ILLINOIS~POLLUTION CONTROL BOARD
June 14, 1973
)
GENERAL ELECTRIC COMPANY
v.
)
PCB 73-80
)
)
ENVIRONMENTAL PROTECTION AGENCY
)
)
OPINION AND ORDFR OF THE BOARD (by Mr. Dumelle)
This is a petition for variance requesting relief from Rule 203
of the Air Regulations. Heariiig was held on April 20, 1973.
Petitioner operates a synthetic paint system at its plant in
Chicago Heights. They filed an operating
permit
application with the
Agency in December, 1972 which was declined because the compliance
dates would not be met. The particulate emissions emanate from the
water-wall spray booth and the bake oven. The booth serves to capture
the over spray which occurs when finish coatings are applied to
various water cooler and food service equipment parts. Efficiency
of particulate capture is stated by the company to be 90.
The allowable particulate
emissions for the booth and oven
under Rule 203(a) are 0.360 pounds/hour. Petitioner has calculated
its total emissions at 1.01 pounds/hour. The Agency has not
observed any visible emissions or odors coming from the facility
nox h*s it received any citizen complaints concerning the plant.
Petitioner has submitted a compliance schedule which provides
for stack testing, engineering evaluation, bidding, construction,
equipment performance tests, shakedown, and additional stack tests
to determine compliance. They also plan to change the paint solvent
to eliminate the use of photochemically reactive materials. They
expect to complete their program by December 31, 1973 with an outside
date of February 1, 1974.
The Agency believes that petitioner’s timetable for completion
of its compliance program is reasonable and therefore recommends
that the variance be granted subject to certain conditions which we
will adopt.in substance.
This opinion constitutes the Board’s findings of fact and
conclusions of law.
8
—
277
-2-
ORDER
General Electric is granted a variance from Rule 203 of the
Air Regulations to February 1, 1974 subject to the following
conditions:
1) That stack tests be performed on the spray paint booth
and baking ovens no later than August 15., 1973, to determine
the level of particulate emissions being emitted while
using solvents that enable Petitioner to comply with the
provisions of Rule 205(f). Results of such stack tests,
and any further tests performed by General Electric to
determine compliance with emission limitation, shall be
submitted to the Agency no later than 30 days after
completion of said tests.
2) That Petitioner shall submit progress reports to the
Agency every other month commencing two months from the
date of the grant of variance, Reports shall be sent
to the Agency at the following address:
State of Illinois
Environmental Protection Agency
Division of Air Pollution Control
2200 Churchill Road
Springfield, Illinois 62706
Attention: Robert Goldberg, Manager
Variance Section
I, Christan L. Moffett, Clerk of the Illinois Pollution Control
Board, hereby certify the above Opinion and Order were adopted on the
j~~~dayof June,
1973
by a vote of
_______________________
Illinois
Pollution