OLIN CORPORATION
)
)
)
)
v.
)
PCB 73-82
)
)
ENVIRONMENTAL PROTECTION AGENCY
)
)
ORDER OF THE BOARD (by Mr. Dumelle):
Motion filed by Olin Corporation on August 31, 1973 for
approval of Project Completion Schedule pursuant to further
variance is denied. Leave is given to file an amended petition
in a variance proceeding.
If it is the desire of the petitioner that the same August 31, 1973
filing date be utilized for the amended petition then a waiver shall
be executed for the period between that date and the date of this
order, relieving the Board of the necessity for a decision within
the 90-day period.
IT IS SO ORDERED.
I, Christan L. Moffett, Clerk of the Illinois Pollution Control
Board, hereby certify the above Order was adopted on the
f~”,
day
of October, 1973 by a vote of ~-O
CQ&nL.M~~?j~