ILLINOIS POLLUTION CONTROL BOARD
    March 15, 1973
    CITY OF DANVILLE,
    Petitioner,
    vs.
    )
    PCB 72—335
    ENVIRONMENTAL PROTECTION AGENCY,
    Respondent.
    Larry Lessen, Attorney for Petitioner
    Delbert Haschemeyer, Assistant Attorney General for the EPA
    OPINION AND ORDER OF THE BOARD (by Mr. Henss)
    Petitioner City of Danville makes several requests for
    variance in the operation of its landfill. The principal
    request is for extension of a variance we granted in PCB 71—282
    allowing Petitioner a six month period ending June 9, 1972 to
    apply final cover to a portion of its landfill known as the
    ~old site”. The entire tract consists of 56 acres. Thirty—one
    acres previously used as a landfill (the old site), have been
    closed since April 23, 1971. Fifteen acres not previously used
    (the new site) have been developed for landfill operations more
    recently under a contract the City obtained with H & L Disposal
    Company.
    In 1971 the City of Danville represented that immediate
    close out and covering of the old 31 acre site would cost $89,000
    whereas the program contemplated by them for the application of
    cover within a period of six months would be accomplished without
    any additional cost to the City. The record in 1971 indicated
    that leachate emanating from the old landfill area ultimately
    entered the Vermilion River but under all of the circumstances
    we felt the six month time schedule for the application of final
    cover was reasonable.
    In August 1972, one month after the variance had expired,
    the City of Danville filed its petition requesting extension.
    Subsequently, the Petitioner filed an amended petition and waived
    the requirement that ruling be made by the Board within 90 days.
    7
    28
    7

    2—
    Petitioner contends that the failure tc meet the original
    June 9, 1972 deadline was due to exceptionally wet weather, a
    breakdown in “internal communications” and a 25 day strike by
    municipal employees in May 1972.
    Our conclusion from a review of the record.. however, is
    that Danville simply did not make a serious effort to meet the
    six month deadline. Rainfall during May 1972 was 2.36 inches
    less than normal.
    During that month H & L Disooaal Company
    did not apply final cover at the old site recaure
    it was allo
    cating all of its efforts to
    the
    oneration of the
    new
    15
    acre
    landfill
    site.
    The toLal rainfall
    for May, dune, July and
    August 1972 actually war slightly
    less than normal.
    The
    ~internal
    communieati~nn” problem of the riunicinafity
    and a
    25
    day
    strike by municipal employees woo
    were
    not involred in
    the landfill
    oneration could hardly constitute
    ~uatification
    for
    a one year delay in meeting the Standard,
    The City
    o:
    Danvillo has applied f~na1
    co or
    tr~
    ‘uch
    ().~
    the
    area
    hut should take immediate
    steps
    to coepl:
    te tn
    ore ject.
    Petitioner contends that denial of the variance
    eaLensien
    would
    impose
    ar
    unreasonable
    and arbLtrar\’ hards~ir, unon the Cit,
    because of the estimated $9,000 cost of
    cc’rinc into corel
    lance
    immediately.
    We regard this as a self~ir o~od ha~dm1:: nince
    the municipality
    has failed to oursue that coui:e
    ehich
    it
    earlier represented would bring it into cc
    lianee dun ine
    1972.
    According to the record the necessary additional
    Tranpc) or and
    esuioment was not made available until September
    1972.
    (P.
    16, 68)
    We
    deny the request to extend the variance.
    Other requests by the Petitioner,
    however, ,v 1
    Li a
    Loed.
    The EPA recommends that Petitioner
    and
    the
    H
    &
    D~sposa~ Coopan’~
    be nermitted
    to
    take those steps outlined in a ;uppielTlentai
    permit granted by the Agency on October 2L1,
    1972 which modify the
    planned use of the 56 acre tract.
    This modification
    i.~ partly
    due
    to
    earlier error in mapping the site.
    The Petitioner
    and
    the
    Acency have reached agreement on specific chan’os
    regarding
    trenching
    and the
    filling of low areas and ravines, and these agreements
    will he incorporated in the Order.
    ORDER
    It is ordered that:
    1. Petitioner’s request for a variance extension of
    one year for the murpose of applying final cover
    to the “old site~ 31 acre tract is denied.
    Petitioner’s request for a variance is allowed
    to the following extent:
    7
    288

    o) ‘lime ~P/\
    supplemental permit of October 24, 1972
    is aeprovee
    and the au~horizations incorporated
    therein are included as a part of the variance.
    h.
    PetItioner
    shall he permitted to excavate a
    drainage ditch through the southwest corner
    of the otd landfill
    site.
    Upon completion of
    water drainage, Petitioner
    will fill the
    drainage to grade level only with proper landfill
    co~cr material.
    Petitioner will be permitted to
    fill in low spots at the old landfill
    site with
    an accumulation of burned and exposed refuse
    materia.l which is then to receive proper final
    cover.
    The area presently containing the burned
    and
    exoosed refuse is to be properly graded and
    is not to be used for refuse disposal.
    Petitioner
    will be permitted to fill in a ravine located at
    the old landfill site but only with proper final
    cover material.
    I, Christan L. Moffett, Clerk of the Illinois Pollution Control
    Board, hereby certify the above Opinion and Order was adopted
    this
    /4~
    dayof March, 1973 by a vote of _____to
    0
    7
    289

    I

    Back to top