ILLINOIS POLLUTION CONTROL BOARD
    September 6, 1972
    RICHARDSON CO.
    )
    V.
    )
    ##72—41,72—l44
    3
    ENVIRONMENTAL PROTECTION AGENCY
    Mr. Douglas T. Moring, Assistant Attorney General, for
    Environmental Protection Agency
    Mr. Alan Abrams, for the Richardson Co.
    Opinion of the Board (by Mr. Currie)
    Richardson applied to us for a variance to permit
    continued operation of its ~henolic laminate plant in DeKalb
    until December, 1972 while completing an emission control
    program approved by our predecessor the Air Pollution Control
    Board. We granted the variance only until September 9 be-
    cause of doubts as to whether the company should have
    accelerated the purchase of the last incineration equipnent, requir-
    ed by the program, expressly inviting further proceedings in which
    if our doubts were answered the variance could be extended
    to December. Richardson Co. v. EPA, #72—41 (May 3, 1972).
    The Agency had in the meantime filed a complaint against
    the company alleging particulate violation
    (#
    72-14 4)
    ,
    the
    company filed a request for extensionof the variance, the
    two matters were consolidated, and a hearing was held.
    The original compliance program contemplated installation
    of afterburners to reduce solvent and other emissions from
    phenolic laminate treaters. The first unit was installed but
    proved defective (see Stipulation, p. 4)
    .
    The initial
    variance petition contemplated the rebuilding of the defective
    unit by July 1972, which has since been accomplished (id.,
    p. 7)
    ,
    and the ordering of the remaining equipment in time
    for completion by the end of 1972 “if granted sufficient time.”
    We indicated that this seemed to imply that Richardson was
    delaying in curing its pollution problems until it obtained
    a variance and made clear that this would be no excuse.
    We asked for an explanation of why the equipment was not
    ordered earlier.
    The record does indicate that Richardson was motivated
    at least in part by the desire to get approval of continued
    operation before making the necessary commitments to clean
    up (R. 30). To the extent that such was the case, it does
    5
    345

    —2—
    not represent diligent action to abate pollution as rapidly
    as is practicable as the law requires. We appreciate the
    company’s reluctance to spend substantial sums only to dis-
    cover later that it must shut down its plant and make the
    expenditures in vain. But such a prospect misconceives
    what actually happens when variances are denied. The in-
    stances in which this Board has ordered going businesses
    closed for polluting are few indeed; the almost invariable
    practice, in the absence of a most considerable nuisance or
    health hazard or utter disregard of the law, is to leave
    the petitioner open to money penalties commensurate with the
    seriousness of the delay but to permit continued operation.
    See, e.g., Marquette Cement Mfg. Co. v. EPA, *70-23 (Jan.
    6, 1971). We emphasize once more that we expect those who
    petition for variances approving deferred compliance to
    proceed posthaste, as many have done, see, e.g., A.E. Staley
    Mfg. Co. v. EPA, #71-174 (Sept. 30, 1971), to achieve com-
    pliance as soon as possible while their petition for variance
    is being considered.
    We find, however, that in the present case the delay was
    to a significant extent mitigated by the company’s legitimate
    concern that the bugs should be taken out of the first
    incinerator before substantial sums were committed for the
    purchase of more of the same equipment (R. 39—42). The
    timetable Richardson was following, moreover, was such as
    to achieve compliance, despite the delay, within the period
    approved by the predecessor Board. (See Exs. 7, Il)
    Finally, the remaining equipment was promptly ordered upon
    entry of our earlier order (R. 42)
    .
    Under these facts we
    think no great purpose would be served by requiring the
    payment of a penalty for this relatively brief delay or by
    leaving the company open to a further prosecution on that
    account. The variance will therefore be extended to
    December 1972, the earliest date on which the program can
    now be completed (R. 51-52).
    The Agency’s complaint is based upon a different matter.
    Agency evidence brought out, and the company conceded, that
    the incinerators as presently designed will control emissions
    only from the curing ovens and not from other sources such
    as dip trays and recirculation tanks, from which the evidence
    is clear certain gaseous contaminants are emitted. (R. 18—19,
    42-43, Ex. 28). The Agency asks us to require control of
    these sources as well. The company responds that from
    preliminary sniffing at vents on the roof it believes
    these emissions will not independently cause any odor problem
    but declares itself willing and able to connect these sources
    to the incinerators if a problem should be found to exist in
    lhe future (R. 42-43). Ascertaining whether or not there
    will be such a problem is complicated by the fact that the
    more obvious oven emissions have not yet all been brought
    under control.
    5
    346

    —3—
    The principal difficulty with the Agency’s case is that
    the only violation charged is under the process weight table
    of Rule 3—3.111 of the old air regulations, which expressly
    applies only to particulate emissions. The evidence is that
    the only particulate emissions from the plant come from the
    curing ovens (Ex. 28)
    ,
    which are covered by the company’s
    existing program. Emissions from the dip trays and re-
    circulating tanks, so far as the evidence shows, are entire-
    ly of gaseous solvents (Id.) and therefore not covered by
    the rule in question. There was no allegation ‘of statutory
    air pollution, and indeed no adequate proof that existing
    odors were caused even in part by these sources rather
    than by the ovens themselves (R. 21). But the basic princi-
    ple that governs here is that the Agency may not allege one
    violation and prove another, for to do so deprives the res-
    pondent of the notice indispensable to a meaningful oppor-
    tunity to defend. See EPA v. McHugh, Healy & Keeny Con-
    struction Co. & City of Chicago, (# 71—291) (May 17, 1972).
    We therefore find the EPA has failed to prove any violation it
    has alleged.
    The evidence does establish, however, that there are possibly
    significant odor sources within the plant that are not be-
    ing controlled by the present program, even though the
    original compliance program (See Ex. 3) did indicate an
    intention to deal with emissions from the “coating head
    and oven combination.” We think it appropriate, therefore,
    to ma’Ke it a condition of the variance that the Intent of
    the original program be carried out insofar as is necessary
    to prevent an odor nuisance. If such a nuisance continues
    to exist as a result of other sources after the ovens are
    fully controlled, the company will be required to connect
    those sources expeditiously to the afterburners and to take
    any other steps necessary to eliminate the problem. Cf.
    Greenlee Foundries v. EPA, #70-33 (March 17, 1971).
    ORDER
    1. The complaint in #72—144 is hereby dismissed for want
    of proof of the violation alleged.
    2. The variance granted to Richardson Co. (#72-41) May 3,
    1972 is hereby extended to December 31, 1972, subject
    to all conditions
    of the order of May 3, 1972 and to the
    following additional condition:
    3. In the event that an odor problem continues to exist
    after completion of the installation of afterburners on
    the curing ovens, Richardson shall expeditiously take
    such steps as are necessary and practicable to abate
    such problem, including the duct~ing of emissions from
    the dip trays and recirculating tanks to the afterburners.
    5
    347

    —4—
    I, Christan Moffett, Clerk of the Pollution Control Board,
    certify that the Board adopted the above Opinion this
    __________day of September,
    1972, by a vote of
    d/_C~
    4’
    7/
    5
    348

    Back to top