ILLINOIS POLLUTION CONTROL BOARD
    January 30, 1973
    MONTEBELLO MANOR CORP.
    v.
    )
    PCB 72—429
    ENVIRONMENTAL PROTECTION AGENCY
    OPINION AND ORDER OF THE BOARD (by Mr. Dumelle):
    This is a petition for variance to allow connection to a
    sanitary sewer in the
    City
    of Hamilton. Hearing was held on
    December 27, 1972. Petitioner, a closely held corporation
    consisting of three individual shareholders, has undertaken
    the building of a nursing care facility for the residents of
    Hamilton, Hancock and surrounding counties. There is no other
    such facility in Hamilton. The facility will contain eighty-
    two beds and would discharge approximately 8,200 gallons of
    waste water per day containing 15 pounds BOD. Around sixty of
    these beds will be taken by current Hamilton residents, thus
    providing for a net increase of only twenty persons to the
    sewage system.
    The total cost of the facility is $585,000. Petitioner’s
    president has advanced $50,000 of his personal assets and his
    two associates have advanced $30,000 and $20,000 each toward the
    project. In addition, a loan in the amount of $454,000 has been
    approved by a Springfield bank. As of October 1, 1972, $170,000
    of that loan was advanced at 8-1/4 interest with an additional
    $50,000 being advanced as of November 1, 1972. They have also
    borrowed another $20,000 at 7-1/2 interest from a bank in
    Hamilton. Should the variance be denied they would suffer a
    loss of $300,000 to $400,000.
    Petitioner applied to the Agency on August 10, 1972 for a
    permit to connect up to the sanitary sewer. The Agency denied the
    permit on September 1, 1972. The reason for the denial was
    because the Hamilton Sewage Treatment Plant does not have ade-
    quate capacity to accept any additional waste load. The plant
    was designed to serve 1,640 persons at a design flow of 164,000
    gallons per day. The plant presently serves around 2,488 persons
    with an average flow of 270,000 gallons per day. The plant
    provides primary settling treatment only with bar screens, sludge
    digestion and sludge drying beds. Plans and specifications for
    upgrading the plant were approved by the Agency on August 31, 1972.
    The City is attempting to obtain federal clearance essential for
    both federal and state grant funds but has a low priority rating
    6
    667

    ———.-~u~
    jt~c~LL
    ~~iiy
    could be arranged, the earliest
    completion date for the plant would be around July, 1974.
    The Hamilton plant discharges to the open Hamilton Slough
    which drains into the Mississippi River. The plant is currently
    discharging an effluent which on October 30, 1972, measured
    600 mg/i BOD, 110 mg/i suspended solids and 7,900,000/100 mg/i
    fecal coiiforrn. Other BOD values have been recorded at 420 and
    180 mg/i.
    The petitioner entered into construction contracts around
    February, 1972 with actual construction beginning around April.
    The Water Regulations requiring permits were adopted by the
    Board in March, 1972. It appears, then, that the obligations
    were entered into with the full expectancy that the sewer con-
    nection would be forthcoming~
    The Agency indicates that while the granting of this petition
    would permit some increase in the pollution load to Hamilton
    Slough and then to the Mississippi River, it would not be expected
    to noticeably change the present outfall conditions in the
    Slough. The Agency also indicates that the increase would not
    likely alter the biota and fish life measurably and also that
    due to the Mississippi River dilution ratio, the increase would
    not be expected to make a measurable difference in the quality
    of river water entering the intake of the Warsaw Public Water
    Supply which is six miles downstream from the Hamilton discharge.
    Based upon the facts and the Agency’s recommendation we will
    grant the variance. The need for this nursing care facility
    outweighs the harm which will
    occur as a
    result of the additional
    discharge volume. We should note, however, that we are far more
    persuaded in this case by the fact that a nursing facility (the
    only one in Hamilton), is involved than by its financial aspects.
    If the proposed facility were not intended for the general benefit
    of the community our decision may well have been different.
    This opinion constitutes the Board1s findings of fact and
    conclusions of law.
    ORDER
    The Petition for Variance is granted. Petitioner shall be
    allowed to connect up to the Hamilton sewer system in conformity
    with all applicable laws and regulations except as excused by
    this variance.
    I, Christan L. Moffett, Clerk of the Pollution Control Board,
    certify tiat the Board adopted the above Opinion and Order this
    ~
    day of
    ______________,
    1973, by a vote of
    3
    to ~
    __
    ~ ~
    —2—
    6
    668

    Back to top