ILLINOIS POLIJUTION CONTROL BOARD
    October 10, 1972
    COMMONWEALTH EDISON COMPANY
    (Dresden Fnit #3)
    PCB 72-350
    ENVIRONMENTAL PROTECTION AGENCY
    INTERIM OPINION & ORDER OF THE BOARD (by Mr. Dumelle)
    This is a petition for a one-year extension of the variance granted to
    Edison on November 23, 1971 (PCB 70-21) from the thermal standards outside
    of the applicable mixing zone on the Illinois River. That variance, by its
    own terms, will expire on November 23, 1972.
    We find it necessary to conduct a public hearing on this new petition
    in order to fully comprehend the current
    situation. Among
    other
    issues,
    we would like to have more information on: the extent of the need for
    Dresden power in view of the recent Quad-Cities plant startup; the degree
    of improved water quality in this reach of the Illinois River as a result
    of improved treatment upstream by both the GAF Corporation and the
    Metropolitan Sanitary District of Greater Chicago; and the degree to which
    the river diffuser acts as a barrier to the passage of fish.
    The variance granted on November 23, 1971 is hereby extended for
    sixty (60) days (January 22, 1973) on the condition that Edison files, by
    November 1, 1972, a written waiver of the right to a final decision within
    90 days from the filing date of the pending petition.
    IT IS SO ORDERED.
    I, Christan L. Moffett, Clerk of the Illinois Pollution Control Board, L
    hereby certify the above Interim Opinion & Order were adopted on the
    ~.
    day of October, 1972 by a vote of
    ~
    ~
    L~\
    7) )
    .~Y
    ~.
    Christan L. Moffett, Cle~k’
    Illinois Pollution Control Board