scheduled for
startup in
mid-November
1973. Attached to the Petition were copies
of letters from 9 major oil
companies which substantiate
10
—
529
—2—
Petitioner’s claim that extensive efforts to secure low sulfur
fuel oil have been fruitless. Adding to Petitionerts fuel
problem is the present fuel allotment program which is based on
1972 fuel usage.
Petitioner was not in operation during 1972
and thus
did not establish a base allotment on which to secure
fuel for 1973.
General Tire maintains that the requirement for
variance
will exist until the Company can
1) secure adequate commitment
for supplies of #2 fuel oil, #5 low sulfur fuel oil, or #6 low
sulfur fuel oil, or 2) select, design, engineer and install a
flue gas desulfurization unit on the plant’s single stack.
General
Tire has already initiated efforts to
control sulfur oxide and
estimates that a flue gas
desulfurization control program will
cost from $300,000 to $1 million.
If the variance is allowed, General Tire agrees to
1) con-
tinue to seek low sulfur fuel oil, 2) seek a long—term contract
for low sulfur fuel oil, or, 3) in the event such fuel oil contracts
are not secured by August 1, 1974, install sulfur oxide removal
equipment by May 30, 1975.
The Agency states that Petitioner has made a serious attempt
at compliance and should be granted the variance subject to certain
conditions. An Agency representative visited the plant site on
September 4, 1973 where he discussed the proposed variance with
several area residents. They made no objection to the granting
of the variance.
A public hearing on the variance request was held on November 20,
1973. Petitioner’s plant engineer, John Cappellin, testified that
the plant is now scheduled for startup in mid-December 1973. During
the design phase of the plant, General Tire had originally considered
natural gas, #2 fuel oil and *6 fuel oil for the plant boilers.
Natural gas was quickly eliminated from further consideration when
it was learned that supplies of this fuel were not available for
commercial establishments in the Mt. Vernon area.
After filing the variance petition, General Tire was able to
secure 550,000 gallons of #6 fuel oil from a local supp1ier~ The
fuel oil, thought to have a sulfur content of 0.96, was tested
and found to have a sulfur content of 1.07. About 35,000 gallons of
#2 fuel oil was obtained during this time. Petitioner plans to
start its boilers on #2 fuel oil (low sulfur) and then switch to
the #6 fuel oil when sufficient heat has been applied to the more
viscous #6 oil to allow a smooth flow to the boilers (R. 17).
10
—
530
—3—
Once the plant achieves maximum capacity, approximately 5
million gallons of fuel oil will be required annually (R. 10).
A commitment for an additional 1 million gallons from the local
supplier has been obtained (R. 15) and should last through the
startup phase or until early fall of 1974. Sulfur content of
the additional fuel was not revealed in the record.
Petitioner has already obtained preliminary cost figures
for its proposed flue gas desulfurization system. William Lang,
Manager of Chemical Engineering and Chairman of the Corporate
Environmental Control Committee, testified that the Chemical
Construction Corporation roughly estimated $1.1 million as the
construction cost of the proposed system (R. 36). The system
wou~Erequire about 24 months for construction.
General Tire has
investigated the feasibility of constructing
additional facilities at Mt. Vernon to remove the sulfur from high
sulfur fuel oil prior to burning and is now investigating the
possibility of gaining proprietary access to low sulfur fuel oil
by investing money in an oil refinery (R. 44).
Robert J. Schreiher, Jr., an Agency engineer, testified that
Petitioner’s sulfur dioxide emissions would be about 3,388 lbs.
per day if the plant were operating in compliance with the Regu-
lations. He estimated that the burning of 1.07 sulfur fuel oil
would add an additional 372 lbs. of sulfur dioxide per day over
the allowable rate. Schreiber testified that there were no large
(5,000 lbs./day) sulfur dioxide emission sources in the Mt. Vernon
area presently. Schreiber also testified that it was his opinion
that the sulfur dioxide emissions from the plant would not pose
any serious health hazard for the area (R. 54). If fuel with a
higher sulfur content is ultimately used, of course the sulfur
dioxide emissions would be higher.
We believe Petitioner has proven’its need for a variance.
The attempt to secure adequate supplies of low sulfur fuel oil
was exhaustive and fruitless. Time will be needed to obtain a
low sulfur fuel supply or install flue gas desulfurization equipment.
By using present fuel oil supplies Petitioner will add about 10
more sulfur dioxide to the Mt. Vernon atmosphere than the Company
would emit if it were operating in compliance, but the Agency does
not believe this quantity of additional emissions will create any
serious health hazards in the area. Petitioner has indicated that
it is willing to comply with the conditions requested by the Agency.
General Tire has invested $40 million in an area which needs
the stimulus of industry. Ultimately Petitioner will employ 450
to 1,000 persons. The Company has expended a great deal of effort
in its attempt to comply with the Regulations. It has committed
itself to the installation of sulfur dioxide control equipment in
10—531
—4—
the event it is unable to secure contracts for adequate supplies
of low sulfur fuel oil. From the record we believe that the
Company will continue with its efforts until compliance is achieved.
The variance will be granted subject to those conditions suggested
by the Agency.
ORDER
It is the Order of the Pollution Control Board that:
General Tire and Rubber Company be granted a variance
from Rule 204 of the Illinois Air Pollution Control
Regulations for its Mt. Vernon tire plant until
December 20, 1974. The variance is subject to the
following conditions:
a) Petitioner shall continue good faith negotiations
for securing an adequate supply of low sulfur fuel
oil and immediately use such oil upon its avail-
ability regardless of any other date set forth in
this order.
b) Petitioner shall submit quarterly progress reports
to the Environmental Protection Agency.
Said
progress reports shall commence on January 15, 1974
and shall provide details on the characteristics
and usage of fuel oil, progress in choosing a
control option, and negotiations for long term
contracts guaranteeing an adequate supply of low
sulfur fuel oil.
c) Petitioner shall reapply to the Board for any
extension of this variance by September 20, 1974
if compliance with Rule 204 of the Air Pollution
Control Regulations has not been achieved by that
date.
I, Christan L. Moffett, Clerk of the Illinois Pollution Control
Board, hereby certify the above Opinion and Order was adopted
this
.3~
day ~
,
1974 by a vote of ~ to
O_.
10
—
532